PMI -SP Scheduling Professional PMI-SP Dumps in PDF

Free PMI PMI-SP Real Questions (page: 12)

Fred is the project manager of the NHA project. This project has a BAC of $2,456,900 and is sixty percent complete. Fred has crashed the project, which has driven the project costs to date to $1,525,140, but his project is five percent more complete than what was planned.
What is the cost variance for this project that Fred needs to report to management?

  1. $122,845
  2. -$51,000
  3. -$85,000
  4. Zero

Answer(s): B

Explanation:

The cost variance for the project is -$51,000. You can find the cost variance by using the formula earned value minus planned value. In this instance, it is: CV = EV - AC = (0.60* 2,456,900) - 1,525,140 = -51,000
Answer option C is incorrect. -$85,000 is the project's variance at completion.
Answer option A is incorrect. $122,845 is the project's schedule variance.
Answer option D is incorrect. There is a cost variance on this project of -$51,000.



You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be at your second milestone which accounts for half of the project completion. There have been some errors in the project which has caused you to spend $2,073,654.
What is this project's schedule performance index?

  1. 1.02
  2. 0.98
  3. 0.90
  4. -$108,120

Answer(s): C

Explanation:

The schedule performance index shows how well the project is performing on its schedule goals. The SPI can be found by dividing the earned value by the planned value. In this instance, it is $2,025,000 divided by $2,250,000 for .90. The closer to 1, the better the performance. Schedule performance index (SPI) is the measure of schedule efficiency on a project. It is used in trend analysis to predict future performance. SPI is the ratio of earned value to planned value. The SPI is calculated based on the following formula: SPI = Earned Value (EV) / Planned Value (PV) If the SPI value is greater than 1, it indicates better than expected performance, whereas if the value is less than 1, it shows poor performance. The SPI value of 1 indicates that the project is right on target.
Answer option B is incorrect. 0.98 is the cost performance index.
Answer option A is incorrect. 1.02 is the to-complete performance index.
Answer option D is incorrect. -$108,120 is the variance at completion based on current performance.



Holly is the project manager for her organization. She is creating the activity list and would like to tag those activities that are comprised of discrete effort.
What is discrete effort?

  1. It is a term used to describe activities whose effort cannot be directly measured to the project objectives.
  2. It is a term used to describe activities whose effort can be directly measured and linked to the project objectives.
  3. It is a term used to describe activities that are supportive of the project work, but not linked to the project deliverables.
  4. It is a term used to describe activities that are core project management processes, but not core project activities.

Answer(s): B

Explanation:

Discrete effort is a term used to describe the work that can be measured and traced to the components in the work packages. It is the actual work to create the project deliverables.

Discrete effort refers to the particular work effort that can be identified and traced as having a direct tie to the final completion of the project- related work breakdown structure components and the deliverables. It is necessary that all the efforts have a specific measurable end product or end result. Answer options A, D, and C are incorrect. These are not valid definitions of discrete effort.



Lily works as a project manager for Blue Well Inc. She has recorded the following duration estimates for an activity in her project: optimistic 35, most likely 50, and pessimistic 95.
What time will she record for this activity?

  1. 48
  2. 55
  3. 54
  4. 40

Answer(s): B

Explanation:

This is an example of three-point estimate. A three-point estimate records the optimistic, most likely, and the pessimistic duration and then records an average for the predicted duration Three-point estimate is a way to enhance the accuracy of activity duration estimates. This concept is originated with the Program Evaluation and Review Technique (PERT). PERT charts the following three estimates: Most likely (TM): The duration of activity based on realistic factors such as resources assigned, interruptions, etc. Optimistic (TO): The activity duration based on the best-case scenario Pessimistic (TP): The activity duration based on the worst-case scenario The expected (TE) activity duration is a weighted average of these three estimates: TE = (TO + 4TM + TP) / 6 Duration estimates based on the above equations (sometimes simple average of the three estimates is also used) provide more accuracy. Here, it is, TE = ( 35 + 50*4 + 95) / 6 = 330/6 = 55



Nancy is the project manager of the JJJ Project. This project has recently been approved by the project customer as complete so Nancy must now finalize the administrative closure. Nancy needs to create the final project report to report the successes and failures in the project. Who should Nancy deliver this final project report to if she is participating in a projectized structure?

  1. Functional Management
  2. Project sponsor
  3. Whomever the communications management plan directs her to
  4. Project customer

Answer(s): C

Explanation:

The communications management plan will define who will receive what information.
Answer option B is incorrect. The project sponsor may be a recipient but the project communications management plan is the best selection.
Answer option A is incorrect. Functional management is not the best choice in a projectile structure.
Answer option D is incorrect. The project customer may receive a copy of the report, but the project communications management plan should direct the communications.



Share your comments for PMI PMI-SP exam with other users:

R
Rizwan
1/6/2024 2:18:00 AM

very helpful

Y
Yady
5/24/2023 10:40:00 PM

these questions look good.

K
Kettie
10/12/2023 1:18:00 AM

this is very helpful content

S
SB
7/21/2023 3:18:00 AM

please provide the dumps

D
David
8/2/2023 8:20:00 AM

it is amazing

U
User
8/3/2023 3:32:00 AM

quesion 178 about "a banking system that predicts whether a loan will be repaid is an example of the" the answer is classification. not regresion, you should fix it.

Q
quen
7/26/2023 10:39:00 AM

please upload apache spark dumps

E
Erineo
11/2/2023 5:34:00 PM

q14 is b&c to reduce you will switch off mail for every single alert and you will switch on daily digest to get a mail once per day, you might even skip the empty digest mail but i see this as a part of the daily digest adjustment

P
Paul
10/21/2023 8:25:00 AM

i think it is good question

U
Unknown
8/15/2023 5:09:00 AM

good for students who wish to give certification.

C
Ch
11/20/2023 10:56:00 PM

is there a google drive link to the images? the links in questions are not working.

J
Joey
5/16/2023 5:25:00 AM

very promising, looks great, so much wow!

A
alaska
10/24/2023 5:48:00 AM

i scored 87% on the az-204 exam. thanks! i always trust

N
nnn
7/9/2023 11:09:00 PM

good need more

U
User-sfdc
12/29/2023 7:21:00 AM

sample questions seems good

T
Tamer dam
8/4/2023 10:21:00 AM

huawei is ok

Y
YK
12/11/2023 1:10:00 AM

good one nice

D
de
8/28/2023 2:38:00 AM

please continue

D
DMZ
6/25/2023 11:56:00 PM

this exam dumps just did the job. i donot want to ruffle your feathers but your exam dumps and mock test engine is amazing.

J
Jose
8/30/2023 6:14:00 AM

nice questions

T
Tar01
7/24/2023 7:07:00 PM

the explanation are really helpful

D
DaveG
12/15/2023 4:50:00 PM

just passed my exam yesterday on my first attempt. these dumps were extremely helpful in passing first time. the questions were very, very similar to these questions!

A
A.K.
6/30/2023 6:34:00 AM

cosmos db is paas not saas

S
S Roychowdhury
6/26/2023 5:27:00 PM

what is the percentage of common questions in gcp exam compared to 197 dump questions? are they 100% matching with real gcp exam?

B
Bella
7/22/2023 2:05:00 AM

not able to see questions

S
Scott
9/8/2023 7:19:00 AM

by far one of the best sites for free questions. i have pass 2 exams with the help of this website.

D
donald
8/19/2023 11:05:00 AM

excellent question bank.

A
Ashwini
8/22/2023 5:13:00 AM

it really helped

S
sk
5/13/2023 2:07:00 AM

excelent material

C
Christopher
9/5/2022 10:54:00 PM

the new versoin of this exam which i downloaded has all the latest questions from the exam. i only saw 3 new questions in the exam which was not in this dump.

S
Sam
9/7/2023 6:51:00 AM

question 8 - can cloudtrail be used for storing jobs? based on aws - aws cloudtrail is used for governance, compliance and investigating api usage across all of our aws accounts. every action that is taken by a user or script is an api call so this is logged to [aws] cloudtrail. something seems incorrect here.

T
Tanvi Rajput
8/14/2023 10:55:00 AM

question 13 tda - c01 answer : quick table calculation -> percentage of total , compute using table down

P
PMSAGAR
9/19/2023 2:48:00 AM

pls share teh dump

Z
zazza
6/16/2023 10:47:00 AM

question 44 answer is user risk

AI Tutor 👋 I’m here to help!