PMI PMI-SP Exam (page: 4)
PMI -SP Scheduling Professional
Updated on: 12-Jan-2026

Viewing Page 4 of 67

Sam is the project manager of the NQQ project. He and the project team have completed the stakeholder identification process for his project.
What is the main output of the identify stakeholders process?

  1. Communications management plan
  2. Stakeholder register
  3. Requirements
  4. Stakeholder management strategy

Answer(s): B

Explanation:

According to the PMBOK, the main output of the identify stakeholders process is the stakeholder register. The stakeholder register is a project management document that contains a list of the stakeholders associated with the project. It assesses how they are involved in the project and identifies what role they play in the organization. The information in this document can be very perceptive and is meant for limited exchange only. It also contains relevant information about the stakeholders, such as their requirements, expectations, and influence on the project.
Answer option A is incorrect. The communications management plan is an output of communications planning.
Answer option D is incorrect. The stakeholder management strategy is an output of stakeholder identification, but it is not the main output.
Answer option C is incorrect. Requirements are not an output of the stakeholder identification process.



You work as a project manager for BlueWell Inc. Management has asked you not to communicate performance unless the CPI is less than 0.96 or the SPI dips below 0.98.
What type of report would you create for management, if these instances develop in your project?

  1. Cost variance report
  2. Exceptions report
  3. Performance management report
  4. Schedule variance report

Answer(s): B

Explanation:

The best answer is simply an exception report.

An exception report refers and documents the major mistakes, mishaps, and goofs. In other words, it itemizes the important and critically significant piece of documentation that is vital to the proper and effective functioning of a project. It does not document what has gone right, but rather documents what has gone wrong.
Answer option C is incorrect. A performance management report is not a valid project management report.
Answer option A is incorrect. The question is asked a out cost and schedule so this answer would not be appropriate for both the cost and the schedule.
Answer option D is incorrect. The question is asked about cost and schedule so this answer would not be appropriate for both the cost and the schedule.



You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned. Considering that the project has a BAC of $567,899, you are thirty percent complete, and you have spent $179,450.
What is this project's to- complete performance index based on the current BAC?

  1. 1.02
  2. 0.010
  3. 0.75
  4. 0.95

Answer(s): A

Explanation:

This project is not performing well on schedule, but moderately well on costs. The project's TCPI based on the current BAC is 1.02. To-complete Performance Index (TCPI) is the measured projection of the anticipated performance required to achieve either the BAC or the EAC. TCPI indicates the future required cost efficiency needed to achieve a target EAC (Estimate At Complete).Once approved, the EAC supersedes the BAC as the cost performance goal. Any significant difference between TCPI and the CPI needed to meet the EAC should be accounted for by management in their forecast of the final cost. The formula for TCPI is as follows: TCPI = {(BAC- EV)/(BAC-AC)}
Answer option D is incorrect. 0.95 is the project's TCPI value based on the estimate at completion.
Answer option C is incorrect. 0.75 is the project's schedule performance index.
Answer option B is incorrect. 0.010 is not a valid calculation.



Andy works as the project manager for Bluewell Inc. He is developing the schedule for the project. There are eight tools and techniques that a project manager can use to develop the project schedule.
Which of the following is a tool and technique for the Schedule Development process?

  1. Schedule compression
  2. Reserve analysis
  3. Variance analysis
  4. Expert judgment

Answer(s): A

Explanation:

Schedule compression is a tool used as part of the Schedule Development process. The tools and techniques for schedule development are as follows: Schedule network analysis Critical path method Critical chain method Resource leveling What-if scenario analysis Applying leads and lags Schedule compression Scheduling tool Answer options D, B, and C are incorrect. These are not tools and techniques for schedule development.



You are the project manager for your organization. You have recorded the following duration estimates for an activity in your project: optimistic 20, most likely 45, pessimistic 90.
What time will you record for this activity?

  1. 48
  2. 20o, 45m, 90p
  3. 90
  4. 45

Answer(s): A

Explanation:

This is an example of a three-point estimate. A three-point estimate records the optimistic, most likely, and the pessimistic duration, and then records an average for the predicted duration Three- point estimate is a way to enhance the accuracy of activity duration estimates. This concept is originated with the Program Evaluation and Review Technique (PERT). PERT charts the following three estimates:

Most likely (TM): The duration of activity based on realistic factors such as resources assigned, interruptions, etc. Optimistic (TO): The activity duration based on the best-case scenario Pessimistic (TP): The activity duration based on the worst-case scenario The expected (TE) activity duration is a weighted average of these three estimates: TE = (TO + 4TM + TP) / 6 Duration estimates based on the above equations (sometimes simple average of the three estimates is also used) provide more accuracy. It can be calculated as follows: TE = ( 20 + 45*4 + 90) / 6 = 290/6 =48 Answer options B, C, and D are incorrect. These are not the valid answers for this question.



Viewing Page 4 of 67



Share your comments for PMI PMI-SP exam with other users:

1 10/28/2023 7:32:00 AM

great sharing
Anonymous


Anand 1/20/2024 10:36:00 AM

very helpful
UNITED STATES


Kumar 6/23/2023 1:07:00 PM

thanks.. very helpful
FRANCE


User random 11/15/2023 3:01:00 AM

i registered for 1z0-1047-23 but dumps qre available for 1z0-1047-22. help me with this...
UNITED STATES


kk 1/17/2024 3:00:00 PM

very helpful
UNITED STATES


Raj 7/24/2023 10:20:00 AM

please upload oracle 1z0-1110-22 exam pdf
INDIA


Blessious Phiri 8/13/2023 11:58:00 AM

becoming interesting on the logical part of the cdbs and pdbs
Anonymous


LOL what a joke 9/10/2023 9:09:00 AM

some of the answers are incorrect, i would be wary of using this until an admin goes back and reviews all the answers
UNITED STATES


Muhammad Rawish Siddiqui 12/9/2023 7:40:00 AM

question # 267: federated operating model is also correct.
SAUDI ARABIA


Mayar 9/22/2023 4:58:00 AM

its helpful alot.
Anonymous


Sandeep 7/25/2022 11:58:00 PM

the questiosn from this braindumps are same as in the real exam. my passing mark was 84%.
INDIA


Eman Sawalha 6/10/2023 6:09:00 AM

it is an exam that measures your understanding of cloud computing resources provided by aws. these resources are aligned under 6 categories: storage, compute, database, infrastructure, pricing and network. with all of the services and typees of services under each category
GREECE


Mars 11/16/2023 1:53:00 AM

good and very useful
TAIWAN PROVINCE OF CHINA


ronaldo7 10/24/2023 5:34:00 AM

i cleared the az-104 exam by scoring 930/1000 on the exam. it was all possible due to this platform as it provides premium quality service. thank you!
UNITED STATES


Palash Ghosh 9/11/2023 8:30:00 AM

easy questions
Anonymous


Noor 10/2/2023 7:48:00 AM

could you please upload ad0-127 dumps
INDIA


Kotesh 7/27/2023 2:30:00 AM

good content
Anonymous


Biswa 11/20/2023 9:07:00 AM

understanding about joins
Anonymous


Jimmy Lopez 8/25/2023 10:19:00 AM

please upload oracle cloud infrastructure 2023 foundations associate exam braindumps. thank you.
Anonymous


Lily 4/24/2023 10:50:00 PM

questions made studying easy and enjoyable, passed on the first try!
UNITED STATES


John 8/7/2023 12:12:00 AM

has anyone recently attended safe 6.0 exam? did you see any questions from here?
Anonymous


Big Dog 6/24/2023 4:47:00 PM

question 13 should be dhcp option 43, right?
UNITED STATES


B.Khan 4/19/2022 9:43:00 PM

the buy 1 get 1 is a great deal. so far i have only gone over exam. it looks promissing. i report back once i write my exam.
INDIA


Ganesh 12/24/2023 11:56:00 PM

is this dump good
Anonymous


Albin 10/13/2023 12:37:00 AM

good ................
EUROPEAN UNION


Passed 1/16/2022 9:40:00 AM

passed
GERMANY


Harsh 6/12/2023 1:43:00 PM

yes going good
Anonymous


Salesforce consultant 1/2/2024 1:32:00 PM

good questions for practice
FRANCE


Ridima 9/12/2023 4:18:00 AM

need dump and sap notes for c_s4cpr_2308 - sap certified application associate - sap s/4hana cloud, public edition - sourcing and procurement
Anonymous


Tanvi Rajput 10/6/2023 6:50:00 AM

question 11: d i personally feel some answers are wrong.
UNITED KINGDOM


Anil 7/18/2023 9:38:00 AM

nice questions
Anonymous


Chris 8/26/2023 1:10:00 AM

looking for c1000-158: ibm cloud technical advocate v4 questions
Anonymous


sachin 6/27/2023 1:22:00 PM

can you share the pdf
Anonymous


Blessious Phiri 8/13/2023 10:26:00 AM

admin ii is real technical stuff
Anonymous