You are the project manager of the NHQ Project. You have created the project network diagram as shown in the figure:You are concerned about a risk on Activity G that if it happens will delay the project by four days. You would like to utilize float for Activity G . How much float is available for Activity G to help offset the risk event?
Answer(s): D
There is no float available for Activity G because it is on the critical path. Float or total float (TF) is the total amount of time that a schedule activity may be delayed from its early start date without delaying the project finish date, or violating a schedule constraint. It is calculated by using the critical path method technique and determining the difference between the early finish dates and late finish dates. Answer options B, A, and C are incorrect. There is no float available for Activity G because it is on the critical path.
Beth is the project manager for her organization. Her current project has many deliverables that have been defined at a high level, but the details of the deliverables are still unknown. In her project, Beth is planning in detail only the activities that are most imminent in the project work. This approach to project management planning is known as what?
Answer(s): B
Rolling wave planning is a technique to plan and do the most imminent project work before moving onto the details that are far off in the project schedule and project plan. Rolling wave planning is a technique for performing progressive elaboration planning where the work to be accomplished in the near future is planned in detail at a low level of the work breakdown structure. The work to be performed within another one or two reporting periods in the near future is planned in detail as work is being completed during the current period. Answer option D is incorrect. Decomposition is the process of breaking down work packages into the activity list. Answer options A and C are incorrect. These are not valid project management terms.
Gina is the project manager for her organization and she is working with her project team to define the project activities. In this project, the stakeholders are sensitive to the project completion date, so Gina is stressing to her project team members that while they need to provide and account for all of the project activities, they should focus on one work package in the WBS at a time. In order to start the decomposition of the project work packages into activities, Gina will need all of the following except for which one?
Answer(s): C
According to the PMBOK, Gina will not need the WBS directly, but will rely on the scope baseline.A Work Breakdown Structure (WBS) in project management is a tool that defines a project and groups the project's discrete work elements in a way that helps organize and define the total work scope of the project. A WBS element may be a product, data, a service, or any combination. WBS also provides the necessary framework for detailed cost estimating and control along with providing guidance for schedule development and control. Answer option A is incorrect. The scope baseline is an input to define the project activities. Answer option D is incorrect. Enterprise environmental factors are an input to define the project activities. Answer option B is incorrect. Organizational process assets are an input to define the project activities.
You have created the project network diagram for the ABC project. You are exploring total float and free float for that project. Martin, a project team member, wants to know the difference between total float and free float. What is the difference between total float and free float?
Total float is the time you can delay an activity without delaying the project end date, whereas free float is on each activity and does not affect the early start date of successor activities. Float, also called slack, is the amount of time an activity can be delayed without affecting any subsequent activities. There are two types of floats available: Free Float: It is the amount of time a schedule activity can be delayed without delaying the early start date of any immediately following schedule activities. Total Float: It is the total amount of time that a schedule activity may be delayedfrom its early start date without delaying the project finish date, or violating schedule constraint. Float is calculated by using the critical path method technique. Answer options C, A, and D are incorrect. These are not accurate definitions of free float and total float.
John works as a project manager of the NHQ Project. He has created the project network diagram as shown in the figure:Based on the project network diagram, how much float is available for Activity H if Activity B is delayed by four days and Activity E is delayed by two days?
Answer(s): A
The path of ABEHJ will take 22 days to complete and cannot exceed 28 days or else the project will be late. If Activity B takes four additional days and Activity E takes two additional days, this adds (4+2= 6) six days to the path, bringing the path's duration to exactly (22+6 = 28) days. There is no available float left for Activity D or H. Float or total float (TF) is the total amount of time that a schedule activity may be delayed from its early start date without delaying the project fish date, or violating a schedule constraint. It is calculated by using the critical path method technique and determining the difference between the early finish dates and late finish dates. Answer options B, C, and D are incorrect. There is no float available because the path's duration has increased to 28 days.
Share your comments for PMI PMI-SP exam with other users:
i took the aws saa-c03 test and scored 935/1000. it has all the exam dumps and important info.
good questions
well explained
i got the full version and it helped me pass the exam. pdf version is very good.
provide the download link, please
please upload thank.
please can you share 1z0-1055-22 dump pls
i will wait impatiently. thank youu
is it possible to clear the exam if we focus on only these 156 questions instead of 623 questions? kindly help!
really helped with preparation of my scrum exam
very informative and through explanations
prep for exam
thanks for helping us
i prepared for the eccouncil 350-401 exam. i scored 92% on the test.
aba questions to practice
great content
how do i get the remaining questions?
well formatted pdf and the test engine software is free. well worth the money i sept.
looking for 1z0-116
in question 22, shouldnt be in the data (option a) layer?
the questions are incredibly close to real exam. you people are amazing.
q15. answer is b. simple
great practice
thanks to this exam dumps, i felt confident and passed my exam with ease.
need 1z0-1105-22 exam
this is a beautiful tool. passed after a week of studying.
can you please upload the dumps for 1z0-1096-23 for oracle
its intresting, i would like to learn more abouth this
q252: dns poisoning is the correct answer, not locator redirection. beaconing is detected from a host. this indicates that the system has been infected with malware, which could be the source of local dns poisoning. location redirection works by either embedding the redirection in the original websites code or having a user click on a url that has an embedded redirect. since users at a different office are not getting redirected, it isnt an embedded redirection on the original website and since the user is manually typing in the url and not clicking a link, it isnt a modified link.
helpful dump questions
question 423 eigrp uses metric
hello nice dumps
good resource for learning
very useful