Examine the figure given below:



If Activity B takes eight days to complete instead of five days as schedule, how long can you now delay Activity H?

  1. Three days
  2. One day
  3. Four days
  4. Zero days

Answer(s): B

Explanation:

Activity B is not on the critical path and it has a total of four days of float. If Activity B takes a total of eight days, it will consume three days of float. However, the total duration of the path ABEHJ may not exceed 26 days, as this is the total duration for the project. Although Activity H has a total of four days of float available, the consumption of three days of float on this path will reduce the total float for Activity H to just one day. If Activity H is delayed by more than one day, then the project will be late.
Answer option D is incorrect. There is one day of float still available for Activity H. Answer options A and C are incorrect. These are not the valid answers, as there is just one day of float available for Activity H.



You are the project manager of the GHT Project. Ben, one of your project team members, does not understand the idea of a milestone.
Which of the following best describes what a milestone is?

  1. A significant point in the project
  2. A goal of reaching a significant delivery of project benefits by an identified date
  3. An imposed date for the project to reach a given point
  4. The completion of a project activity that is crucial to project completion

Answer(s): A

Explanation:

A milestone is simply a significant point or event in the project. It does not have to be assigned to a specific date, but is usually assigned to the completion of project phases. A milestone is the end of a stage that marks the completion of a work package or phase, typically mark d by a high level event such as completion, endorsement or signing of a deliverable, document or a high level review meeting. In addition to signaling the completion of a key deliverable, a milestone may also signify an important decision or the derivation of a critical piece of information, which outlines or affects the future of a project. In this sense, a milestone not only signifies distance traveled (key stages in a project) but also indicates direction of travel since key decisions made at milestones may alter the route through the project plan. To create a milestone, enter 0 (zero) in the Duration field. The task will automatically be classified as a milestone.
Answer option C is incorrect. This is a project constraint.
Answer option B is incorrect. A project goal is an objective for time, cost, scope, and other metrics.
Answer option D is incorrect. All activities must be completed in order to complete the project work. Activities that are not completed are quality issues that prevent the project from completing the project scope.



You are the project manager of the GHY Project. Management wants you to create a process improvement plan for your project. Your project will be studied by management and will become a standard for all future organizational projects based on your project's performance, approach, and implementation of project processes.
All of the following should be included in your project's process improvement plan except for which one?

  1. Process boundaries
  2. Process configuration
  3. Targets for improved performance
  4. Identification of project risks

Answer(s): D

Explanation:

Identification of the project risks is not part of the process improvement plan. Identify risks is a risk management process, and risks are recorded in the risk register. Answer options A, B, and C are incorrect. Process boundaries, Process configuration and Targets for improved performance are parts of the process improvement plan.



George is the project manager of the NHQ Project and has a budget of $778,000. The project is scheduled to last for one year with an equal amount of work completed each quarter. The second quarter of the project has ended and George has spent $325,000 but has only finished forty percent of the project. Management needs a variance report for the project schedule.
What value should George report in this instance?

  1. .96
  2. -$77,800
  3. $-34,500
  4. -$13,800

Answer(s): B

Explanation:

Schedule variance (SV) is a measure of schedule performance on a project. The variance notifies that the schedule is ahead or behind what was planned for this period in time. The schedule variance is calculated based on the following formula: SV = Earned Value (EV) - Planned Value (PV) If the resulting schedule is negative, it indicates that the project is behind schedule. A value greater than 0 shows that the project is ahead of the planned schedule. A value of 0 indicates that the project is right on target. The earned value in this instance is forty percent of the project budget, $778,000, and the planned value is $398,000 because George is to be fifty percent done at the end of the second quarter, as the work is spread evenly across all quarters. The schedule variance is -$77,800 for the project.
Answer option A is incorrect. .96 represents the cost performance index.
Answer option C is incorrect. -$34,500 represents the project's variance at completion if the project continues as is.
Answer option D is incorrect. -$13,800 is the cost variance for the project.



You are the project manager of the NHQ Project. Management has set a conformance to the project schedule for your project at 0.95.
What does this term mean?

  1. It means the largest schedule variance you can have is five percent.
  2. It is the earned value divided by the planned value for your project.
  3. It is the expectation of management to be 95 on schedule at 95 percent of the project.
  4. It means you will need to earn at least 95 cents per dollar invested in the project.

Answer(s): A

Explanation:

Conformance to schedule is a required adherence for the project's schedule. In this instance, the project manager must not allow the schedule to slip more than five percent.
Answer option B is incorrect. This is the description of the schedule performance index.
Answer option D is incorrect. This is the description of the cost performance index.
Answer option C is incorrect. This is not a valid statement about the project performance.



Viewing Page 2 of 67



Share your comments for PMI PMI-SP exam with other users:

Biswa 11/20/2023 9:07:00 AM

understanding about joins
Anonymous


Jimmy Lopez 8/25/2023 10:19:00 AM

please upload oracle cloud infrastructure 2023 foundations associate exam braindumps. thank you.
Anonymous


Lily 4/24/2023 10:50:00 PM

questions made studying easy and enjoyable, passed on the first try!
UNITED STATES


John 8/7/2023 12:12:00 AM

has anyone recently attended safe 6.0 exam? did you see any questions from here?
Anonymous


Big Dog 6/24/2023 4:47:00 PM

question 13 should be dhcp option 43, right?
UNITED STATES


B.Khan 4/19/2022 9:43:00 PM

the buy 1 get 1 is a great deal. so far i have only gone over exam. it looks promissing. i report back once i write my exam.
INDIA


Ganesh 12/24/2023 11:56:00 PM

is this dump good
Anonymous


Albin 10/13/2023 12:37:00 AM

good ................
EUROPEAN UNION


Passed 1/16/2022 9:40:00 AM

passed
GERMANY


Harsh 6/12/2023 1:43:00 PM

yes going good
Anonymous


Salesforce consultant 1/2/2024 1:32:00 PM

good questions for practice
FRANCE


Ridima 9/12/2023 4:18:00 AM

need dump and sap notes for c_s4cpr_2308 - sap certified application associate - sap s/4hana cloud, public edition - sourcing and procurement
Anonymous


Tanvi Rajput 10/6/2023 6:50:00 AM

question 11: d i personally feel some answers are wrong.
UNITED KINGDOM


Anil 7/18/2023 9:38:00 AM

nice questions
Anonymous


Chris 8/26/2023 1:10:00 AM

looking for c1000-158: ibm cloud technical advocate v4 questions
Anonymous


sachin 6/27/2023 1:22:00 PM

can you share the pdf
Anonymous


Blessious Phiri 8/13/2023 10:26:00 AM

admin ii is real technical stuff
Anonymous


Luis Manuel 7/13/2023 9:30:00 PM

could you post the link
UNITED STATES


vijendra 8/18/2023 7:54:00 AM

hello send me dumps
Anonymous


Simeneh 7/9/2023 8:46:00 AM

it is very nice
Anonymous


john 11/16/2023 5:13:00 PM

i gave the amazon dva-c02 tests today and passed. very helpful.
Anonymous


Tao 11/20/2023 8:53:00 AM

there is an incorrect word in the problem statement. for example, in question 1, there is the word "speci c". this is "specific. in the other question, there is the word "noti cation". this is "notification. these mistakes make this site difficult for me to use.
Anonymous


patricks 10/24/2023 6:02:00 AM

passed my az-120 certification exam today with 90% marks. studied using the dumps highly recommended to all.
Anonymous


Ananya 9/14/2023 5:17:00 AM

i need it, plz make it available
UNITED STATES


JM 12/19/2023 2:41:00 PM

q47: intrusion prevention system is the correct answer, not patch management. by definition, there are no patches available for a zero-day vulnerability. the way to prevent an attacker from exploiting a zero-day vulnerability is to use an ips.
UNITED STATES


Ronke 8/18/2023 10:39:00 AM

this is simple but tiugh as well
Anonymous


CesarPA 7/12/2023 10:36:00 PM

questão 4, segundo meu compilador local e o site https://www.jdoodle.com/online-java-compiler/, a resposta correta é "c" !
UNITED STATES


Jeya 9/13/2023 7:50:00 AM

its very useful
INDIA


Tracy 10/24/2023 6:28:00 AM

i mastered my skills and aced the comptia 220-1102 exam with a score of 920/1000. i give the credit to for my success.
Anonymous


James 8/17/2023 4:33:00 PM

real questions
UNITED STATES


Aderonke 10/23/2023 1:07:00 PM

very helpful assessments
UNITED KINGDOM


Simmi 8/24/2023 7:25:00 AM

hi there, i would like to get dumps for this exam
AUSTRALIA


johnson 10/24/2023 5:47:00 AM

i studied for the microsoft azure az-204 exam through it has 100% real questions available for practice along with various mock tests. i scored 900/1000.
GERMANY


Manas 9/9/2023 1:48:00 AM

please upload 1z0-1072-23 exam dups
UNITED STATES