PMI PMI-SP Exam (page: 1)
PMI -SP Scheduling Professional
Updated on: 26-Jul-2025

Viewing Page 1 of 67

Once the project's WBS has been created what process may happen next?

  1. Estimate activity resources
  2. Define activities
  3. Estimate activity durations
  4. Sequence activities

Answer(s): B

Explanation:

The define activities process is the process that may begin once the project's WBS has been completed and approved. It is possible, in some projects, to complete the WBS and the activity list at the same time.
Answer option D is incorrect. Sequencing the activities cannot happen until the activity list has been created.
Answer option A is incorrect. Estimating activity resources is dependent on the activity list, so this choice is not valid.
Answer option C is incorrect. Estimate activity durations are dependent on the activity list, so this choice is not valid.



Which of the following scheduling techniques identifies the successor activities and the predecessor activities to assist the project manager in sequencing the project work?

  1. Precedence Diagramming Method
  2. Schedule network template
  3. Dependency determination
  4. Activity on the Node

Answer(s): A

Explanation:

The Precedence Diagramming Method uses both predecessors and successors as nodes in theproject network diagram. The PDM approach is the most common network diagram approach used.
Answer option C is incorrect. Dependency determination identifies the order of the project work.
Answer option B is incorrect. The schedule network template is a tool that uses a previous project network diagram as a base for the current project network diagram.
Answer option D is incorrect. Activity on the node laces activities on circles within a network diagram. It is an example of the precedence diagramming method.



You are the project manager of the NHGQ project for your company. You must create and distribute performance reports every week to your key project stakeholders.
What communication technique do you normally use to distribute reports?

  1. Push technique
  2. Many-to-many
  3. One-to-one
  4. Pull technique

Answer(s): A

Explanation:

Performance reports are distributed through the push technique. This means that the project manager distributes the reports regularly through a mechanism, such as email.
Answer option C is incorrect. One-to-one technique describes a conversation between two people.
Answer option B is incorrect. Many-to-many technique describes a conversation between many people.
Answer option D is incorrect. A pull technique describes the recipients of the report "pulling" the information, such as from a Website.



Your project team is executing the project plan and things are going well. Your team has reached its first milestone and is now in the second phase of the project. The project stakeholders have requested that you find a method to reduce the duration of the project. They will reward you and your project team with a 25 percent bonus of the project costs if you can finish the project thirty days earlier than what was already planned. The stakeholders, however, will not approve any additional labor costs as part of the agreement.
Which approach could you use to shorten the duration of the project?

  1. Perform resource leveling for the project.
  2. Crash the project schedule.
  3. Fast track the project.
  4. Remove things from the project scope.

Answer(s): C

Explanation:

Fast tracking is a technique for compressing project schedule. In fast tracking, phases are overlapped that would normally be done in sequence. It is shortening the project schedule without reducing the project scope. It does not add any additional labor but it can introduce project risks.
Answer option D is incorrect. Removing things from the project scope can reduce the project duration, but it will not satisfy the requirements the stakeholders have identified.
Answer option A is incorrect. Resource leveling can actually increase the project duration.
Answer option B is incorrect. Crashing can reduce the project duration but it increases the labor expense, something the stakeholders won't approve.



The Define Activities process is the first process in the project time management knowledge area. The Define Activities process creates just three outputs as a result of decomposition, rolling wave planning, templates, and expert judgment.
Which one of the following is not an output of the Define Activities process?

  1. Activity list
  2. Milestone list
  3. Activity attributes
  4. Project document updates

Answer(s): D

Explanation:

Project document updates are not an output of the Define Activities process. Project document updates are the outputs for estimate activity resources. Project document updates include the following:
Activity list Activity attributes Resource calendars
Answer option A is incorrect. The activity list is an output of the define activities process.
Answer option C is incorrect. The activity attributes is an output of the define activities process.
Answer option B is incorrect. The milestone list is an output of the define activities process.



Viewing Page 1 of 67



Share your comments for PMI PMI-SP exam with other users:

sushant 6/28/2023 4:38:00 AM

please upoad
EUROPEAN UNION


John 8/7/2023 12:09:00 AM

has anyone recently attended safe 6.0 certification? is it the samq question from here.
Anonymous


Blessious Phiri 8/14/2023 3:49:00 PM

expository experience
Anonymous


concerned citizen 12/29/2023 11:31:00 AM

52 should be b&c. controller failure has nothing to do with this type of issue. degraded state tells us its a raid issue, and if the os is missing then the bootable device isnt found. the only other consideration could be data loss but thats somewhat broad whereas b&c show understanding of the specific issues the question is asking about.
UNITED STATES


deedee 12/23/2023 5:10:00 PM

great help!!!
UNITED STATES


Samir 8/1/2023 3:07:00 PM

very useful tools
UNITED STATES


Saeed 11/7/2023 3:14:00 AM

looks a good platform to prepare az-104
Anonymous


Matiullah 6/24/2023 7:37:00 AM

want to pass the exam
Anonymous


SN 9/5/2023 2:25:00 PM

good resource
UNITED STATES


Zoubeyr 9/8/2023 5:56:00 AM

question 11 : d
FRANCE


User 8/29/2023 3:24:00 AM

only the free dumps will be enough for pass, or have to purchase the premium one. please suggest.
Anonymous


CW 7/6/2023 7:37:00 PM

good questions. thanks.
Anonymous


Farooqi 11/21/2023 1:37:00 AM

good for practice.
INDIA


Isaac 10/28/2023 2:30:00 PM

great case study
UNITED STATES


Malviya 2/3/2023 9:10:00 AM

the questions in this exam dumps is valid. i passed my test last monday. i only whish they had their pricing in inr instead of usd. but it is still worth it.
INDIA


rsmyth 5/18/2023 12:44:00 PM

q40 the answer is not d, why are you giving incorrect answers? snapshot consolidation is used to merge the snapshot delta disk files to the vm base disk
IRELAND


Keny 6/23/2023 9:00:00 PM

thanks, very relevant
PERU


Muhammad Rawish Siddiqui 11/29/2023 12:14:00 PM

wrong answer. it is true not false.
SAUDI ARABIA


Josh 7/10/2023 1:54:00 PM

please i need the mo-100 questions
Anonymous


VINNY 6/2/2023 11:59:00 AM

very good use full
Anonymous


Andy 12/6/2023 5:56:00 AM

very valid questions
Anonymous


Mamo 8/12/2023 7:46:00 AM

will these question help me to clear pl-300 exam?
UNITED STATES


Marial Manyang 7/26/2023 10:13:00 AM

please provide me with these dumps questions. thanks
Anonymous


Amel Mhamdi 12/16/2022 10:10:00 AM

in the pdf downloaded is write google cloud database engineer i think that it isnt the correct exam
FRANCE


Angel 8/30/2023 10:58:00 PM

i think you have the answers wrong regarding question: "what are three core principles of web content accessibility guidelines (wcag)? answer: robust, operable, understandable
UNITED STATES


SH 5/16/2023 1:43:00 PM

these questions are not valid , they dont come for the exam now
UNITED STATES


sudhagar 9/6/2023 3:02:00 PM

question looks valid
UNITED STATES


Van 11/24/2023 4:02:00 AM

good for practice
Anonymous


Divya 8/2/2023 6:54:00 AM

need more q&a to go ahead
Anonymous


Rakesh 10/6/2023 3:06:00 AM

question 59 - a newly-created role is not assigned to any user, nor granted to any other role. answer is b https://docs.snowflake.com/en/user-guide/security-access-control-overview
Anonymous


Nik 11/10/2023 4:57:00 AM

just passed my exam today. i saw all of these questions in my text today. so i can confirm this is a valid dump.
HONG KONG


Deep 6/12/2023 7:22:00 AM

needed dumps
INDIA


tumz 1/16/2024 10:30:00 AM

very helpful
UNITED STATES


NRI 8/27/2023 10:05:00 AM

will post once the exam is finished
UNITED STATES