PMI PMI-SP Exam (page: 1)
PMI -SP Scheduling Professional
Updated on: 12-Jan-2026

Viewing Page 1 of 67

Once the project's WBS has been created what process may happen next?

  1. Estimate activity resources
  2. Define activities
  3. Estimate activity durations
  4. Sequence activities

Answer(s): B

Explanation:

The define activities process is the process that may begin once the project's WBS has been completed and approved. It is possible, in some projects, to complete the WBS and the activity list at the same time.
Answer option D is incorrect. Sequencing the activities cannot happen until the activity list has been created.
Answer option A is incorrect. Estimating activity resources is dependent on the activity list, so this choice is not valid.
Answer option C is incorrect. Estimate activity durations are dependent on the activity list, so this choice is not valid.



Which of the following scheduling techniques identifies the successor activities and the predecessor activities to assist the project manager in sequencing the project work?

  1. Precedence Diagramming Method
  2. Schedule network template
  3. Dependency determination
  4. Activity on the Node

Answer(s): A

Explanation:

The Precedence Diagramming Method uses both predecessors and successors as nodes in theproject network diagram. The PDM approach is the most common network diagram approach used.
Answer option C is incorrect. Dependency determination identifies the order of the project work.
Answer option B is incorrect. The schedule network template is a tool that uses a previous project network diagram as a base for the current project network diagram.
Answer option D is incorrect. Activity on the node laces activities on circles within a network diagram. It is an example of the precedence diagramming method.



You are the project manager of the NHGQ project for your company. You must create and distribute performance reports every week to your key project stakeholders.
What communication technique do you normally use to distribute reports?

  1. Push technique
  2. Many-to-many
  3. One-to-one
  4. Pull technique

Answer(s): A

Explanation:

Performance reports are distributed through the push technique. This means that the project manager distributes the reports regularly through a mechanism, such as email.
Answer option C is incorrect. One-to-one technique describes a conversation between two people.
Answer option B is incorrect. Many-to-many technique describes a conversation between many people.
Answer option D is incorrect. A pull technique describes the recipients of the report "pulling" the information, such as from a Website.



Your project team is executing the project plan and things are going well. Your team has reached its first milestone and is now in the second phase of the project. The project stakeholders have requested that you find a method to reduce the duration of the project. They will reward you and your project team with a 25 percent bonus of the project costs if you can finish the project thirty days earlier than what was already planned. The stakeholders, however, will not approve any additional labor costs as part of the agreement.
Which approach could you use to shorten the duration of the project?

  1. Perform resource leveling for the project.
  2. Crash the project schedule.
  3. Fast track the project.
  4. Remove things from the project scope.

Answer(s): C

Explanation:

Fast tracking is a technique for compressing project schedule. In fast tracking, phases are overlapped that would normally be done in sequence. It is shortening the project schedule without reducing the project scope. It does not add any additional labor but it can introduce project risks.
Answer option D is incorrect. Removing things from the project scope can reduce the project duration, but it will not satisfy the requirements the stakeholders have identified.
Answer option A is incorrect. Resource leveling can actually increase the project duration.
Answer option B is incorrect. Crashing can reduce the project duration but it increases the labor expense, something the stakeholders won't approve.



The Define Activities process is the first process in the project time management knowledge area. The Define Activities process creates just three outputs as a result of decomposition, rolling wave planning, templates, and expert judgment.
Which one of the following is not an output of the Define Activities process?

  1. Activity list
  2. Milestone list
  3. Activity attributes
  4. Project document updates

Answer(s): D

Explanation:

Project document updates are not an output of the Define Activities process. Project document updates are the outputs for estimate activity resources. Project document updates include the following:
Activity list Activity attributes Resource calendars
Answer option A is incorrect. The activity list is an output of the define activities process.
Answer option C is incorrect. The activity attributes is an output of the define activities process.
Answer option B is incorrect. The milestone list is an output of the define activities process.



Viewing Page 1 of 67



Share your comments for PMI PMI-SP exam with other users:

Rasha 6/29/2023 8:23:00 PM

yes .. i need the dump if you can help me
Anonymous


Anonymous 7/25/2023 8:05:00 AM

good morning, could you please upload this exam again?
SPAIN


AJ 9/24/2023 9:32:00 AM

hi please upload sre foundation and practitioner exam questions
Anonymous


peter parker 8/10/2023 10:59:00 AM

the exam is listed as 80 questions with a pass mark of 70%, how is your 50 questions related?
Anonymous


Berihun 7/13/2023 7:29:00 AM

all questions are so important and covers all ccna modules
Anonymous


nspk 1/19/2024 12:53:00 AM

q 44. ans:- b (goto setup > order settings > select enable optional price books for orders) reference link --> https://resources.docs.salesforce.com/latest/latest/en-us/sfdc/pdf/sfom_impl_b2b_b2b2c.pdf(decide whether you want to enable the optional price books feature. if so, select enable optional price books for orders. you can use orders in salesforce while managing price books in an external platform. if you’re using d2c commerce, you must select enable optional price books for orders.)
Anonymous


Muhammad Rawish Siddiqui 12/2/2023 5:28:00 AM

"cost of replacing data if it were lost" is also correct.
SAUDI ARABIA


Anonymous 7/14/2023 3:17:00 AM

pls upload the questions
UNITED STATES


Mukesh 7/10/2023 4:14:00 PM

good questions
UNITED KINGDOM


Elie Abou Chrouch 12/11/2023 3:38:00 AM

question 182 - correct answer is d. ethernet frame length is 64 - 1518b. length of user data containing is that frame: 46 - 1500b.
Anonymous


Damien 9/23/2023 8:37:00 AM

i need this exam pls
Anonymous


Nani 9/10/2023 12:02:00 PM

its required for me, please make it enable to access. thanks
UNITED STATES


ethiopia 8/2/2023 2:18:00 AM

seems good..
ETHIOPIA


whoAreWeReally 12/19/2023 8:29:00 PM

took the test last week, i did have about 15 - 20 word for word from this site on the test. (only was able to cram 600 of the questions from this site so maybe more were there i didnt review) had 4 labs, bgp, lacp, vrf with tunnels and actually had to skip a lab due to time. lots of automation syntax questions.
EUROPEAN UNION


vs 9/2/2023 12:19:00 PM

no comments
Anonymous


john adenu 11/14/2023 11:02:00 AM

nice questions bring out the best in you.
Anonymous


Osman 11/21/2023 2:27:00 PM

really helpful
Anonymous


Edward 9/13/2023 5:27:00 PM

question #50 and question #81 are exactly the same questions, azure site recovery provides________for virtual machines. the first says that it is fault tolerance is the answer and second says disater recovery. from my research, it says it should be disaster recovery. can anybody explain to me why? thank you
CANADA


Monti 5/24/2023 11:14:00 PM

iam thankful for these exam dumps questions, i would not have passed without this exam dumps.
UNITED STATES


Anon 10/25/2023 10:48:00 PM

some of the answers seem to be inaccurate. q10 for example shouldnt it be an m custom column?
MALAYSIA


PeterPan 10/18/2023 10:22:00 AM

are the question real or fake?
Anonymous


CW 7/11/2023 3:19:00 PM

thank you for providing such assistance.
UNITED STATES


Mn8300 11/9/2023 8:53:00 AM

nice questions
Anonymous


Nico 4/23/2023 11:41:00 PM

my 3rd purcahse from this site. these exam dumps are helpful. very helpful.
ITALY


Chere 9/15/2023 4:21:00 AM

found it good
Anonymous


Thembelani 5/30/2023 2:47:00 AM

excellent material
Anonymous


vinesh phale 9/11/2023 2:51:00 AM

very helpfull
UNITED STATES


Bhagiii 11/4/2023 7:04:00 AM

well explained.
Anonymous


Rahul 8/8/2023 9:40:00 PM

i need the pdf, please.
CANADA


CW 7/11/2023 2:51:00 PM

a good source for exam preparation
UNITED STATES


Anchal 10/23/2023 4:01:00 PM

nice questions
INDIA


J Nunes 9/29/2023 8:19:00 AM

i need ielts general training audio guide questions
BRAZIL


Ananya 9/14/2023 5:16:00 AM

please make this content available
UNITED STATES


Swathi 6/4/2023 2:18:00 PM

content is good
Anonymous