Ben is the project manager of the NHF Project for his organization. Some delays early in the project have caused the project schedule to slip by nearly 15 percent. Management would like Ben to find a method to recoup the schedule slippage and to get the project back on track. Management is risk- adverse with this project. Which of the following methods should Ben avoid to recoup the project time?
Answer(s): B
Of all the choices, Ben should avoid fast tracking, as it allows complete phases of the project to overlap, and this increases project risks. Management wants to avoid risks, so fast tracking would not be helpful. Fast tracking is a technique for compressing project schedule. In fast tracking, phases are overlapped that would normally be done in sequence. It is shortening the project schedule without reducing the project scope. Answer option A is incorrect. Crashing adds people and costs but is relatively safe in regard to risks. Answer option C is incorrect. Critical chain is not a schedule compression technique and would not necessarily help the project get back on schedule. Answer option D is incorrect. Lead time, similar to fast tracking, can increase project risks; however, fast tracking is more risky than lead time. Lead time allows individual activities to overlap, while fast tracking allows entire project phases to overlap.
Laura is the project manager for her organization and management has requested her to create a report on her project's performance. Laura needs to analyze her current project performance and then compare it against what, in order to create a performance report?
Answer(s): C
The performance measurement baseline, which can be comprised of cost, scope, and schedule, is the foundation for creating a performance report. Answer option B is incorrect. The scope baseline will only reflect the performance of the scope, whereas performance reports typically need scope, time, and cost as its foundation. Answer option A is incorrect. Cost variances and the cost performance index are cost values that must be considered along with the scope performance and schedule performance. Answer option D is incorrect. Only reporting performance on the schedule is not enough for a performance report. Laura should also report on scope and cost at a minimum.
Which of the following documents captures and defines the work activities, deliverables, and a timeline that a vendor will execute against in performance of work for a customer?
A statement of work (SOW) is a document that captures and defines the work activities, deliverables and timeline that a vendor will execute against in performance of work for a customer. Detailed requirements and pricing are usually specified in it, along with many other terms and conditions. SOW is a narrative description of products or services to be supplied by the project. For internal projects, the project initiator or sponsor provides the statement of work based on business needs, product, or service requirements. For external projects, the statement of work can be received from the customer as part of a bid document. Answer option B is incorrect. Scope of statement gives the narrative description of the project scope. Answer option A is incorrect. Project charter is a document that formally authorizes a project manager to work on a project. Answer option D is incorrect. WBS is a tool that defines a project and groups the project discrete work in a way that helps organize and define the total work scope.
A construction company is about to start a new project. It requires hiring a project manager for this project. Which of the following are the most important skills that a person must have to be selected as a project manager?
Answer(s): D
A good project manager must have all of the above mentioned skills. Out of these, the communication skills are the most important skills for a project manager. Communications skills are part of general management skills and are used to exchange information. Communication has many dimensions: Written and oral, listening, and speaking Internal (within the project) and external (customer, the media, the public) Formal (reports, briefings) and informal (memos, ad hoc conversations) Vertical (up and down the organization) and horizontal (with peers) Communication is the most important skill that a project manager must posses. It is the single most important characteristics of a top-class project manager. Project managers must communicate well in order to integrate and maximize the performance of team members. Oral and written communications are the backbone of every successful project. During different phases of a project, a project manager requires to communicate through different manners (for example, documentation, meeting updates, etc.) and he must ensure that the information communicated is explicit, clear, and complete. Answer options E, C, A, and B are incorrect. All these mentioned skills make a person a good project manager. Communication skills top the list. What are organizational skills? Organizational skills are part of management skills to organize various aspects of a project in order to complete it successfully. A good project manager uses these skills to successfully organize his meetings, as well as to keep documentations, quotes, contracts, etc., which can be fetched at any given moment. Organizational skills also include planning and time management skills. What are budgeting skills? Budgeting skills include the knowledge of finance and accounting principles. A project manager must possess these skills in order to perform cost estimates for project budgeting. Reading and understanding quotes, preparing purchase orders, and reconciling purchase invoices are all part of budgeting skills. In order to make the budget of a project, the project manager must have excellent budgeting skills. What are problem solving skills? Problem solving skills include the ability to define and analyze problems, and to take decisions in order to solve the problems by implementing those decisions. Every project manager must possess strong problem solving skills. Problem solving is a two-fold process: Defining the problem Taking a decision and then implementing it A project manager is responsible for determining the best course of action to take in order to resolve the problem. What are negotiating and influencing skills?Negotiating skills includes demanding and convincing others for the rightful thing or act. A project manager needs this skill to negotiate on projects in almost every area such as scope definitions, budgets, contracts, resource assignments, schedules, etc. Influencing skills include the convincing power of a person. It is an ability to change minds and the course of events. A good project manager requires these skills to utilize them in all areas of project management.
Which of the following individuals has a management role in a core business area, such as research and development, design, manufacturing, provisioning, testing, or maintenance?
The role of operations manager is to perform various management roles in a core business area, such as research and development, design, manufacturing, provisioning, testing, or maintenance. The operations manager directly deals with constructing and maintaining the saleable products or services of the enterprise. Answer option C is incorrect. A project manager is an expert in the field of project management. He is responsible for the entire project from inception to completion. The project manager leads the team and helps negotiate the multiple relationships within any project whether with clients, team members, firm principals or any variety of partners and functions as the hub of a project. Answer option A is incorrect. The role of a functional manager is to perform various management roles within an administrative or functional area of the business, such as human resources, finance, accounting, or procurement. He is assigned his own permanent staff to carry out the ongoing work. He should have a clear directive to manage all tasks within his functional area of responsibility. Answer option D is incorrect. Seller is also known as a vendor, supplier or contractor. They are external company's elements that enter into a contractual agreement to provide components or services necessary for the project.
Share your comments for PMI PMI-SP exam with other users:
Helpful to test your preparedness before giving exam
Really helped
Good explanation
very helpful
Question 1, Ans is - Developer,Standard,Professional Direct and Premier
Passed this exam in first appointment. Great resource and valid exam dump.
Today I wrote this exam and passed, i totally relay on this practice exam. The questions were very tough, these questions are valid and I encounter the same.
Anyone used this dump recently?
173 question is A not D
nice questions
Thanks for the practice questions they helped me a lot.
Passed this exam today. All questions are valid and this is not something you can find in ChatGPT.
i need to pass exam for VMware 2V0-11.25
Great questions.
great dumps to practice for the exam
How reliable and relevant are these questions?? also i can see the last update here was January and definitely new questions would have emerged.
Can I trust to this source?
can you please provide the CBDA latest test preparation
This is the best and only way of passing this exam as it is extremely hard. Good questions and valid dump.
Can I use this dumps when I am taking the exam? I mean does somebody look what tabs or windows I have opened ?
Finally got a change to write this exam and pass it! Valid and accurate!
Upload this exam please!
Thank you for providing these questions. It helped me a lot with passing my exam.
my first attempt
very explainable
i think answer of q 462 is variance analysis
hi i need see questions
best study material for exam
very interesting repository
american history 1
good level of questions
i need this dump kindly upload it
do we need c# coding to be az204 certified
excellent topics covered