PMI PMI-SP Exam (page: 2)
PMI -SP Scheduling Professional
Updated on: 26-Jul-2025

Viewing Page 2 of 67

Examine the figure given below:



If Activity B takes eight days to complete instead of five days as schedule, how long can you now delay Activity H?

  1. Three days
  2. One day
  3. Four days
  4. Zero days

Answer(s): B

Explanation:

Activity B is not on the critical path and it has a total of four days of float. If Activity B takes a total of eight days, it will consume three days of float. However, the total duration of the path ABEHJ may not exceed 26 days, as this is the total duration for the project. Although Activity H has a total of four days of float available, the consumption of three days of float on this path will reduce the total float for Activity H to just one day. If Activity H is delayed by more than one day, then the project will be late.
Answer option D is incorrect. There is one day of float still available for Activity H. Answer options A and C are incorrect. These are not the valid answers, as there is just one day of float available for Activity H.



You are the project manager of the GHT Project. Ben, one of your project team members, does not understand the idea of a milestone.
Which of the following best describes what a milestone is?

  1. A significant point in the project
  2. A goal of reaching a significant delivery of project benefits by an identified date
  3. An imposed date for the project to reach a given point
  4. The completion of a project activity that is crucial to project completion

Answer(s): A

Explanation:

A milestone is simply a significant point or event in the project. It does not have to be assigned to a specific date, but is usually assigned to the completion of project phases. A milestone is the end of a stage that marks the completion of a work package or phase, typically mark d by a high level event such as completion, endorsement or signing of a deliverable, document or a high level review meeting. In addition to signaling the completion of a key deliverable, a milestone may also signify an important decision or the derivation of a critical piece of information, which outlines or affects the future of a project. In this sense, a milestone not only signifies distance traveled (key stages in a project) but also indicates direction of travel since key decisions made at milestones may alter the route through the project plan. To create a milestone, enter 0 (zero) in the Duration field. The task will automatically be classified as a milestone.
Answer option C is incorrect. This is a project constraint.
Answer option B is incorrect. A project goal is an objective for time, cost, scope, and other metrics.
Answer option D is incorrect. All activities must be completed in order to complete the project work. Activities that are not completed are quality issues that prevent the project from completing the project scope.



You are the project manager of the GHY Project. Management wants you to create a process improvement plan for your project. Your project will be studied by management and will become a standard for all future organizational projects based on your project's performance, approach, and implementation of project processes.
All of the following should be included in your project's process improvement plan except for which one?

  1. Process boundaries
  2. Process configuration
  3. Targets for improved performance
  4. Identification of project risks

Answer(s): D

Explanation:

Identification of the project risks is not part of the process improvement plan. Identify risks is a risk management process, and risks are recorded in the risk register. Answer options A, B, and C are incorrect. Process boundaries, Process configuration and Targets for improved performance are parts of the process improvement plan.



George is the project manager of the NHQ Project and has a budget of $778,000. The project is scheduled to last for one year with an equal amount of work completed each quarter. The second quarter of the project has ended and George has spent $325,000 but has only finished forty percent of the project. Management needs a variance report for the project schedule.
What value should George report in this instance?

  1. .96
  2. -$77,800
  3. $-34,500
  4. -$13,800

Answer(s): B

Explanation:

Schedule variance (SV) is a measure of schedule performance on a project. The variance notifies that the schedule is ahead or behind what was planned for this period in time. The schedule variance is calculated based on the following formula: SV = Earned Value (EV) - Planned Value (PV) If the resulting schedule is negative, it indicates that the project is behind schedule. A value greater than 0 shows that the project is ahead of the planned schedule. A value of 0 indicates that the project is right on target. The earned value in this instance is forty percent of the project budget, $778,000, and the planned value is $398,000 because George is to be fifty percent done at the end of the second quarter, as the work is spread evenly across all quarters. The schedule variance is -$77,800 for the project.
Answer option A is incorrect. .96 represents the cost performance index.
Answer option C is incorrect. -$34,500 represents the project's variance at completion if the project continues as is.
Answer option D is incorrect. -$13,800 is the cost variance for the project.



You are the project manager of the NHQ Project. Management has set a conformance to the project schedule for your project at 0.95.
What does this term mean?

  1. It means the largest schedule variance you can have is five percent.
  2. It is the earned value divided by the planned value for your project.
  3. It is the expectation of management to be 95 on schedule at 95 percent of the project.
  4. It means you will need to earn at least 95 cents per dollar invested in the project.

Answer(s): A

Explanation:

Conformance to schedule is a required adherence for the project's schedule. In this instance, the project manager must not allow the schedule to slip more than five percent.
Answer option B is incorrect. This is the description of the schedule performance index.
Answer option D is incorrect. This is the description of the cost performance index.
Answer option C is incorrect. This is not a valid statement about the project performance.



Viewing Page 2 of 67



Share your comments for PMI PMI-SP exam with other users:

treyf 11/9/2023 5:13:00 AM

i took the aws saa-c03 test and scored 935/1000. it has all the exam dumps and important info.
UNITED STATES


anonymous 1/11/2024 4:50:00 AM

good questions
Anonymous


Anjum 9/23/2023 6:22:00 PM

well explained
Anonymous


Thakor 6/7/2023 11:52:00 PM

i got the full version and it helped me pass the exam. pdf version is very good.
INDIA


sartaj 7/18/2023 11:36:00 AM

provide the download link, please
INDIA


loso 7/25/2023 5:18:00 AM

please upload thank.
THAILAND


Paul 6/23/2023 7:12:00 AM

please can you share 1z0-1055-22 dump pls
UNITED STATES


exampei 10/7/2023 8:14:00 AM

i will wait impatiently. thank youu
Anonymous


Prince 10/31/2023 9:09:00 PM

is it possible to clear the exam if we focus on only these 156 questions instead of 623 questions? kindly help!
Anonymous


Ali Azam 12/7/2023 1:51:00 AM

really helped with preparation of my scrum exam
Anonymous


Jerman 9/29/2023 8:46:00 AM

very informative and through explanations
Anonymous


Jimmy 11/4/2023 12:11:00 PM

prep for exam
INDONESIA


Abhi 9/19/2023 1:22:00 PM

thanks for helping us
Anonymous


mrtom33 11/20/2023 4:51:00 AM

i prepared for the eccouncil 350-401 exam. i scored 92% on the test.
Anonymous


JUAN 6/28/2023 2:12:00 AM

aba questions to practice
UNITED STATES


LK 1/2/2024 11:56:00 AM

great content
Anonymous


Srijeeta 10/8/2023 6:24:00 AM

how do i get the remaining questions?
INDIA


Jovanne 7/26/2022 11:42:00 PM

well formatted pdf and the test engine software is free. well worth the money i sept.
ITALY


CHINIMILLI SATISH 8/29/2023 6:22:00 AM

looking for 1z0-116
Anonymous


Pedro Afonso 1/15/2024 8:01:00 AM

in question 22, shouldnt be in the data (option a) layer?
Anonymous


Pushkar 11/7/2022 12:12:00 AM

the questions are incredibly close to real exam. you people are amazing.
INDIA


Ankit S 11/13/2023 3:58:00 AM

q15. answer is b. simple
UNITED STATES


S. R 12/8/2023 9:41:00 AM

great practice
FRANCE


Mungara 3/14/2023 12:10:00 AM

thanks to this exam dumps, i felt confident and passed my exam with ease.
UNITED STATES


Anonymous 7/25/2023 2:55:00 AM

need 1z0-1105-22 exam
Anonymous


Nigora 5/31/2022 10:05:00 PM

this is a beautiful tool. passed after a week of studying.
UNITED STATES


Av dey 8/16/2023 2:35:00 PM

can you please upload the dumps for 1z0-1096-23 for oracle
INDIA


Mayur Shermale 11/23/2023 12:22:00 AM

its intresting, i would like to learn more abouth this
JAPAN


JM 12/19/2023 2:23:00 PM

q252: dns poisoning is the correct answer, not locator redirection. beaconing is detected from a host. this indicates that the system has been infected with malware, which could be the source of local dns poisoning. location redirection works by either embedding the redirection in the original websites code or having a user click on a url that has an embedded redirect. since users at a different office are not getting redirected, it isnt an embedded redirection on the original website and since the user is manually typing in the url and not clicking a link, it isnt a modified link.
UNITED STATES


Freddie 12/12/2023 12:37:00 PM

helpful dump questions
SOUTH AFRICA


Da Costa 8/25/2023 7:30:00 AM

question 423 eigrp uses metric
Anonymous


Bsmaind 8/20/2023 9:22:00 AM

hello nice dumps
Anonymous


beau 1/12/2024 4:53:00 PM

good resource for learning
UNITED STATES


Sandeep 12/29/2023 4:07:00 AM

very useful
Anonymous