John works as the project manager for Honeywell Inc. He is involved in the periodic collection and analysis of baseline versus actual data to understand and communicate the project progress.
Which of the following techniques is used in generating performance reports?

  1. Work performance information
  2. Change requests
  3. Work performance measurements
  4. Forecasting method

Answer(s): D

Explanation:

Forecasting method is a technique used in generating performance reports. Forecasting is the process of estimating or predicting in unknown situations. Forecasting is about pre icting the future as accurately as possible with the help of all the information available, including historical data and knowledge of any future events that might impact forecasts. The forecasting methods are categorized as follows: Time series method: It uses historical data as the basis for estimating future outcomes. Causal/econometric method: This forecasting method is based on the assumption that it is possible to identify some factors that might influence the variable that is being forecasted. If the causes are understood, projections of the influencing variables can be made and used in the forecast.

Judgmental method: Judgmental forecasting methods incorporate intuitive judgments, opinions, and subjective probability estimates. Other methods: Other methods may include probabilistic forecasting, simulation, and ensemble forecasting. It is one of the tools and techniques of the report performance process.
Answer option A is incorrect. Work performance information is the data gathered on the status of the project schedule activities that are performed to accomplish the project work. This data is collected as part of the Direct and Manage Project Execution processes. WPI includes the following: Deliverables status Schedule Progress Costs incurred It is used as an input in generating the report performance process.
Answer option C is incorrect. Work performance measurements are created from the work performance information. WPMs are an output of Control schedule, Control cost, and Control scope processes, which are monitoring and controlling processes. WPMs consist of planned versus actual performance indicators with respect to scope, schedule, and cost. They are documented and communicated to the stakeholders and are used to make project activity metrics, such as the following: Planned vs. Actual Technical performance and Scope performance Planned vs. Actual Schedule performance Planned vs. Actual Cost performance They are used as an input in generating the report performance process.

Answer option B is incorrect. Change requests are requests to expand or reduce the project scope, modify policies, processes, plans, or procedures, modify costs or budgets or revise schedules. These requests for a change can be direct or indirect, externally or internally initiated, and legally or contractually imposed or optional. A Project Manager needs to ensure that only formally documented requested changes are processed and only approved change requests are implemented. It is an output of the report performance process.



Which of the following are the inputs to the Develop Project Charter process? Each correct answer represents a complete solution. Choose all that apply.

  1. Procurement document
  2. Contract
  3. Business case
  4. Project statement of work

Answer(s): B,C,D

Explanation:

The Develop Project Charter process documents the formal authorization of a project or a phase. It also documents initial requirements that satisfy the stakeholder's needs and expectations. It is used to validate the decisions made during the previous iteration of the Develop Project Charter process. The various inputs of this process are as follows: Project statement of work Business case Contract Enterprise environmental factors Organizational process assets The output of the Develop project Charter process is as follows : Project charter
Answer option A is incorrect. Procurement document is the input of the Identify Stakeholders process.



Beth is the project manager for the NHQ project. This project deals with fiber optic cabling in her organizational campus. Tim is the electrical engineer for her company and is the only internal resource that can complete several of the project activities that deal with the fiber optic cables. Because Tim is a highly-skilled resource, he is already scheduled on several projects within the organization and is not available when Beth needs him to complete some of the project activities.
This is an example of which term?

  1. Resource calendar conflict
  2. Matrix network
  3. Organizational process assets
  4. Activity resource requirements

Answer(s): D

Explanation:

Because the activities in Beth's project require Tim and his skills. This is an example of an activity resource requirement. A resource constraint would also have been an acceptable answer.
Answer option B is incorrect. This may be a matrix organization, but matrix network is not a valid project management term.
Answer option C is incorrect. Organizational process assets are things that have been created to help assist the management of the project.
Answer option A is incorrect. A resource calendar conflict is not a valid project management term.



Fill in the blank with an appropriate phrase. The_____ allows the project team to look at the performance of the project to date, and use that data to make more accurate projections about the future.

  1. Schedule model

Answer(s): A

Explanation:

The main function of the schedule model is to provide useful 'road map' that can be used by the project manager and the project team to assist them in completing the project fruitfully. A well-developed schedule model is an active tool used to predict at what time the project work that remains to be completed can reasonably be completed. The schedule model allows the project team to look at the performance of the project to date, and use that data to make more accurate projections about the future.



John works as a Project Manager for Blue Well Inc. He is measuring cost efficiency of his project. The key values are provided in the table below:



What is the cost performance index (CPI) of the project at the current point of time?

  1. 0.96
  2. 1.082
  3. 0.833
  4. 1.0625

Answer(s): C

Explanation:

According to the question, you are required to calculate the cost performance index (CPI) of the project. Cost performance index (CPI) is used to calculate performance efficiencies. It is used in trend analysis to predict future performance. CPI is the ratio of earned value to actual cost. The CPI is calculated based on the following formula: CPI = Earned Value (EV) / Actual Cost (AC) If the CPI value is greater than 1, it indicates better than expected performance, whereas if the value is less than 1, it shows poor performance. The CPI value of 1 indicates that the project is right on target.
Here, CPI is as follows:

CPI = EV / AV
=
= 0.833

As the CPI (0.833) is less than 1, it shows that the schedule performance is below expectation.
What is BCWP (or EV)?
Budgeted cost of work performed (BCWP) or Earned Value (EV) is the value of completed work. It is the budgeted amount for the work actually completed on the schedule activity during a given time period.

What is BCWS (or PV)?
Budgeted Cost of Work Scheduled (BCWS) or Planned Value (PV) is the authorized budget assigned to the scheduled work to be accomplished for a schedule activity or Work Breakdown Structure (WBS) component.

What is ACWP (or AC)?
Actual cost of work performed (ACWP) or Actual Cost (AC) is the total costs actually incurred and recorded in accomplishing work performed during a given time period for a schedule activity. It is the cost of the work to date, including direct and indirect costs. AC is money that has actually been expended to date.



Viewing Page 9 of 67



Share your comments for PMI PMI-SP exam with other users:

Laolu 2/15/2023 11:04:00 PM

aside from pdf the test engine software is helpful. the interface is user-friendly and intuitive, making it easy to navigate and find the questions.
UNITED STATES


Zaynik 9/17/2023 5:36:00 AM

questions and options are correct, but the answers are wrong sometimes. so please check twice or refer some other platform for the right answer
Anonymous


Massam 6/11/2022 5:55:00 PM

90% of questions was there but i failed the exam, i marked the answers as per the guide but looks like they are not accurate , if not i would have passed the exam given that i saw about 45 of 50 questions from dump
Anonymous


Anonymous 12/27/2023 12:47:00 AM

answer to this question "what administrative safeguards should be implemented to protect the collected data while in use by manasa and her product management team? " it should be (c) for the following reasons: this administrative safeguard involves controlling access to collected data by ensuring that only individuals who need the data for their job responsibilities have access to it. this helps minimize the risk of unauthorized access and potential misuse of sensitive information. while other options such as (a) documenting data flows and (b) conducting a privacy impact assessment (pia) are important steps in data protection, implementing a "need to know" access policy directly addresses the issue of protecting data while in use by limiting access to those who require it for legitimate purposes. (d) is not directly related to safeguarding data during use; it focuses on data transfers and location.
INDIA


Japles 5/23/2023 9:46:00 PM

password lockout being the correct answer for question 37 does not make sense. it should be geofencing.
Anonymous


Faritha 8/10/2023 6:00:00 PM

for question 4, the righr answer is :recover automatically from failures
UNITED STATES


Anonymous 9/14/2023 4:27:00 AM

question number 4s answer is 3, option c. i
UNITED STATES


p das 12/7/2023 11:41:00 PM

very good questions
UNITED STATES


Anna 1/5/2024 1:12:00 AM

i am confused about the answers to the questions. are the answers correct?
KOREA REPUBLIC OF


Bhavya 9/13/2023 10:15:00 AM

very usefull
Anonymous


Rahul Kumar 8/31/2023 12:30:00 PM

need certification.
CANADA


Diran Ole 9/17/2023 5:15:00 PM

great exam prep
CANADA


Venkata Subbarao Bandaru 6/24/2023 8:45:00 AM

i require dump
Anonymous


D 7/15/2023 1:38:00 AM

good morning, could you please upload this exam again,
Anonymous


Ann 9/15/2023 5:39:00 PM

hi can you please upload the dumps for sap contingent module. thanks
AUSTRALIA


Sridhar 1/16/2024 9:19:00 PM

good questions
Anonymous


Summer 10/4/2023 9:57:00 PM

looking forward to the real exam
Anonymous


vv 12/2/2023 2:45:00 PM

good ones for exam preparation
UNITED STATES


Danny Zas 9/15/2023 4:45:00 AM

this is a good experience
UNITED STATES


SM 1211 10/12/2023 10:06:00 PM

hi everyone
UNITED STATES


A 10/2/2023 6:08:00 PM

waiting for the dump. please upload.
UNITED STATES


Anonymous 7/16/2023 11:05:00 AM

upload cks exam questions
Anonymous


Johan 12/13/2023 8:16:00 AM

awesome training material
NETHERLANDS


PC 7/28/2023 3:49:00 PM

where is dump
Anonymous


YoloStar Yoloing 10/22/2023 9:58:00 PM

q. 289 - the correct answer should be b not d, since the question asks for the most secure way to provide access to a s3 bucket (a single one), and by principle of the least privilege you should not be giving access to all buckets.
Anonymous


Zelalem Nega 5/14/2023 12:45:00 PM

please i need if possible h12-831,
UNITED KINGDOM


unknown-R 11/23/2023 7:36:00 AM

good collection of questions and solution for pl500 certification
UNITED STATES


Swaminathan 5/11/2023 9:59:00 AM

i would like to appear the exam.
Anonymous


Veenu 10/24/2023 6:26:00 AM

i am very happy as i cleared my comptia a+ 220-1101 exam. i studied from as it has all exam dumps and mock tests available. i got 91% on the test.
Anonymous


Karan 5/17/2023 4:26:00 AM

need this dump
Anonymous


Ramesh Kutumbaka 12/30/2023 11:17:00 PM

its really good to eventuate knowledge before appearing for the actual exam.
Anonymous


anonymous 7/20/2023 10:31:00 PM

this is great
CANADA


Xenofon 6/26/2023 9:35:00 AM

please i want the questions to pass the exam
UNITED STATES


Diego 1/21/2024 8:21:00 PM

i need to pass exam
Anonymous