PMI PMI-SP Exam (page: 9)
PMI -SP Scheduling Professional
Updated on: 12-Jan-2026

Viewing Page 9 of 67

John works as the project manager for Honeywell Inc. He is involved in the periodic collection and analysis of baseline versus actual data to understand and communicate the project progress.
Which of the following techniques is used in generating performance reports?

  1. Work performance information
  2. Change requests
  3. Work performance measurements
  4. Forecasting method

Answer(s): D

Explanation:

Forecasting method is a technique used in generating performance reports. Forecasting is the process of estimating or predicting in unknown situations. Forecasting is about pre icting the future as accurately as possible with the help of all the information available, including historical data and knowledge of any future events that might impact forecasts. The forecasting methods are categorized as follows: Time series method: It uses historical data as the basis for estimating future outcomes. Causal/econometric method: This forecasting method is based on the assumption that it is possible to identify some factors that might influence the variable that is being forecasted. If the causes are understood, projections of the influencing variables can be made and used in the forecast.

Judgmental method: Judgmental forecasting methods incorporate intuitive judgments, opinions, and subjective probability estimates. Other methods: Other methods may include probabilistic forecasting, simulation, and ensemble forecasting. It is one of the tools and techniques of the report performance process.
Answer option A is incorrect. Work performance information is the data gathered on the status of the project schedule activities that are performed to accomplish the project work. This data is collected as part of the Direct and Manage Project Execution processes. WPI includes the following: Deliverables status Schedule Progress Costs incurred It is used as an input in generating the report performance process.
Answer option C is incorrect. Work performance measurements are created from the work performance information. WPMs are an output of Control schedule, Control cost, and Control scope processes, which are monitoring and controlling processes. WPMs consist of planned versus actual performance indicators with respect to scope, schedule, and cost. They are documented and communicated to the stakeholders and are used to make project activity metrics, such as the following: Planned vs. Actual Technical performance and Scope performance Planned vs. Actual Schedule performance Planned vs. Actual Cost performance They are used as an input in generating the report performance process.

Answer option B is incorrect. Change requests are requests to expand or reduce the project scope, modify policies, processes, plans, or procedures, modify costs or budgets or revise schedules. These requests for a change can be direct or indirect, externally or internally initiated, and legally or contractually imposed or optional. A Project Manager needs to ensure that only formally documented requested changes are processed and only approved change requests are implemented. It is an output of the report performance process.



Which of the following are the inputs to the Develop Project Charter process? Each correct answer represents a complete solution. Choose all that apply.

  1. Procurement document
  2. Contract
  3. Business case
  4. Project statement of work

Answer(s): B,C,D

Explanation:

The Develop Project Charter process documents the formal authorization of a project or a phase. It also documents initial requirements that satisfy the stakeholder's needs and expectations. It is used to validate the decisions made during the previous iteration of the Develop Project Charter process. The various inputs of this process are as follows: Project statement of work Business case Contract Enterprise environmental factors Organizational process assets The output of the Develop project Charter process is as follows : Project charter
Answer option A is incorrect. Procurement document is the input of the Identify Stakeholders process.



Beth is the project manager for the NHQ project. This project deals with fiber optic cabling in her organizational campus. Tim is the electrical engineer for her company and is the only internal resource that can complete several of the project activities that deal with the fiber optic cables. Because Tim is a highly-skilled resource, he is already scheduled on several projects within the organization and is not available when Beth needs him to complete some of the project activities.
This is an example of which term?

  1. Resource calendar conflict
  2. Matrix network
  3. Organizational process assets
  4. Activity resource requirements

Answer(s): D

Explanation:

Because the activities in Beth's project require Tim and his skills. This is an example of an activity resource requirement. A resource constraint would also have been an acceptable answer.
Answer option B is incorrect. This may be a matrix organization, but matrix network is not a valid project management term.
Answer option C is incorrect. Organizational process assets are things that have been created to help assist the management of the project.
Answer option A is incorrect. A resource calendar conflict is not a valid project management term.



Fill in the blank with an appropriate phrase. The_____ allows the project team to look at the performance of the project to date, and use that data to make more accurate projections about the future.

  1. Schedule model

Answer(s): A

Explanation:

The main function of the schedule model is to provide useful 'road map' that can be used by the project manager and the project team to assist them in completing the project fruitfully. A well-developed schedule model is an active tool used to predict at what time the project work that remains to be completed can reasonably be completed. The schedule model allows the project team to look at the performance of the project to date, and use that data to make more accurate projections about the future.



John works as a Project Manager for Blue Well Inc. He is measuring cost efficiency of his project. The key values are provided in the table below:



What is the cost performance index (CPI) of the project at the current point of time?

  1. 0.96
  2. 1.082
  3. 0.833
  4. 1.0625

Answer(s): C

Explanation:

According to the question, you are required to calculate the cost performance index (CPI) of the project. Cost performance index (CPI) is used to calculate performance efficiencies. It is used in trend analysis to predict future performance. CPI is the ratio of earned value to actual cost. The CPI is calculated based on the following formula: CPI = Earned Value (EV) / Actual Cost (AC) If the CPI value is greater than 1, it indicates better than expected performance, whereas if the value is less than 1, it shows poor performance. The CPI value of 1 indicates that the project is right on target.
Here, CPI is as follows:

CPI = EV / AV
=
= 0.833

As the CPI (0.833) is less than 1, it shows that the schedule performance is below expectation.
What is BCWP (or EV)?
Budgeted cost of work performed (BCWP) or Earned Value (EV) is the value of completed work. It is the budgeted amount for the work actually completed on the schedule activity during a given time period.

What is BCWS (or PV)?
Budgeted Cost of Work Scheduled (BCWS) or Planned Value (PV) is the authorized budget assigned to the scheduled work to be accomplished for a schedule activity or Work Breakdown Structure (WBS) component.

What is ACWP (or AC)?
Actual cost of work performed (ACWP) or Actual Cost (AC) is the total costs actually incurred and recorded in accomplishing work performed during a given time period for a schedule activity. It is the cost of the work to date, including direct and indirect costs. AC is money that has actually been expended to date.



Viewing Page 9 of 67



Share your comments for PMI PMI-SP exam with other users:

quen 7/26/2023 10:39:00 AM

please upload apache spark dumps
Anonymous


Erineo 11/2/2023 5:34:00 PM

q14 is b&c to reduce you will switch off mail for every single alert and you will switch on daily digest to get a mail once per day, you might even skip the empty digest mail but i see this as a part of the daily digest adjustment
Anonymous


Paul 10/21/2023 8:25:00 AM

i think it is good question
Anonymous


Unknown 8/15/2023 5:09:00 AM

good for students who wish to give certification.
INDIA


Ch 11/20/2023 10:56:00 PM

is there a google drive link to the images? the links in questions are not working.
AUSTRALIA


Joey 5/16/2023 5:25:00 AM

very promising, looks great, so much wow!
Anonymous


alaska 10/24/2023 5:48:00 AM

i scored 87% on the az-204 exam. thanks! i always trust
GERMANY


nnn 7/9/2023 11:09:00 PM

good need more
Anonymous


User-sfdc 12/29/2023 7:21:00 AM

sample questions seems good
Anonymous


Tamer dam 8/4/2023 10:21:00 AM

huawei is ok
UNITED STATES


YK 12/11/2023 1:10:00 AM

good one nice
JAPAN


de 8/28/2023 2:38:00 AM

please continue
GERMANY


DMZ 6/25/2023 11:56:00 PM

this exam dumps just did the job. i donot want to ruffle your feathers but your exam dumps and mock test engine is amazing.
UNITED KINGDOM


Jose 8/30/2023 6:14:00 AM

nice questions
PORTUGAL


Tar01 7/24/2023 7:07:00 PM

the explanation are really helpful
Anonymous


DaveG 12/15/2023 4:50:00 PM

just passed my exam yesterday on my first attempt. these dumps were extremely helpful in passing first time. the questions were very, very similar to these questions!
Anonymous


A.K. 6/30/2023 6:34:00 AM

cosmos db is paas not saas
Anonymous


S Roychowdhury 6/26/2023 5:27:00 PM

what is the percentage of common questions in gcp exam compared to 197 dump questions? are they 100% matching with real gcp exam?
Anonymous


Bella 7/22/2023 2:05:00 AM

not able to see questions
Anonymous


Scott 9/8/2023 7:19:00 AM

by far one of the best sites for free questions. i have pass 2 exams with the help of this website.
CANADA


donald 8/19/2023 11:05:00 AM

excellent question bank.
Anonymous


Ashwini 8/22/2023 5:13:00 AM

it really helped
Anonymous


sk 5/13/2023 2:07:00 AM

excelent material
INDIA


Christopher 9/5/2022 10:54:00 PM

the new versoin of this exam which i downloaded has all the latest questions from the exam. i only saw 3 new questions in the exam which was not in this dump.
CANADA


Sam 9/7/2023 6:51:00 AM

question 8 - can cloudtrail be used for storing jobs? based on aws - aws cloudtrail is used for governance, compliance and investigating api usage across all of our aws accounts. every action that is taken by a user or script is an api call so this is logged to [aws] cloudtrail. something seems incorrect here.
UNITED STATES


Tanvi Rajput 8/14/2023 10:55:00 AM

question 13 tda - c01 answer : quick table calculation -> percentage of total , compute using table down
UNITED KINGDOM


PMSAGAR 9/19/2023 2:48:00 AM

pls share teh dump
UNITED STATES


zazza 6/16/2023 10:47:00 AM

question 44 answer is user risk
ITALY


Prasana 6/23/2023 1:59:00 AM

please post the questions for preparation
Anonymous


test user 9/24/2023 3:15:00 AM

thanks for the questions
AUSTRALIA


Draco 7/19/2023 5:34:00 AM

please reopen it now ..its really urgent
UNITED STATES


Megan 4/14/2023 5:08:00 PM

these practice exam questions were exactly what i needed. the variety of questions and the realistic exam-like environment they created helped me assess my strengths and weaknesses. i felt more confident and well-prepared on exam day, and i owe it to this exam dumps!
UNITED KINGDOM


abdo casa 8/9/2023 6:10:00 PM

thank u it very instructuf
Anonymous


Danny 1/15/2024 9:10:00 AM

its helpful?
INDIA