PMI PMI-SP Exam (page: 1)
PMI -SP Scheduling Professional
Updated on: 30-Nov-2025

Viewing Page 1 of 67

Once the project's WBS has been created what process may happen next?

  1. Estimate activity resources
  2. Define activities
  3. Estimate activity durations
  4. Sequence activities

Answer(s): B

Explanation:

The define activities process is the process that may begin once the project's WBS has been completed and approved. It is possible, in some projects, to complete the WBS and the activity list at the same time.
Answer option D is incorrect. Sequencing the activities cannot happen until the activity list has been created.
Answer option A is incorrect. Estimating activity resources is dependent on the activity list, so this choice is not valid.
Answer option C is incorrect. Estimate activity durations are dependent on the activity list, so this choice is not valid.



Which of the following scheduling techniques identifies the successor activities and the predecessor activities to assist the project manager in sequencing the project work?

  1. Precedence Diagramming Method
  2. Schedule network template
  3. Dependency determination
  4. Activity on the Node

Answer(s): A

Explanation:

The Precedence Diagramming Method uses both predecessors and successors as nodes in theproject network diagram. The PDM approach is the most common network diagram approach used.
Answer option C is incorrect. Dependency determination identifies the order of the project work.
Answer option B is incorrect. The schedule network template is a tool that uses a previous project network diagram as a base for the current project network diagram.
Answer option D is incorrect. Activity on the node laces activities on circles within a network diagram. It is an example of the precedence diagramming method.



You are the project manager of the NHGQ project for your company. You must create and distribute performance reports every week to your key project stakeholders.
What communication technique do you normally use to distribute reports?

  1. Push technique
  2. Many-to-many
  3. One-to-one
  4. Pull technique

Answer(s): A

Explanation:

Performance reports are distributed through the push technique. This means that the project manager distributes the reports regularly through a mechanism, such as email.
Answer option C is incorrect. One-to-one technique describes a conversation between two people.
Answer option B is incorrect. Many-to-many technique describes a conversation between many people.
Answer option D is incorrect. A pull technique describes the recipients of the report "pulling" the information, such as from a Website.



Your project team is executing the project plan and things are going well. Your team has reached its first milestone and is now in the second phase of the project. The project stakeholders have requested that you find a method to reduce the duration of the project. They will reward you and your project team with a 25 percent bonus of the project costs if you can finish the project thirty days earlier than what was already planned. The stakeholders, however, will not approve any additional labor costs as part of the agreement.
Which approach could you use to shorten the duration of the project?

  1. Perform resource leveling for the project.
  2. Crash the project schedule.
  3. Fast track the project.
  4. Remove things from the project scope.

Answer(s): C

Explanation:

Fast tracking is a technique for compressing project schedule. In fast tracking, phases are overlapped that would normally be done in sequence. It is shortening the project schedule without reducing the project scope. It does not add any additional labor but it can introduce project risks.
Answer option D is incorrect. Removing things from the project scope can reduce the project duration, but it will not satisfy the requirements the stakeholders have identified.
Answer option A is incorrect. Resource leveling can actually increase the project duration.
Answer option B is incorrect. Crashing can reduce the project duration but it increases the labor expense, something the stakeholders won't approve.



The Define Activities process is the first process in the project time management knowledge area. The Define Activities process creates just three outputs as a result of decomposition, rolling wave planning, templates, and expert judgment.
Which one of the following is not an output of the Define Activities process?

  1. Activity list
  2. Milestone list
  3. Activity attributes
  4. Project document updates

Answer(s): D

Explanation:

Project document updates are not an output of the Define Activities process. Project document updates are the outputs for estimate activity resources. Project document updates include the following:
Activity list Activity attributes Resource calendars
Answer option A is incorrect. The activity list is an output of the define activities process.
Answer option C is incorrect. The activity attributes is an output of the define activities process.
Answer option B is incorrect. The milestone list is an output of the define activities process.



Viewing Page 1 of 67



Share your comments for PMI PMI-SP exam with other users:

Naveed 8/28/2023 2:48:00 AM

good questions with simple explanation
UNITED STATES


cert 9/24/2023 4:53:00 PM

admin guide (windows) respond to malicious causality chains. when the cortex xdr agent identifies a remote network connection that attempts to perform malicious activity—such as encrypting endpoint files—the agent can automatically block the ip address to close all existing communication and block new connections from this ip address to the endpoint. when cortex xdrblocks an ip address per endpoint, that address remains blocked throughout all agent profiles and policies, including any host-firewall policy rules. you can view the list of all blocked ip addresses per endpoint from the action center, as well as unblock them to re-enable communication as appropriate. this module is supported with cortex xdr agent 7.3.0 and later. select the action mode to take when the cortex xdr agent detects remote malicious causality chains: enabled (default)—terminate connection and block ip address of the remote connection. disabled—do not block remote ip addresses. to allow specific and known s
Anonymous


Yves 8/29/2023 8:46:00 PM

very inciting
Anonymous


Miguel 10/16/2023 11:18:00 AM

question 5, it seems a instead of d, because: - care plan = case - patient = person account - product = product2;
SPAIN


Byset 9/25/2023 12:49:00 AM

it look like real one
Anonymous


Debabrata Das 8/28/2023 8:42:00 AM

i am taking oracle fcc certification test next two days, pls share question dumps
Anonymous


nITA KALE 8/22/2023 1:57:00 AM

i need dumps
Anonymous


CV 9/9/2023 1:54:00 PM

its time to comptia sec+
GREECE


SkepticReader 8/1/2023 8:51:00 AM

question 35 has an answer for a different question. i believe the answer is "a" because it shut off the firewall. "0" in registry data means that its false (aka off).
UNITED STATES


Nabin 10/16/2023 4:58:00 AM

helpful content
MALAYSIA


Blessious Phiri 8/15/2023 3:19:00 PM

oracle 19c is complex db
Anonymous


Sreenivas 10/24/2023 12:59:00 AM

helpful for practice
Anonymous


Liz 9/11/2022 11:27:00 PM

support team is fast and deeply knowledgeable. i appreciate that a lot.
UNITED STATES


Namrata 7/15/2023 2:22:00 AM

helpful questions
Anonymous


lipsa 11/8/2023 12:54:00 PM

thanks for question
Anonymous


Eli 6/18/2023 11:27:00 PM

the software is provided for free so this is a big change. all other sites are charging for that. also that fucking examtopic site that says free is not free at all. you are hit with a pay-wall.
EUROPEAN UNION


open2exam 10/29/2023 1:14:00 PM

i need exam questions nca 6.5 any help please ?
Anonymous


Gerald 9/11/2023 12:22:00 PM

just took the comptia cybersecurity analyst (cysa+) - wished id seeing this before my exam
UNITED STATES


ryo 9/10/2023 2:27:00 PM

very helpful
MEXICO


Jamshed 6/20/2023 4:32:00 AM

i need this exam
PAKISTAN


Roberto Capra 6/14/2023 12:04:00 PM

nice questions... are these questions the same of the exam?
Anonymous


Synt 5/23/2023 9:33:00 PM

need to view
UNITED STATES


Vey 5/27/2023 12:06:00 AM

highly appreciate for your sharing.
CAMBODIA


Tshepang 8/18/2023 4:41:00 AM

kindly share this dump. thank you
Anonymous


Jay 9/26/2023 8:00:00 AM

link plz for download
UNITED STATES


Leo 10/30/2023 1:11:00 PM

data quality oecd
Anonymous


Blessious Phiri 8/13/2023 9:35:00 AM

rman is one good recovery technology
Anonymous


DiligentSam 9/30/2023 10:26:00 AM

need it thx
Anonymous


Vani 8/10/2023 8:11:00 PM

good questions
NEW ZEALAND


Fares 9/11/2023 5:00:00 AM

good one nice revision
Anonymous


Lingaraj 10/26/2023 1:27:00 AM

i love this thank you i need
Anonymous


Muhammad Rawish Siddiqui 12/5/2023 12:38:00 PM

question # 142: data governance is not one of the deliverables in the document and content management context diagram.
SAUDI ARABIA


al 6/7/2023 10:25:00 AM

most answers not correct here
Anonymous


Bano 1/19/2024 2:29:00 AM

what % of questions do we get in the real exam?
UNITED STATES