PMI PMI-SP Exam (page: 1)
PMI -SP Scheduling Professional
Updated on: 12-Oct-2025

Viewing Page 1 of 67

Once the project's WBS has been created what process may happen next?

  1. Estimate activity resources
  2. Define activities
  3. Estimate activity durations
  4. Sequence activities

Answer(s): B

Explanation:

The define activities process is the process that may begin once the project's WBS has been completed and approved. It is possible, in some projects, to complete the WBS and the activity list at the same time.
Answer option D is incorrect. Sequencing the activities cannot happen until the activity list has been created.
Answer option A is incorrect. Estimating activity resources is dependent on the activity list, so this choice is not valid.
Answer option C is incorrect. Estimate activity durations are dependent on the activity list, so this choice is not valid.



Which of the following scheduling techniques identifies the successor activities and the predecessor activities to assist the project manager in sequencing the project work?

  1. Precedence Diagramming Method
  2. Schedule network template
  3. Dependency determination
  4. Activity on the Node

Answer(s): A

Explanation:

The Precedence Diagramming Method uses both predecessors and successors as nodes in theproject network diagram. The PDM approach is the most common network diagram approach used.
Answer option C is incorrect. Dependency determination identifies the order of the project work.
Answer option B is incorrect. The schedule network template is a tool that uses a previous project network diagram as a base for the current project network diagram.
Answer option D is incorrect. Activity on the node laces activities on circles within a network diagram. It is an example of the precedence diagramming method.



You are the project manager of the NHGQ project for your company. You must create and distribute performance reports every week to your key project stakeholders.
What communication technique do you normally use to distribute reports?

  1. Push technique
  2. Many-to-many
  3. One-to-one
  4. Pull technique

Answer(s): A

Explanation:

Performance reports are distributed through the push technique. This means that the project manager distributes the reports regularly through a mechanism, such as email.
Answer option C is incorrect. One-to-one technique describes a conversation between two people.
Answer option B is incorrect. Many-to-many technique describes a conversation between many people.
Answer option D is incorrect. A pull technique describes the recipients of the report "pulling" the information, such as from a Website.



Your project team is executing the project plan and things are going well. Your team has reached its first milestone and is now in the second phase of the project. The project stakeholders have requested that you find a method to reduce the duration of the project. They will reward you and your project team with a 25 percent bonus of the project costs if you can finish the project thirty days earlier than what was already planned. The stakeholders, however, will not approve any additional labor costs as part of the agreement.
Which approach could you use to shorten the duration of the project?

  1. Perform resource leveling for the project.
  2. Crash the project schedule.
  3. Fast track the project.
  4. Remove things from the project scope.

Answer(s): C

Explanation:

Fast tracking is a technique for compressing project schedule. In fast tracking, phases are overlapped that would normally be done in sequence. It is shortening the project schedule without reducing the project scope. It does not add any additional labor but it can introduce project risks.
Answer option D is incorrect. Removing things from the project scope can reduce the project duration, but it will not satisfy the requirements the stakeholders have identified.
Answer option A is incorrect. Resource leveling can actually increase the project duration.
Answer option B is incorrect. Crashing can reduce the project duration but it increases the labor expense, something the stakeholders won't approve.



The Define Activities process is the first process in the project time management knowledge area. The Define Activities process creates just three outputs as a result of decomposition, rolling wave planning, templates, and expert judgment.
Which one of the following is not an output of the Define Activities process?

  1. Activity list
  2. Milestone list
  3. Activity attributes
  4. Project document updates

Answer(s): D

Explanation:

Project document updates are not an output of the Define Activities process. Project document updates are the outputs for estimate activity resources. Project document updates include the following:
Activity list Activity attributes Resource calendars
Answer option A is incorrect. The activity list is an output of the define activities process.
Answer option C is incorrect. The activity attributes is an output of the define activities process.
Answer option B is incorrect. The milestone list is an output of the define activities process.



Viewing Page 1 of 67



Share your comments for PMI PMI-SP exam with other users:

asad Raza 5/15/2023 5:38:00 AM

please upload this exam
CHINA


Reeta 7/17/2023 5:22:00 PM

please upload the c_activate22 dump questions with answer
SWEDEN


Wong 12/20/2023 11:34:00 AM

q10 - the answer should be a. if its c, the criteria will meet if either the prospect is not part of the suppression lists or if the job title contains vice president
MALAYSIA


david 12/12/2023 12:38:00 PM

this was on the exam as of 1211/2023
Anonymous


Tink 7/24/2023 9:23:00 AM

great for prep
GERMANY


Jaro 12/18/2023 3:12:00 PM

i think in question 7 the first answer should be power bi portal (not power bi)
Anonymous


9eagles 4/7/2023 10:04:00 AM

on question 10 and so far 2 wrong answers as evident in the included reference link.
Anonymous


Tai 8/28/2023 5:28:00 AM

wonderful material
SOUTH AFRICA


VoiceofMidnight 12/29/2023 4:48:00 PM

i passed!! ...but barely! got 728, but needed 720 to pass. the exam hit me with labs right out of the gate! then it went to multiple choice. protip: study the labs!
UNITED STATES


A K 8/3/2023 11:56:00 AM

correct answer for question 92 is c -aws shield
Anonymous


Nitin Mindhe 11/27/2023 6:12:00 AM

great !! it is really good
IRELAND


BailleyOne 11/22/2023 1:45:00 AM

explanations for the answers are to the point.
Anonymous


patel 10/25/2023 8:17:00 AM

how can rea next
INDIA


MortonG 10/19/2023 6:32:00 PM

question: 128 d is the wrong answer...should be c
EUROPEAN UNION


Jayant 11/2/2023 3:15:00 AM

thanks for az 700 dumps
Anonymous


Bipul Mishra 12/14/2023 7:12:00 AM

thank you for this tableau dumps . it will helpfull for tableau certification
UNITED STATES


hello 10/31/2023 12:07:00 PM

good content
Anonymous


Matheus 9/3/2023 2:14:00 PM

just testing if the comments are real
UNITED STATES


yenvti2@gmail.com 8/12/2023 7:56:00 PM

very helpful for exam preparation
Anonymous


Miguel 10/5/2023 12:16:00 PM

question 11: https://help.salesforce.com/s/articleview?id=sf.admin_lead_to_patient_setup_overview.htm&type=5
SPAIN


Noushin 11/28/2023 4:52:00 PM

i think the answer to question 42 is b not c
CANADA


susan sandivore 8/28/2023 1:00:00 AM

thanks for the dump
Anonymous


Aderonke 10/31/2023 12:51:00 AM

fantastic assessments
Anonymous


Priscila 7/22/2022 9:59:00 AM

i find the xengine test engine simulator to be more fun than reading from pdf.
GERMANY


suresh 12/16/2023 10:54:00 PM

nice document
Anonymous


Wali 6/4/2023 10:07:00 PM

thank you for making the questions and answers intractive and selectable.
UNITED STATES


Nawaz 7/18/2023 1:10:00 AM

answers are correct?
UNITED STATES


das 6/23/2023 7:57:00 AM

can i belive this dump
INDIA


Sanjay 10/15/2023 1:34:00 PM

great site to practice for sitecore exam
INDIA


jaya 12/17/2023 8:36:00 AM

good for students
UNITED STATES


Bsmaind 8/20/2023 9:23:00 AM

nice practice dumps
Anonymous


kumar 11/15/2023 11:24:00 AM

nokia 4a0-114 dumps
Anonymous


Vetri 10/3/2023 12:59:00 AM

great content and wonderful to have the answers with explanation
UNITED STATES


Ranjith 8/21/2023 3:39:00 PM

for question #118, the answer is option c. the screen shot is showing the drop down, but the answer is marked incorrectly please update . thanks for sharing such nice questions.
Anonymous