PMI PMI-SP Exam (page: 4)
PMI -SP Scheduling Professional
Updated on: 28-Jul-2025

Viewing Page 4 of 67

Sam is the project manager of the NQQ project. He and the project team have completed the stakeholder identification process for his project.
What is the main output of the identify stakeholders process?

  1. Communications management plan
  2. Stakeholder register
  3. Requirements
  4. Stakeholder management strategy

Answer(s): B

Explanation:

According to the PMBOK, the main output of the identify stakeholders process is the stakeholder register. The stakeholder register is a project management document that contains a list of the stakeholders associated with the project. It assesses how they are involved in the project and identifies what role they play in the organization. The information in this document can be very perceptive and is meant for limited exchange only. It also contains relevant information about the stakeholders, such as their requirements, expectations, and influence on the project.
Answer option A is incorrect. The communications management plan is an output of communications planning.
Answer option D is incorrect. The stakeholder management strategy is an output of stakeholder identification, but it is not the main output.
Answer option C is incorrect. Requirements are not an output of the stakeholder identification process.



You work as a project manager for BlueWell Inc. Management has asked you not to communicate performance unless the CPI is less than 0.96 or the SPI dips below 0.98.
What type of report would you create for management, if these instances develop in your project?

  1. Cost variance report
  2. Exceptions report
  3. Performance management report
  4. Schedule variance report

Answer(s): B

Explanation:

The best answer is simply an exception report.

An exception report refers and documents the major mistakes, mishaps, and goofs. In other words, it itemizes the important and critically significant piece of documentation that is vital to the proper and effective functioning of a project. It does not document what has gone right, but rather documents what has gone wrong.
Answer option C is incorrect. A performance management report is not a valid project management report.
Answer option A is incorrect. The question is asked a out cost and schedule so this answer would not be appropriate for both the cost and the schedule.
Answer option D is incorrect. The question is asked about cost and schedule so this answer would not be appropriate for both the cost and the schedule.



You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned. Considering that the project has a BAC of $567,899, you are thirty percent complete, and you have spent $179,450.
What is this project's to- complete performance index based on the current BAC?

  1. 1.02
  2. 0.010
  3. 0.75
  4. 0.95

Answer(s): A

Explanation:

This project is not performing well on schedule, but moderately well on costs. The project's TCPI based on the current BAC is 1.02. To-complete Performance Index (TCPI) is the measured projection of the anticipated performance required to achieve either the BAC or the EAC. TCPI indicates the future required cost efficiency needed to achieve a target EAC (Estimate At Complete).Once approved, the EAC supersedes the BAC as the cost performance goal. Any significant difference between TCPI and the CPI needed to meet the EAC should be accounted for by management in their forecast of the final cost. The formula for TCPI is as follows: TCPI = {(BAC- EV)/(BAC-AC)}
Answer option D is incorrect. 0.95 is the project's TCPI value based on the estimate at completion.
Answer option C is incorrect. 0.75 is the project's schedule performance index.
Answer option B is incorrect. 0.010 is not a valid calculation.



Andy works as the project manager for Bluewell Inc. He is developing the schedule for the project. There are eight tools and techniques that a project manager can use to develop the project schedule.
Which of the following is a tool and technique for the Schedule Development process?

  1. Schedule compression
  2. Reserve analysis
  3. Variance analysis
  4. Expert judgment

Answer(s): A

Explanation:

Schedule compression is a tool used as part of the Schedule Development process. The tools and techniques for schedule development are as follows: Schedule network analysis Critical path method Critical chain method Resource leveling What-if scenario analysis Applying leads and lags Schedule compression Scheduling tool Answer options D, B, and C are incorrect. These are not tools and techniques for schedule development.



You are the project manager for your organization. You have recorded the following duration estimates for an activity in your project: optimistic 20, most likely 45, pessimistic 90.
What time will you record for this activity?

  1. 48
  2. 20o, 45m, 90p
  3. 90
  4. 45

Answer(s): A

Explanation:

This is an example of a three-point estimate. A three-point estimate records the optimistic, most likely, and the pessimistic duration, and then records an average for the predicted duration Three- point estimate is a way to enhance the accuracy of activity duration estimates. This concept is originated with the Program Evaluation and Review Technique (PERT). PERT charts the following three estimates:

Most likely (TM): The duration of activity based on realistic factors such as resources assigned, interruptions, etc. Optimistic (TO): The activity duration based on the best-case scenario Pessimistic (TP): The activity duration based on the worst-case scenario The expected (TE) activity duration is a weighted average of these three estimates: TE = (TO + 4TM + TP) / 6 Duration estimates based on the above equations (sometimes simple average of the three estimates is also used) provide more accuracy. It can be calculated as follows: TE = ( 20 + 45*4 + 90) / 6 = 290/6 =48 Answer options B, C, and D are incorrect. These are not the valid answers for this question.



Viewing Page 4 of 67



Share your comments for PMI PMI-SP exam with other users:

AD 10/22/2023 9:08:00 AM

3rd so far, need to cover more
Anonymous


Matt 11/18/2023 2:32:00 AM

aligns with the pecd notes
Anonymous


Sri 10/15/2023 4:38:00 PM

question 4: b securityadmin is the correct answer. https://docs.snowflake.com/en/user-guide/security-access-control-overview#access-control-framework
GERMANY


H.T.M. D 6/25/2023 2:55:00 PM

kindly please share dumps
Anonymous


Satish 11/6/2023 4:27:00 AM

it is very useful, thank you
Anonymous


Chinna 7/30/2023 8:37:00 AM

need safe rte dumps
FRANCE


1234 6/30/2023 3:40:00 AM

can you upload the cis - cpg dumps
Anonymous


Did 1/12/2024 3:01:00 AM

q6 = 1. download odt application 2. create a configuration file (xml) 3. setup.exe /download to download the installation files 4. setup.exe /configure to deploy the application
FRANCE


John 10/12/2023 12:30:00 PM

great material
Anonymous


Dinesh 8/1/2023 2:26:00 PM

could you please upload sap c_arsor_2302 questions? it will be very much helpful.
Anonymous


LBert 6/19/2023 10:23:00 AM

vraag 20c: rsa veilig voor symmtrische cryptografie? antwoord c is toch fout. rsa is voor asymmetrische cryptogafie??
NETHERLANDS


g 12/22/2023 1:51:00 PM

so far good
UNITED STATES


Milos 8/4/2023 9:33:00 AM

question 31 has obviously wrong answers. tls and ssl are used to encrypt data at transit, not at rest.
Serbia And Montenegro


Diksha 9/25/2023 2:32:00 AM

pls provide dump for 1z0-1080-23 planning exams
Anonymous


H 7/17/2023 4:28:00 AM

could you please upload the exam?
Anonymous


Anonymous 9/14/2023 4:47:00 AM

please upload this
UNITED STATES


Naveena 1/13/2024 9:55:00 AM

good material
Anonymous


WildWilly 1/19/2024 10:43:00 AM

lets see if this is good stuff...
Anonymous


Lavanya 11/2/2023 1:53:00 AM

useful information
UNITED STATES


Moussa 12/12/2023 5:52:00 AM

intéressant
BURKINA FASO


Madan 6/22/2023 9:22:00 AM

thank you for making the interactive questions
Anonymous


Vavz 11/2/2023 6:51:00 AM

questions are accurate
Anonymous


Su 11/23/2023 4:34:00 AM

i need questions/dumps for this exam.
Anonymous


LuvSN 7/16/2023 11:19:00 AM

i need this exam, when will it be uploaded
ROMANIA


Mihai 7/19/2023 12:03:00 PM

i need the dumps !
Anonymous


Wafa 11/13/2023 3:06:00 AM

very helpful
Anonymous


Alokit 7/3/2023 2:13:00 PM

good source
Anonymous


Show-Stopper 7/27/2022 11:19:00 PM

my 3rd test and passed on first try. hats off to this brain dumps site.
UNITED STATES


Michelle 6/23/2023 4:06:00 AM

please upload it
Anonymous


Lele 11/20/2023 11:55:00 AM

does anybody know if are these real exam questions?
EUROPEAN UNION


Girish Jain 10/9/2023 12:01:00 PM

are these questions similar to actual questions in the exam? because they seem to be too easy
Anonymous


Phil 12/8/2022 11:16:00 PM

i have a lot of experience but what comes in the exam is totally different from the practical day to day tasks. so i thought i would rather rely on these brain dumps rather failing the exam.
GERMANY


BV 6/8/2023 4:35:00 AM

good questions
NETHERLANDS


krishna 12/19/2023 2:05:00 AM

valied exam dumps. they were very helpful and i got a pretty good score. i am very grateful for this service and exam questions
Anonymous