Which one of the following estimate types is a form of expert judgment?
Answer(s): B
An analogous estimate is a form of expert judgment because it relies on historical information. The historical information, assuming that it is accurate, serves as the conduit to the expert that created the historical information. Answer option C is incorrect. A bottom-up estimate creates an activity duration estimate for each work package in the WBS. Answer option A is incorrect. Parametric estimating uses a parameter, such as 10 hours per fixture installation, as a base to predict the duration of the project. Answer option D is incorrect. A definitive estimate, also known as a bottom- up estimate, accounts for the cost of each work package.
You are the project manager of the NHA Project. This project is expected to last one year with quarterly milestones throughout the year. Your project is supposed to be at the third milestone today but you're likely only 60 percent complete. Your project has a BAC of $745,000 and you've spent $440,000 of the budget-to-date. What is your schedule performance index for this project?
Answer(s): D
The schedule performance index can be found by dividing the earned value by the planned value. In this project, it's $447,000 divided by the $558,750 for a value of 0.80. Schedule performance index (SPI) is the measure of schedule efficiency on a project. It is used in trend analysis to predict future performance. SPI is the ratio of earned value to planned value. The SPI is calculated based on the following formula:SPI = Earned Value (EV) / Planned Value (PV)If the SPI value is greater than 1, it indicates better than expected performance, whereas if the value is less than 1, it shows poor performance. The SPI value of 1 indicates that the project is right on target.Answer option A is incorrect. "80" is not the same value as ".80". Answer option B is incorrect. 1.02 is the cost performance index. Answer option C is incorrect. 102 is not a valid calculation for this question.
Fill in the blank with an appropriate phrase.The __________ includes a description of any collateral services required, such as performance reporting or post-project operational support for the procured item.
Answer(s): A
The procurement SOW consists of a description of som collateral services required, such as performance reporting or post- project operational support for the procured item. The procurement SOW is revised and refined as required when it moves through the procurement process until incorporated into a signed contract award.
Mark is the project manager of the GHQ Project. He is happily reporting that his project has a schedule performance index of 2.12. Management, however, does not think this is good news. What is the most likely reason why management does not like an SPI of 2.12?
Cost and schedule performance indexes should be as close to 1 as possible. A larger value, such as 2.12, means that the schedule duration estimates were likely bloated or incorrect to begin with. Answer option B is incorrect. This is not the best choice for this question. Answer option C is incorrect. The number should not be close to 100; it should be close to 1. Answer option D is incorrect. While Mark may have crashed the schedule and driven up costs to achieve the SPI value, a more likely reason is that the time estimates were bloated.
You are the project manager of the BHG Project. You are creating a network diagram as shown in the figure:Mary, a project team member, reports that an identified risk is likely to happen in the project that will affect the completion date of Activity D . She reports that the risk event will likely cause the duration of the activity to increase by six days. If this happens what is the earliest the project can complete?
If Activity D increases by six days, the duration of the project will not change. There is 11 days of float available for Activity D so it may delay by six days without affecting the project end date. What is float? Float or total float (TF) is the total amount of time that a schedule activity may be delayed from its early start date without delaying the project finish date, or violating a schedule constraint. It is calculated by using the critical path method technique and determining the difference between the early finish dates and late finish dates. Answer options A, B, and C are incorrect. These are not valid answers for the question.
Share your comments for PMI PMI-SP exam with other users:
could you post the link
hello send me dumps
it is very nice
i gave the amazon dva-c02 tests today and passed. very helpful.
there is an incorrect word in the problem statement. for example, in question 1, there is the word "speci c". this is "specific. in the other question, there is the word "noti cation". this is "notification. these mistakes make this site difficult for me to use.
passed my az-120 certification exam today with 90% marks. studied using the dumps highly recommended to all.
i need it, plz make it available
q47: intrusion prevention system is the correct answer, not patch management. by definition, there are no patches available for a zero-day vulnerability. the way to prevent an attacker from exploiting a zero-day vulnerability is to use an ips.
this is simple but tiugh as well
questão 4, segundo meu compilador local e o site https://www.jdoodle.com/online-java-compiler/, a resposta correta é "c" !
its very useful
i mastered my skills and aced the comptia 220-1102 exam with a score of 920/1000. i give the credit to for my success.
real questions
very helpful assessments
hi there, i would like to get dumps for this exam
i studied for the microsoft azure az-204 exam through it has 100% real questions available for practice along with various mock tests. i scored 900/1000.
please upload 1z0-1072-23 exam dups
i was hoping if you could please share the pdf as i’m currently preparing to give the exam.
i am looking for oracle 1z0-116 exam
where we can get the answer to the questions
nice questions
question 129 is completely wrong.
i need dump
love the site.
can you please upload it back?
could you please re-upload this exam? thanks a lot!
great about shared quiz
goood helping
pay attention to questions. they are very tricky. i waould say about 80 to 85% of the questions are in this exam dump.
wish you would allow more free questions
great simulation
very g inood
q35 should be a
sap c_ts450_2021