PMI PMI-SP Exam (page: 8)
PMI -SP Scheduling Professional
Updated on: 28-Jul-2025

Viewing Page 8 of 67

You work as a project manager for BlueWell Inc. There have been changes to the project scope in your project. These changes will cause the project schedule to change as well, so you will need to update the schedule and the schedule baseline. The schedule baseline is a component of what?

  1. Project calendar
  2. Project constraints
  3. Project objectives
  4. Project management plan

Answer(s): D

Explanation:

The schedule baseline is a required component of the project management plan. Project management plan is a formal, agreed document that defines how the project is executed, monitored and controlled. It may be summary or detailed and may be composed of one or more subsidiary management plans and other planning documents. The objective of a project management plan is to define the approach to be used by the project team to deliver the intended project management scope of the project. The project manager creates the project management plan with the inputs from the project team and key stakeholders. The plan should be agreed and approved by at least the project team and its key stakeholders.
Answer option C is incorrect. The schedule baseline is not a project objective.
Answer option A is incorrect. The project calendar defines when the project will take place.
Answer option B is incorrect. Project constraints are restrictions imposed on the project, such as time, cost, and scope.



Holly is the project manager of her project. She has chosen to crash the project due to time constraints that have been imposed on her project.
When Holly crashes the project what project document must be updated to reflect this change to the approach?

  1. Develop schedule process
  2. Risk register
  3. Project risk management plan
  4. Activity attributes

Answer(s): D

Explanation:

When Holly adds resources to the project, as in this instance, she will need to update the activity attributes to reflect the new labor. Activity attributes are an output of the Define Activity process. These attributes refer to the multiple components that frame up an activity. The components for each activity during the early stages of the project are the Activity ID, WBS ID, and Activity name. At the later stages, the activity attributes include Activity codes, Predecessor activity, activity description, logical relationship, successor activity, leads and lags, imposed dates, and constraints and assumptions. Activity attributes are used for schedule development and for ordering, selecting, and sorting the planned schedule activities in a number of ways within reports. In project document updates, activity attributes are updated to include any revised resource requirements and other revision generated by the develop schedule process.



Examine the figure given below: Which path is considered the critical path?

  1. ACDFJ
  2. ACGIJ
  3. ABEFJ
  4. ABDFJ

Answer(s): B

Explanation:

The critical path is the path in the project network diagram with the longest duration. In project management, a critical path is the sequence of project network activities which add up to the longest overall duration. This determines the shortest time possible to complete the project. Any delay of an activity on the critical path directly impacts the planned project completion date (i.e. there is no float on the critical path). In this instance path ACGIJ is the longest as it takes 23 days.

Answer options C and D are incorrect. These paths take 13 days.
Answer option A is incorrect. This path only takes 19 days.



Winnie is the project manager for her company. She has been recording the actual durations of the project work to determine the actual progress of her project. Winnie needs to generate an updated project schedule based on project performance. She is using the supporting schedule data, manual scheduling methods, and her project management software to perform schedule network analysis.
What other tool Winnie can use to help and generate an updated project schedule?

  1. Critical path method
  2. Schedule management plan
  3. Scheduling tool
  4. Critical chain method

Answer(s): C

Explanation:

The scheduling tool is the only other tool that can help Winnie to create an updated project schedule. The scheduling tool is used in combination with manual methods or further project management software to carry out the schedule network analysis to produce an updated project schedule.
Answer option A is incorrect. The critical path method can be analyzed, but it is a part of the project management information system. In addition, the critical path is not better or worse than the critical chain method so by having both answers among the choices both answers are cancelled.
Answer option D is incorrect. The critical chain method can be analyzed, but it is the part of the project management information system. In addition, the critical path is not better or worse than the critical path method so by having both answers among the choices both answers are cancelled.
Answer option B is incorrect. The schedule management plan may need to be referenced to create a new project schedule, but it is not a tool that Winnie can use.



You are the project manager of the NHQ project. Your project has a budget of $1,258,456 and is scheduled to last for three years. Your project is currently forty percent complete though it should be forty-five percent complete. In order to reach this point of the project, you have spent $525,000. Management needs a performance report regarding the NHQ project. Management is concerned that this project will be over budget upon completion.
What is the estimate at completion for this project that you will need to report to management?

  1. -$62,922.80
  2. $1,312,504
  3. $1,525,000
  4. $787,504

Answer(s): B

Explanation:

The estimate at completion can be calculated by dividing the budget at completion by the cost performance index. Here, CPI =EV/AC=(0.40*1,258,456)/525000 = 0.95882 EAC = BAC/CPI = 1,258456/0.95882 = 1,312,504 What is Estimate at Completion (EAC)? Estimate at Completion (EAC) is a field that displays the final cost of the project including the actual costs and the forecast of remaining costs based on the cost performance index (CPI) so far. The formula used to calculate this estimate is as follows: ACWP+(BAC-BCWP)/CPI
Answer option D is incorrect. $787,504 is the estimate to complete.
Answer option A is incorrect. -$62,922.80 is the schedule variance.
Answer option C is incorrect. This is not a valid calculation for this question.



Viewing Page 8 of 67



Share your comments for PMI PMI-SP exam with other users:

Jason 9/30/2023 1:07:00 PM

question 81 should be c.
CANADA


TestPD1 8/10/2023 12:22:00 PM

question 18 : response isnt a ?
EUROPEAN UNION


ally 8/19/2023 5:31:00 PM

plaese add questions
TURKEY


DIA 10/7/2023 5:59:00 AM

is dumps still valid ?
FRANCE


Annie 7/7/2023 8:33:00 AM

thanks for this
EUROPEAN UNION


arnie 9/17/2023 6:38:00 AM

please upload questions
Anonymous


Tanuj Rana 7/22/2023 2:33:00 AM

please upload the question dump for professional machinelearning
Anonymous


Future practitioner 8/10/2023 1:26:00 PM

question 4 answer is c. this site shows the correct answer as b. "adopt a consumption model" is clearly a cost optimization design principle. looks like im done using this site to study!!!
Anonymous


Ace 8/3/2023 10:37:00 AM

number 52 answer is d
UNITED STATES


Nathan 12/17/2023 12:04:00 PM

just started preparing for my exam , and this site is so much help
Anonymous


Corey 12/29/2023 5:06:00 PM

question 35 is incorrect, the correct answer is c, it even states so: explanation: when a vm is infected with ransomware, you should not restore the vm to the infected vm. this is because the ransomware will still be present on the vm, and it will encrypt the files again. you should also not restore the vm to any vm within the companys subscription. this is because the ransomware could spread to other vms in the subscription. the best way to restore a vm that is infected with ransomware is to restore it to a new azure vm. this will ensure that the ransomware is not present on the new vm.
Anonymous


Rajender 10/18/2023 3:54:00 AM

i would like to take psm1 exam.
Anonymous


Blessious Phiri 8/14/2023 9:53:00 AM

cbd and pdb are key to the database
SOUTH AFRICA


Alkaed 10/19/2022 10:41:00 AM

the purchase and download process is very much streamlined. the xengine application is very nice and user-friendly but there is always room for improvement.
NETHERLANDS


Dave Gregen 9/4/2023 3:17:00 PM

please upload p_sapea_2023
SWEDEN


Sarah 6/13/2023 1:42:00 PM

anyone use this? the question dont seem to follow other formats and terminology i have been studying im getting worried
CANADA


Shuv 10/3/2023 8:19:00 AM

good questions
UNITED STATES


Reb974 8/5/2023 1:44:00 AM

hello are these questions valid for ms-102
CANADA


Mchal 7/20/2023 3:38:00 AM

some questions are wrongly answered but its good nonetheless
POLAND


Sonbir 8/8/2023 1:04:00 PM

how to get system serial number using intune
Anonymous


Manju 10/19/2023 1:19:00 PM

is it really helpful to pass the exam
Anonymous


LeAnne Hair 8/24/2023 12:47:00 PM

#229 in incorrect - all the customers require an annual review
UNITED STATES


Abdul SK 9/28/2023 11:42:00 PM

kindy upload
Anonymous


Aderonke 10/23/2023 12:53:00 PM

fantastic assessment on psm 1
UNITED KINGDOM


SAJI 7/20/2023 2:51:00 AM

56 question correct answer a,b
Anonymous


Raj Kumar 10/23/2023 8:52:00 PM

thank you for providing the q bank
CANADA


piyush keshari 7/7/2023 9:46:00 PM

true quesstions
Anonymous


B.A.J 11/6/2023 7:01:00 AM

i can´t believe ms asks things like this, seems to be only marketing material.
Anonymous


Guss 5/23/2023 12:28:00 PM

hi, could you please add the last update of ns0-527
Anonymous


Rond65 8/22/2023 4:39:00 PM

question #3 refers to vnet4 and vnet5. however, there is no vnet5 listed in the case study (testlet 2).
UNITED STATES


Cheers 12/13/2023 9:55:00 AM

sometimes it may be good some times it may be
GERMANY


Sumita Bose 7/21/2023 1:01:00 AM

qs 4 answer seems wrong- please check
AUSTRALIA


Amit 9/7/2023 12:53:00 AM

very detailed explanation !
HONG KONG


FisherGirl 5/16/2022 10:36:00 PM

the interactive nature of the test engine application makes the preparation process less boring.
NETHERLANDS