You are the project manager of the NHQ Project. You have created the project network diagram as shown in the figure:



You are concerned about a risk on Activity G that if it happens will delay the project by four days. You would like to utilize float for Activity G . How much float is available for Activity G to help offset the risk event?

  1. Five days
  2. Four days
  3. Eleven days
  4. Zero

Answer(s): D

Explanation:

There is no float available for Activity G because it is on the critical path. Float or total float (TF) is the total amount of time that a schedule activity may be delayed from its early start date without delaying the project finish date, or violating a schedule constraint. It is calculated by using the critical path method technique and determining the difference between the early finish dates and late finish dates. Answer options B, A, and C are incorrect. There is no float available for Activity G because it is on the critical path.



Beth is the project manager for her organization. Her current project has many deliverables that have been defined at a high level, but the details of the deliverables are still unknown. In her project, Beth is planning in detail only the activities that are most imminent in the project work. This approach to project management planning is known as what?

  1. Imminent activity management
  2. Rolling wave planning
  3. Predecessor-only diagramming
  4. Decomposition

Answer(s): B

Explanation:

Rolling wave planning is a technique to plan and do the most imminent project work before moving onto the details that are far off in the project schedule and project plan. Rolling wave planning is a technique for performing progressive elaboration planning where the work to be accomplished in the near future is planned in detail at a low level of the work breakdown structure. The work to be performed within another one or two reporting periods in the near future is planned in detail as work is being completed during the current period.
Answer option D is incorrect. Decomposition is the process of breaking down work packages into the activity list. Answer options A and C are incorrect. These are not valid project management terms.



Gina is the project manager for her organization and she is working with her project team to define the project activities. In this project, the stakeholders are sensitive to the project completion date, so Gina is stressing to her project team members that while they need to provide and account for all of the project activities, they should focus on one work package in the WBS at a time. In order to start the decomposition of the project work packages into activities, Gina will need all of the following except for which one?

  1. Scope baseline
  2. Organizational process assets
  3. WBS
  4. Enterprise environmental factors

Answer(s): C

Explanation:

According to the PMBOK, Gina will not need the WBS directly, but will rely on the scope baseline.A Work Breakdown Structure (WBS) in project management is a tool that defines a project and groups the project's discrete work elements in a way that helps organize and define the total work scope of the project. A WBS element may be a product, data, a service, or any combination. WBS also provides the necessary framework for detailed cost estimating and control along with providing guidance for schedule development and control.
Answer option A is incorrect. The scope baseline is an input to define the project activities.
Answer option D is incorrect. Enterprise environmental factors are an input to define the project activities.
Answer option B is incorrect. Organizational process assets are an input to define the project activities.



You have created the project network diagram for the ABC project. You are exploring total float and free float for that project. Martin, a project team member, wants to know the difference between total float and free float.
What is the difference between total float and free float?

  1. Total float is the amount of time an activity can be delayed without delaying any project successors, whereas free float is the amount of time an activity can be delayed without delaying the project completion date.
  2. Total float is the amount of time an activity can be delayed without delaying the project completion date, whereas free float is the amount of time an activity can be delayed without delaying any project successors.
  3. Total float is the amount of time an activity can be delayed without delaying the project completion date, whereas free float is the amount of time an activity can be delayed without delaying any project predecessors.
  4. Total float is the amount of time a non-critical activity can be delayed without delaying any project successors, whereas free float is the amount of time an activity can be delayed without delaying the project completion date.

Answer(s): B

Explanation:

Total float is the time you can delay an activity without delaying the project end date, whereas free float is on each activity and does not affect the early start date of successor activities. Float, also called slack, is the amount of time an activity can be delayed without affecting any subsequent activities. There are two types of floats available: Free Float: It is the amount of time a schedule activity can be delayed without delaying the early start date of any immediately following schedule activities. Total Float: It is the total amount of time that a schedule activity may be delayed

from its early start date without delaying the project finish date, or violating schedule constraint. Float is calculated by using the critical path method technique. Answer options C, A, and D are incorrect. These are not accurate definitions of free float and total float.



John works as a project manager of the NHQ Project. He has created the project network diagram as shown in the figure:



Based on the project network diagram, how much float is available for Activity H if Activity B is delayed by four days and Activity E is delayed by two days?

  1. Zero
  2. One
  3. Four
  4. Five

Answer(s): A

Explanation:

The path of ABEHJ will take 22 days to complete and cannot exceed 28 days or else the project will be late. If Activity B takes four additional days and Activity E takes two additional days, this adds (4+2= 6) six days to the path, bringing the path's duration to exactly (22+6 = 28) days. There is no available float left for Activity D or H. Float or total float (TF) is the total amount of time that a schedule activity may be delayed from its early start date without delaying the project fish date, or violating a schedule constraint. It is calculated by using the critical path method technique and determining the difference between the early finish dates and late finish dates. Answer options B, C, and D are incorrect. There is no float available because the path's duration has increased to 28 days.



Viewing Page 5 of 67



Share your comments for PMI PMI-SP exam with other users:

Massam 6/11/2022 5:55:00 PM

90% of questions was there but i failed the exam, i marked the answers as per the guide but looks like they are not accurate , if not i would have passed the exam given that i saw about 45 of 50 questions from dump
Anonymous


Anonymous 12/27/2023 12:47:00 AM

answer to this question "what administrative safeguards should be implemented to protect the collected data while in use by manasa and her product management team? " it should be (c) for the following reasons: this administrative safeguard involves controlling access to collected data by ensuring that only individuals who need the data for their job responsibilities have access to it. this helps minimize the risk of unauthorized access and potential misuse of sensitive information. while other options such as (a) documenting data flows and (b) conducting a privacy impact assessment (pia) are important steps in data protection, implementing a "need to know" access policy directly addresses the issue of protecting data while in use by limiting access to those who require it for legitimate purposes. (d) is not directly related to safeguarding data during use; it focuses on data transfers and location.
INDIA


Japles 5/23/2023 9:46:00 PM

password lockout being the correct answer for question 37 does not make sense. it should be geofencing.
Anonymous


Faritha 8/10/2023 6:00:00 PM

for question 4, the righr answer is :recover automatically from failures
UNITED STATES


Anonymous 9/14/2023 4:27:00 AM

question number 4s answer is 3, option c. i
UNITED STATES


p das 12/7/2023 11:41:00 PM

very good questions
UNITED STATES


Anna 1/5/2024 1:12:00 AM

i am confused about the answers to the questions. are the answers correct?
KOREA REPUBLIC OF


Bhavya 9/13/2023 10:15:00 AM

very usefull
Anonymous


Rahul Kumar 8/31/2023 12:30:00 PM

need certification.
CANADA


Diran Ole 9/17/2023 5:15:00 PM

great exam prep
CANADA


Venkata Subbarao Bandaru 6/24/2023 8:45:00 AM

i require dump
Anonymous


D 7/15/2023 1:38:00 AM

good morning, could you please upload this exam again,
Anonymous


Ann 9/15/2023 5:39:00 PM

hi can you please upload the dumps for sap contingent module. thanks
AUSTRALIA


Sridhar 1/16/2024 9:19:00 PM

good questions
Anonymous


Summer 10/4/2023 9:57:00 PM

looking forward to the real exam
Anonymous


vv 12/2/2023 2:45:00 PM

good ones for exam preparation
UNITED STATES


Danny Zas 9/15/2023 4:45:00 AM

this is a good experience
UNITED STATES


SM 1211 10/12/2023 10:06:00 PM

hi everyone
UNITED STATES


A 10/2/2023 6:08:00 PM

waiting for the dump. please upload.
UNITED STATES


Anonymous 7/16/2023 11:05:00 AM

upload cks exam questions
Anonymous


Johan 12/13/2023 8:16:00 AM

awesome training material
NETHERLANDS


PC 7/28/2023 3:49:00 PM

where is dump
Anonymous


YoloStar Yoloing 10/22/2023 9:58:00 PM

q. 289 - the correct answer should be b not d, since the question asks for the most secure way to provide access to a s3 bucket (a single one), and by principle of the least privilege you should not be giving access to all buckets.
Anonymous


Zelalem Nega 5/14/2023 12:45:00 PM

please i need if possible h12-831,
UNITED KINGDOM


unknown-R 11/23/2023 7:36:00 AM

good collection of questions and solution for pl500 certification
UNITED STATES


Swaminathan 5/11/2023 9:59:00 AM

i would like to appear the exam.
Anonymous


Veenu 10/24/2023 6:26:00 AM

i am very happy as i cleared my comptia a+ 220-1101 exam. i studied from as it has all exam dumps and mock tests available. i got 91% on the test.
Anonymous


Karan 5/17/2023 4:26:00 AM

need this dump
Anonymous


Ramesh Kutumbaka 12/30/2023 11:17:00 PM

its really good to eventuate knowledge before appearing for the actual exam.
Anonymous


anonymous 7/20/2023 10:31:00 PM

this is great
CANADA


Xenofon 6/26/2023 9:35:00 AM

please i want the questions to pass the exam
UNITED STATES


Diego 1/21/2024 8:21:00 PM

i need to pass exam
Anonymous


Vichhai 12/25/2023 3:25:00 AM

great, i appreciate it.
AUSTRALIA


P Simon 8/25/2023 2:39:00 AM

please could you upload (isc)2 certified in cybersecurity (cc) exam questions
SOUTH AFRICA