PMI PMI-SP Exam (page: 4)
PMI -SP Scheduling Professional
Updated on: 02-Mar-2026

Viewing Page 4 of 67

Sam is the project manager of the NQQ project. He and the project team have completed the stakeholder identification process for his project.
What is the main output of the identify stakeholders process?

  1. Communications management plan
  2. Stakeholder register
  3. Requirements
  4. Stakeholder management strategy

Answer(s): B

Explanation:

According to the PMBOK, the main output of the identify stakeholders process is the stakeholder register. The stakeholder register is a project management document that contains a list of the stakeholders associated with the project. It assesses how they are involved in the project and identifies what role they play in the organization. The information in this document can be very perceptive and is meant for limited exchange only. It also contains relevant information about the stakeholders, such as their requirements, expectations, and influence on the project.
Answer option A is incorrect. The communications management plan is an output of communications planning.
Answer option D is incorrect. The stakeholder management strategy is an output of stakeholder identification, but it is not the main output.
Answer option C is incorrect. Requirements are not an output of the stakeholder identification process.



You work as a project manager for BlueWell Inc. Management has asked you not to communicate performance unless the CPI is less than 0.96 or the SPI dips below 0.98.
What type of report would you create for management, if these instances develop in your project?

  1. Cost variance report
  2. Exceptions report
  3. Performance management report
  4. Schedule variance report

Answer(s): B

Explanation:

The best answer is simply an exception report.

An exception report refers and documents the major mistakes, mishaps, and goofs. In other words, it itemizes the important and critically significant piece of documentation that is vital to the proper and effective functioning of a project. It does not document what has gone right, but rather documents what has gone wrong.
Answer option C is incorrect. A performance management report is not a valid project management report.
Answer option A is incorrect. The question is asked a out cost and schedule so this answer would not be appropriate for both the cost and the schedule.
Answer option D is incorrect. The question is asked about cost and schedule so this answer would not be appropriate for both the cost and the schedule.



You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned. Considering that the project has a BAC of $567,899, you are thirty percent complete, and you have spent $179,450.
What is this project's to- complete performance index based on the current BAC?

  1. 1.02
  2. 0.010
  3. 0.75
  4. 0.95

Answer(s): A

Explanation:

This project is not performing well on schedule, but moderately well on costs. The project's TCPI based on the current BAC is 1.02. To-complete Performance Index (TCPI) is the measured projection of the anticipated performance required to achieve either the BAC or the EAC. TCPI indicates the future required cost efficiency needed to achieve a target EAC (Estimate At Complete).Once approved, the EAC supersedes the BAC as the cost performance goal. Any significant difference between TCPI and the CPI needed to meet the EAC should be accounted for by management in their forecast of the final cost. The formula for TCPI is as follows: TCPI = {(BAC- EV)/(BAC-AC)}
Answer option D is incorrect. 0.95 is the project's TCPI value based on the estimate at completion.
Answer option C is incorrect. 0.75 is the project's schedule performance index.
Answer option B is incorrect. 0.010 is not a valid calculation.



Andy works as the project manager for Bluewell Inc. He is developing the schedule for the project. There are eight tools and techniques that a project manager can use to develop the project schedule.
Which of the following is a tool and technique for the Schedule Development process?

  1. Schedule compression
  2. Reserve analysis
  3. Variance analysis
  4. Expert judgment

Answer(s): A

Explanation:

Schedule compression is a tool used as part of the Schedule Development process. The tools and techniques for schedule development are as follows: Schedule network analysis Critical path method Critical chain method Resource leveling What-if scenario analysis Applying leads and lags Schedule compression Scheduling tool Answer options D, B, and C are incorrect. These are not tools and techniques for schedule development.



You are the project manager for your organization. You have recorded the following duration estimates for an activity in your project: optimistic 20, most likely 45, pessimistic 90.
What time will you record for this activity?

  1. 48
  2. 20o, 45m, 90p
  3. 90
  4. 45

Answer(s): A

Explanation:

This is an example of a three-point estimate. A three-point estimate records the optimistic, most likely, and the pessimistic duration, and then records an average for the predicted duration Three- point estimate is a way to enhance the accuracy of activity duration estimates. This concept is originated with the Program Evaluation and Review Technique (PERT). PERT charts the following three estimates:

Most likely (TM): The duration of activity based on realistic factors such as resources assigned, interruptions, etc. Optimistic (TO): The activity duration based on the best-case scenario Pessimistic (TP): The activity duration based on the worst-case scenario The expected (TE) activity duration is a weighted average of these three estimates: TE = (TO + 4TM + TP) / 6 Duration estimates based on the above equations (sometimes simple average of the three estimates is also used) provide more accuracy. It can be calculated as follows: TE = ( 20 + 45*4 + 90) / 6 = 290/6 =48 Answer options B, C, and D are incorrect. These are not the valid answers for this question.



Viewing Page 4 of 67



Share your comments for PMI PMI-SP exam with other users:

John 8/7/2023 12:12:00 AM

has anyone recently attended safe 6.0 exam? did you see any questions from here?
Anonymous


Big Dog 6/24/2023 4:47:00 PM

question 13 should be dhcp option 43, right?
UNITED STATES


B.Khan 4/19/2022 9:43:00 PM

the buy 1 get 1 is a great deal. so far i have only gone over exam. it looks promissing. i report back once i write my exam.
INDIA


Ganesh 12/24/2023 11:56:00 PM

is this dump good
Anonymous


Albin 10/13/2023 12:37:00 AM

good ................
EUROPEAN UNION


Passed 1/16/2022 9:40:00 AM

passed
GERMANY


Harsh 6/12/2023 1:43:00 PM

yes going good
Anonymous


Salesforce consultant 1/2/2024 1:32:00 PM

good questions for practice
FRANCE


Ridima 9/12/2023 4:18:00 AM

need dump and sap notes for c_s4cpr_2308 - sap certified application associate - sap s/4hana cloud, public edition - sourcing and procurement
Anonymous


Tanvi Rajput 10/6/2023 6:50:00 AM

question 11: d i personally feel some answers are wrong.
UNITED KINGDOM


Anil 7/18/2023 9:38:00 AM

nice questions
Anonymous


Chris 8/26/2023 1:10:00 AM

looking for c1000-158: ibm cloud technical advocate v4 questions
Anonymous


sachin 6/27/2023 1:22:00 PM

can you share the pdf
Anonymous


Blessious Phiri 8/13/2023 10:26:00 AM

admin ii is real technical stuff
Anonymous


Luis Manuel 7/13/2023 9:30:00 PM

could you post the link
UNITED STATES


vijendra 8/18/2023 7:54:00 AM

hello send me dumps
Anonymous


Simeneh 7/9/2023 8:46:00 AM

it is very nice
Anonymous


john 11/16/2023 5:13:00 PM

i gave the amazon dva-c02 tests today and passed. very helpful.
Anonymous


Tao 11/20/2023 8:53:00 AM

there is an incorrect word in the problem statement. for example, in question 1, there is the word "speci c". this is "specific. in the other question, there is the word "noti cation". this is "notification. these mistakes make this site difficult for me to use.
Anonymous


patricks 10/24/2023 6:02:00 AM

passed my az-120 certification exam today with 90% marks. studied using the dumps highly recommended to all.
Anonymous


Ananya 9/14/2023 5:17:00 AM

i need it, plz make it available
UNITED STATES


JM 12/19/2023 2:41:00 PM

q47: intrusion prevention system is the correct answer, not patch management. by definition, there are no patches available for a zero-day vulnerability. the way to prevent an attacker from exploiting a zero-day vulnerability is to use an ips.
UNITED STATES


Ronke 8/18/2023 10:39:00 AM

this is simple but tiugh as well
Anonymous


CesarPA 7/12/2023 10:36:00 PM

questão 4, segundo meu compilador local e o site https://www.jdoodle.com/online-java-compiler/, a resposta correta é "c" !
UNITED STATES


Jeya 9/13/2023 7:50:00 AM

its very useful
INDIA


Tracy 10/24/2023 6:28:00 AM

i mastered my skills and aced the comptia 220-1102 exam with a score of 920/1000. i give the credit to for my success.
Anonymous


James 8/17/2023 4:33:00 PM

real questions
UNITED STATES


Aderonke 10/23/2023 1:07:00 PM

very helpful assessments
UNITED KINGDOM


Simmi 8/24/2023 7:25:00 AM

hi there, i would like to get dumps for this exam
AUSTRALIA


johnson 10/24/2023 5:47:00 AM

i studied for the microsoft azure az-204 exam through it has 100% real questions available for practice along with various mock tests. i scored 900/1000.
GERMANY


Manas 9/9/2023 1:48:00 AM

please upload 1z0-1072-23 exam dups
UNITED STATES


SB 9/12/2023 5:15:00 AM

i was hoping if you could please share the pdf as i’m currently preparing to give the exam.
Anonymous


Jagjit 8/26/2023 5:01:00 PM

i am looking for oracle 1z0-116 exam
UNITED STATES


S Mallik 11/27/2023 12:32:00 AM

where we can get the answer to the questions
Anonymous