PMI PMI-SP Exam (page: 3)
PMI -SP Scheduling Professional
Updated on: 12-Jan-2026

Viewing Page 3 of 67

Which one of the following estimate types is a form of expert judgment?

  1. Parametric estimate
  2. Analogous estimate
  3. Bottom-up estimate
  4. Definitive estimate

Answer(s): B

Explanation:

An analogous estimate is a form of expert judgment because it relies on historical information. The historical information, assuming that it is accurate, serves as the conduit to the expert that created the historical information.
Answer option C is incorrect. A bottom-up estimate creates an activity duration estimate for each work package in the WBS.
Answer option A is incorrect. Parametric estimating uses a parameter, such as 10 hours per fixture installation, as a base to predict the duration of the project.
Answer option D is incorrect. A definitive estimate, also known as a bottom- up estimate, accounts for the cost of each work package.



You are the project manager of the NHA Project. This project is expected to last one year with quarterly milestones throughout the year. Your project is supposed to be at the third milestone today but you're likely only 60 percent complete. Your project has a BAC of $745,000 and you've spent $440,000 of the budget-to-date.
What is your schedule performance index for this project?

  1. 80
  2. 1.02
  3. 102
  4. 0.80

Answer(s): D

Explanation:

The schedule performance index can be found by dividing the earned value by the planned value. In this project, it's $447,000 divided by the $558,750 for a value of 0.80. Schedule performance index (SPI) is the measure of schedule efficiency on a project. It is used in trend analysis to predict future performance. SPI is the ratio of earned value to planned value. The SPI is calculated based on the following formula:

SPI = Earned Value (EV) / Planned Value (PV)
If the SPI value is greater than 1, it indicates better than expected performance, whereas if the value is less than 1, it shows poor performance. The SPI value of 1 indicates that the project is right on target.

Answer option A is incorrect. "80" is not the same value as ".80".
Answer option B is incorrect. 1.02 is the cost performance index.
Answer option C is incorrect. 102 is not a valid calculation for this question.



Fill in the blank with an appropriate phrase.
The __________ includes a description of any collateral services required, such as performance reporting or post-project operational support for the procured item.

  1. procurement SOW

Answer(s): A

Explanation:

The procurement SOW consists of a description of som collateral services required, such as performance reporting or post- project operational support for the procured item. The procurement SOW is revised and refined as required when it moves through the procurement process until incorporated into a signed contract award.



Mark is the project manager of the GHQ Project. He is happily reporting that his project has a schedule performance index of 2.12. Management, however, does not think this is good news.
What is the most likely reason why management does not like an SPI of 2.12?

  1. It is not good news because a larger number means the schedule duration estimates were likely to be wrong to begin with.
  2. They likely do not understand the SPI formula.
  3. It is not good news, as the number should be closer to 100 than 0.
  4. It is good news, but Mark may have large cost variances to achieve this value.

Answer(s): A

Explanation:

Cost and schedule performance indexes should be as close to 1 as possible. A larger value, such as 2.12, means that the schedule duration estimates were likely bloated or incorrect to begin with.
Answer option B is incorrect. This is not the best choice for this question.
Answer option C is incorrect. The number should not be close to 100; it should be close to 1.
Answer option D is incorrect. While Mark may have crashed the schedule and driven up costs to achieve the SPI value, a more likely reason is that the time estimates were bloated.



You are the project manager of the BHG Project. You are creating a network diagram as shown in the figure:



Mary, a project team member, reports that an identified risk is likely to happen in the project that will affect the completion date of Activity D . She reports that the risk event will likely cause the duration of the activity to increase by six days. If this happens what is the earliest the project can complete?

  1. 32 days
  2. 29 days
  3. 27 days
  4. 26 days

Answer(s): D

Explanation:

If Activity D increases by six days, the duration of the project will not change. There is 11 days of float available for Activity D so it may delay by six days without affecting the project end date.
What is float? Float or total float (TF) is the total amount of time that a schedule activity may be delayed from its early start date without delaying the project finish date, or violating a schedule constraint. It is calculated by using the critical path method technique and determining the difference between the early finish dates and late finish dates. Answer options A, B, and C are incorrect. These are not valid answers for the question.



Viewing Page 3 of 67



Share your comments for PMI PMI-SP exam with other users:

Paul K 11/27/2023 2:28:00 AM

i think it should be a,c. option d goes against the principle of building anything custom unless there are no work arounds available
INDIA


ph 6/16/2023 12:41:00 AM

very legible
Anonymous


sephs2001 7/31/2023 10:42:00 PM

is this exam accurate or helpful?
Anonymous


ash 7/11/2023 3:00:00 AM

please upload dump, i have exam in 2 days
INDIA


Sneha 8/17/2023 6:29:00 PM

this is useful
CANADA


sachin 12/27/2023 2:45:00 PM

question 232 answer should be perimeter not netowrk layer. wrong answer selected
Anonymous


tomAws 7/18/2023 5:05:00 AM

nice questions
BRAZIL


Rahul 6/11/2023 2:07:00 AM

hi team, could you please provide this dump ?
INDIA


TeamOraTech 12/5/2023 9:49:00 AM

very helpful to clear the exam and understand the concept.
Anonymous


Curtis 7/12/2023 8:20:00 PM

i think it is great that you are helping people when they need it. thanks.
UNITED STATES


sam 7/17/2023 6:22:00 PM

cannot evaluate yet
Anonymous


nutz 7/20/2023 1:54:00 AM

a laptops wireless antenna is most likely located in the bezel of the lid
UNITED STATES


rajesh soni 1/17/2024 6:53:00 AM

good examplae to learn basic
INDIA


Tanya 10/25/2023 7:07:00 AM

this is useful information
Anonymous


Nasir Mahmood 12/11/2023 7:32:00 AM

looks usefull
Anonymous


Jason 9/30/2023 1:07:00 PM

question 81 should be c.
CANADA


TestPD1 8/10/2023 12:22:00 PM

question 18 : response isnt a ?
EUROPEAN UNION


ally 8/19/2023 5:31:00 PM

plaese add questions
TURKEY


DIA 10/7/2023 5:59:00 AM

is dumps still valid ?
FRANCE


Annie 7/7/2023 8:33:00 AM

thanks for this
EUROPEAN UNION


arnie 9/17/2023 6:38:00 AM

please upload questions
Anonymous


Tanuj Rana 7/22/2023 2:33:00 AM

please upload the question dump for professional machinelearning
Anonymous


Future practitioner 8/10/2023 1:26:00 PM

question 4 answer is c. this site shows the correct answer as b. "adopt a consumption model" is clearly a cost optimization design principle. looks like im done using this site to study!!!
Anonymous


Ace 8/3/2023 10:37:00 AM

number 52 answer is d
UNITED STATES


Nathan 12/17/2023 12:04:00 PM

just started preparing for my exam , and this site is so much help
Anonymous


Corey 12/29/2023 5:06:00 PM

question 35 is incorrect, the correct answer is c, it even states so: explanation: when a vm is infected with ransomware, you should not restore the vm to the infected vm. this is because the ransomware will still be present on the vm, and it will encrypt the files again. you should also not restore the vm to any vm within the companys subscription. this is because the ransomware could spread to other vms in the subscription. the best way to restore a vm that is infected with ransomware is to restore it to a new azure vm. this will ensure that the ransomware is not present on the new vm.
Anonymous


Rajender 10/18/2023 3:54:00 AM

i would like to take psm1 exam.
Anonymous


Blessious Phiri 8/14/2023 9:53:00 AM

cbd and pdb are key to the database
SOUTH AFRICA


Alkaed 10/19/2022 10:41:00 AM

the purchase and download process is very much streamlined. the xengine application is very nice and user-friendly but there is always room for improvement.
NETHERLANDS


Dave Gregen 9/4/2023 3:17:00 PM

please upload p_sapea_2023
SWEDEN


Sarah 6/13/2023 1:42:00 PM

anyone use this? the question dont seem to follow other formats and terminology i have been studying im getting worried
CANADA


Shuv 10/3/2023 8:19:00 AM

good questions
UNITED STATES


Reb974 8/5/2023 1:44:00 AM

hello are these questions valid for ms-102
CANADA


Mchal 7/20/2023 3:38:00 AM

some questions are wrongly answered but its good nonetheless
POLAND