John works as the project manager for Honeywell Inc. He is involved in the periodic collection and analysis of baseline versus actual data to understand and communicate the project progress.
Which of the following techniques is used in generating performance reports?

  1. Work performance information
  2. Change requests
  3. Work performance measurements
  4. Forecasting method

Answer(s): D

Explanation:

Forecasting method is a technique used in generating performance reports. Forecasting is the process of estimating or predicting in unknown situations. Forecasting is about pre icting the future as accurately as possible with the help of all the information available, including historical data and knowledge of any future events that might impact forecasts. The forecasting methods are categorized as follows: Time series method: It uses historical data as the basis for estimating future outcomes. Causal/econometric method: This forecasting method is based on the assumption that it is possible to identify some factors that might influence the variable that is being forecasted. If the causes are understood, projections of the influencing variables can be made and used in the forecast.

Judgmental method: Judgmental forecasting methods incorporate intuitive judgments, opinions, and subjective probability estimates. Other methods: Other methods may include probabilistic forecasting, simulation, and ensemble forecasting. It is one of the tools and techniques of the report performance process.
Answer option A is incorrect. Work performance information is the data gathered on the status of the project schedule activities that are performed to accomplish the project work. This data is collected as part of the Direct and Manage Project Execution processes. WPI includes the following: Deliverables status Schedule Progress Costs incurred It is used as an input in generating the report performance process.
Answer option C is incorrect. Work performance measurements are created from the work performance information. WPMs are an output of Control schedule, Control cost, and Control scope processes, which are monitoring and controlling processes. WPMs consist of planned versus actual performance indicators with respect to scope, schedule, and cost. They are documented and communicated to the stakeholders and are used to make project activity metrics, such as the following: Planned vs. Actual Technical performance and Scope performance Planned vs. Actual Schedule performance Planned vs. Actual Cost performance They are used as an input in generating the report performance process.

Answer option B is incorrect. Change requests are requests to expand or reduce the project scope, modify policies, processes, plans, or procedures, modify costs or budgets or revise schedules. These requests for a change can be direct or indirect, externally or internally initiated, and legally or contractually imposed or optional. A Project Manager needs to ensure that only formally documented requested changes are processed and only approved change requests are implemented. It is an output of the report performance process.



Which of the following are the inputs to the Develop Project Charter process? Each correct answer represents a complete solution. Choose all that apply.

  1. Procurement document
  2. Contract
  3. Business case
  4. Project statement of work

Answer(s): B,C,D

Explanation:

The Develop Project Charter process documents the formal authorization of a project or a phase. It also documents initial requirements that satisfy the stakeholder's needs and expectations. It is used to validate the decisions made during the previous iteration of the Develop Project Charter process. The various inputs of this process are as follows: Project statement of work Business case Contract Enterprise environmental factors Organizational process assets The output of the Develop project Charter process is as follows : Project charter
Answer option A is incorrect. Procurement document is the input of the Identify Stakeholders process.



Beth is the project manager for the NHQ project. This project deals with fiber optic cabling in her organizational campus. Tim is the electrical engineer for her company and is the only internal resource that can complete several of the project activities that deal with the fiber optic cables. Because Tim is a highly-skilled resource, he is already scheduled on several projects within the organization and is not available when Beth needs him to complete some of the project activities.
This is an example of which term?

  1. Resource calendar conflict
  2. Matrix network
  3. Organizational process assets
  4. Activity resource requirements

Answer(s): D

Explanation:

Because the activities in Beth's project require Tim and his skills. This is an example of an activity resource requirement. A resource constraint would also have been an acceptable answer.
Answer option B is incorrect. This may be a matrix organization, but matrix network is not a valid project management term.
Answer option C is incorrect. Organizational process assets are things that have been created to help assist the management of the project.
Answer option A is incorrect. A resource calendar conflict is not a valid project management term.



Fill in the blank with an appropriate phrase. The_____ allows the project team to look at the performance of the project to date, and use that data to make more accurate projections about the future.

  1. Schedule model

Answer(s): A

Explanation:

The main function of the schedule model is to provide useful 'road map' that can be used by the project manager and the project team to assist them in completing the project fruitfully. A well-developed schedule model is an active tool used to predict at what time the project work that remains to be completed can reasonably be completed. The schedule model allows the project team to look at the performance of the project to date, and use that data to make more accurate projections about the future.



John works as a Project Manager for Blue Well Inc. He is measuring cost efficiency of his project. The key values are provided in the table below:



What is the cost performance index (CPI) of the project at the current point of time?

  1. 0.96
  2. 1.082
  3. 0.833
  4. 1.0625

Answer(s): C

Explanation:

According to the question, you are required to calculate the cost performance index (CPI) of the project. Cost performance index (CPI) is used to calculate performance efficiencies. It is used in trend analysis to predict future performance. CPI is the ratio of earned value to actual cost. The CPI is calculated based on the following formula: CPI = Earned Value (EV) / Actual Cost (AC) If the CPI value is greater than 1, it indicates better than expected performance, whereas if the value is less than 1, it shows poor performance. The CPI value of 1 indicates that the project is right on target.
Here, CPI is as follows:

CPI = EV / AV
=
= 0.833

As the CPI (0.833) is less than 1, it shows that the schedule performance is below expectation.
What is BCWP (or EV)?
Budgeted cost of work performed (BCWP) or Earned Value (EV) is the value of completed work. It is the budgeted amount for the work actually completed on the schedule activity during a given time period.

What is BCWS (or PV)?
Budgeted Cost of Work Scheduled (BCWS) or Planned Value (PV) is the authorized budget assigned to the scheduled work to be accomplished for a schedule activity or Work Breakdown Structure (WBS) component.

What is ACWP (or AC)?
Actual cost of work performed (ACWP) or Actual Cost (AC) is the total costs actually incurred and recorded in accomplishing work performed during a given time period for a schedule activity. It is the cost of the work to date, including direct and indirect costs. AC is money that has actually been expended to date.



Viewing Page 9 of 67



Share your comments for PMI PMI-SP exam with other users:

BigMouthDog 1/22/2022 8:17:00 PM

hi team just want to know if there is any update version of the exam 350-401
AUSTRALIA


francesco 10/30/2023 11:08:00 AM

helpful on 2017 scrum guide
EUROPEAN UNION


Amitabha Roy 10/5/2023 3:16:00 AM

planning to attempt for the exam.
Anonymous


Prem Yadav 7/29/2023 6:20:00 AM

pleaseee upload
INDIA


Ahmed Hashi 7/6/2023 5:40:00 PM

thanks ly so i have information cia
EUROPEAN UNION


mansi 5/31/2023 7:58:00 AM

hello team, i need sap qm dumps for practice
INDIA


Jamil aljamil 12/4/2023 4:47:00 AM

it’s good but not senatios based
UNITED KINGDOM


Cath 10/10/2023 10:19:00 AM

q.119 - the correct answer is b - they are not captured in an update set as theyre data.
VIET NAM


P 1/6/2024 11:22:00 AM

good matter
Anonymous


surya 7/30/2023 2:02:00 PM

please upload c_sacp_2308
CANADA


Sasuke 7/11/2023 10:30:00 PM

please upload the dump. thanks very much !!
Anonymous


V 7/4/2023 8:57:00 AM

good questions
UNITED STATES


TTB 8/22/2023 5:30:00 AM

hi, could you please update the latest dump version
Anonymous


T 7/28/2023 9:06:00 PM

this question is keep repeat : you are developing a sales application that will contain several azure cloud services and handle different components of a transaction. different cloud services will process customer orders, billing, payment, inventory, and shipping. you need to recommend a solution to enable the cloud services to asynchronously communicate transaction information by using xml messages. what should you include in the recommendation?
NEW ZEALAND


Gurgaon 9/28/2023 4:35:00 AM

great questions
UNITED STATES


wasif 10/11/2023 2:22:00 AM

its realy good
UNITED ARAB EMIRATES


Shubhra Rathi 8/26/2023 1:12:00 PM

oracle 1z0-1059-22 dumps
Anonymous


Leo 7/29/2023 8:48:00 AM

please share me the pdf..
INDIA


AbedRabbou Alaqabna 12/18/2023 3:10:00 AM

q50: which two functions can be used by an end user when pivoting an interactive report? the correct answer is a, c because we do not have rank in the function pivoting you can check in the apex app
GREECE


Rohan Limaye 12/30/2023 8:52:00 AM

best to practice
Anonymous


Aparajeeta 10/13/2023 2:42:00 PM

so far it is good
Anonymous


Vgf 7/20/2023 3:59:00 PM

please provide me the dump
Anonymous


Deno 10/25/2023 1:14:00 AM

i failed the cisa exam today. but i have found all the questions that were on the exam to be on this site.
Anonymous


CiscoStudent 11/15/2023 5:29:00 AM

in question 272 the right answer states that an autonomous acces point is "configured and managed by the wlc" but this is not what i have learned in my ccna course. is this a mistake? i understand that lightweight aps are managed by wlc while autonomous work as standalones on the wlan.
Anonymous


pankaj 9/28/2023 4:36:00 AM

it was helpful
Anonymous


User123 10/8/2023 9:59:00 AM

good question
UNITED STATES


vinay 9/4/2023 10:23:00 AM

really nice
Anonymous


Usman 8/28/2023 10:07:00 AM

please i need dumps for isc2 cybersecuity
Anonymous


Q44 7/30/2023 11:50:00 AM

ans is coldline i think
UNITED STATES


Anuj 12/21/2023 1:30:00 PM

very helpful
Anonymous


Giri 9/13/2023 10:31:00 PM

can you please provide dumps so that it helps me more
UNITED STATES


Aaron 2/8/2023 12:10:00 AM

thank you for providing me with the updated question and answers. this version has all the questions from the exam. i just saw them in my exam this morning. i passed my exam today.
SOUTH AFRICA


Sarwar 12/21/2023 4:54:00 PM

how i can see exam questions?
CANADA


Chengchaone 9/11/2023 10:22:00 AM

can you please upload please?
Anonymous