PMI PMI-SP Exam (page: 3)
PMI -SP Scheduling Professional
Updated on: 28-Jul-2025

Viewing Page 3 of 67

Which one of the following estimate types is a form of expert judgment?

  1. Parametric estimate
  2. Analogous estimate
  3. Bottom-up estimate
  4. Definitive estimate

Answer(s): B

Explanation:

An analogous estimate is a form of expert judgment because it relies on historical information. The historical information, assuming that it is accurate, serves as the conduit to the expert that created the historical information.
Answer option C is incorrect. A bottom-up estimate creates an activity duration estimate for each work package in the WBS.
Answer option A is incorrect. Parametric estimating uses a parameter, such as 10 hours per fixture installation, as a base to predict the duration of the project.
Answer option D is incorrect. A definitive estimate, also known as a bottom- up estimate, accounts for the cost of each work package.



You are the project manager of the NHA Project. This project is expected to last one year with quarterly milestones throughout the year. Your project is supposed to be at the third milestone today but you're likely only 60 percent complete. Your project has a BAC of $745,000 and you've spent $440,000 of the budget-to-date.
What is your schedule performance index for this project?

  1. 80
  2. 1.02
  3. 102
  4. 0.80

Answer(s): D

Explanation:

The schedule performance index can be found by dividing the earned value by the planned value. In this project, it's $447,000 divided by the $558,750 for a value of 0.80. Schedule performance index (SPI) is the measure of schedule efficiency on a project. It is used in trend analysis to predict future performance. SPI is the ratio of earned value to planned value. The SPI is calculated based on the following formula:

SPI = Earned Value (EV) / Planned Value (PV)
If the SPI value is greater than 1, it indicates better than expected performance, whereas if the value is less than 1, it shows poor performance. The SPI value of 1 indicates that the project is right on target.

Answer option A is incorrect. "80" is not the same value as ".80".
Answer option B is incorrect. 1.02 is the cost performance index.
Answer option C is incorrect. 102 is not a valid calculation for this question.



Fill in the blank with an appropriate phrase.
The __________ includes a description of any collateral services required, such as performance reporting or post-project operational support for the procured item.

  1. procurement SOW

Answer(s): A

Explanation:

The procurement SOW consists of a description of som collateral services required, such as performance reporting or post- project operational support for the procured item. The procurement SOW is revised and refined as required when it moves through the procurement process until incorporated into a signed contract award.



Mark is the project manager of the GHQ Project. He is happily reporting that his project has a schedule performance index of 2.12. Management, however, does not think this is good news.
What is the most likely reason why management does not like an SPI of 2.12?

  1. It is not good news because a larger number means the schedule duration estimates were likely to be wrong to begin with.
  2. They likely do not understand the SPI formula.
  3. It is not good news, as the number should be closer to 100 than 0.
  4. It is good news, but Mark may have large cost variances to achieve this value.

Answer(s): A

Explanation:

Cost and schedule performance indexes should be as close to 1 as possible. A larger value, such as 2.12, means that the schedule duration estimates were likely bloated or incorrect to begin with.
Answer option B is incorrect. This is not the best choice for this question.
Answer option C is incorrect. The number should not be close to 100; it should be close to 1.
Answer option D is incorrect. While Mark may have crashed the schedule and driven up costs to achieve the SPI value, a more likely reason is that the time estimates were bloated.



You are the project manager of the BHG Project. You are creating a network diagram as shown in the figure:



Mary, a project team member, reports that an identified risk is likely to happen in the project that will affect the completion date of Activity D . She reports that the risk event will likely cause the duration of the activity to increase by six days. If this happens what is the earliest the project can complete?

  1. 32 days
  2. 29 days
  3. 27 days
  4. 26 days

Answer(s): D

Explanation:

If Activity D increases by six days, the duration of the project will not change. There is 11 days of float available for Activity D so it may delay by six days without affecting the project end date.
What is float? Float or total float (TF) is the total amount of time that a schedule activity may be delayed from its early start date without delaying the project finish date, or violating a schedule constraint. It is calculated by using the critical path method technique and determining the difference between the early finish dates and late finish dates. Answer options A, B, and C are incorrect. These are not valid answers for the question.



Viewing Page 3 of 67



Share your comments for PMI PMI-SP exam with other users:

Philippe 1/22/2023 10:24:00 AM

iam impressed with the quality of these dumps. they questions and answers were easy to understand and the xengine app was very helpful to use.
CANADA


Sam 8/31/2023 10:32:00 AM

not bad but you question database from isaca
MALAYSIA


Brijesh kr 6/29/2023 4:07:00 AM

awesome contents
INDIA


JM 12/19/2023 1:22:00 PM

answer to 134 is casb. while data loss prevention is the goal, in order to implement dlp in cloud applications you need to deploy a casb.
UNITED STATES


Neo 7/26/2023 9:36:00 AM

are these brain dumps sufficient enough to go write exam after practicing them? or does one need more material this wont be enough?
SOUTH AFRICA


Bilal 8/22/2023 6:33:00 AM

i did attend the required cources and i need to be sure that i am ready to take the exam, i would ask you please to share the questions, to be sure that i am fit to proceed with taking the exam.
Anonymous


John 11/12/2023 8:48:00 PM

why only give explanations on some, and not all questions and their respective answers?
UNITED STATES


Biswa 11/20/2023 8:50:00 AM

refresh db knowledge
Anonymous


Shalini Sharma 10/17/2023 8:29:00 AM

interested for sap certification
JAPAN


ethan 9/24/2023 12:38:00 PM

could you please upload practice questions for scr exam ?
HONG KONG


vijay joshi 8/19/2023 3:15:00 AM

please upload free oracle cloud infrastructure 2023 foundations associate exam braindumps
Anonymous


Ayodele Talabi 8/25/2023 9:25:00 PM

sweating! they are tricky
CANADA


Romero 3/23/2022 4:20:00 PM

i never use these dumps sites but i had to do it for this exam as it is impossible to pass without using these question dumps.
UNITED STATES


John Kennedy 9/20/2023 3:33:00 AM

good practice and well sites.
Anonymous


Nenad 7/12/2022 11:05:00 PM

passed my first exam last week and pass the second exam this morning. thank you sir for all the help and these brian dumps.
INDIA


Lucky 10/31/2023 2:01:00 PM

does anyone who attended exam csa 8.8, can confirm these questions are really coming ? or these are just for practicing?
HONG KONG


Prateek 9/18/2023 11:13:00 AM

kindly share the dumps
UNITED STATES


Irfan 11/25/2023 1:26:00 AM

very nice content
Anonymous


php 6/16/2023 12:49:00 AM

passed today
Anonymous


Durga 6/23/2023 1:22:00 AM

hi can you please upload questions
Anonymous


JJ 5/28/2023 4:32:00 AM

please upload quetions
THAILAND


Norris 1/3/2023 8:06:00 PM

i passed my exam thanks to this braindumps questions. these questions are valid in us and i highly recommend it!
UNITED STATES


abuti 7/21/2023 6:10:00 PM

are they truely latest
Anonymous


Curtis Nakawaki 7/5/2023 8:46:00 PM

questions appear contemporary.
UNITED STATES


Vv 12/2/2023 6:31:00 AM

good to prepare in this site
UNITED STATES


praveenkumar 11/20/2023 11:57:00 AM

very helpful to crack first attempt
Anonymous


asad Raza 5/15/2023 5:38:00 AM

please upload this exam
CHINA


Reeta 7/17/2023 5:22:00 PM

please upload the c_activate22 dump questions with answer
SWEDEN


Wong 12/20/2023 11:34:00 AM

q10 - the answer should be a. if its c, the criteria will meet if either the prospect is not part of the suppression lists or if the job title contains vice president
MALAYSIA


david 12/12/2023 12:38:00 PM

this was on the exam as of 1211/2023
Anonymous


Tink 7/24/2023 9:23:00 AM

great for prep
GERMANY


Jaro 12/18/2023 3:12:00 PM

i think in question 7 the first answer should be power bi portal (not power bi)
Anonymous


9eagles 4/7/2023 10:04:00 AM

on question 10 and so far 2 wrong answers as evident in the included reference link.
Anonymous


Tai 8/28/2023 5:28:00 AM

wonderful material
SOUTH AFRICA