PMI PMI-SP Exam (page: 12)
PMI -SP Scheduling Professional
Updated on: 02-Mar-2026

Viewing Page 12 of 67

Fred is the project manager of the NHA project. This project has a BAC of $2,456,900 and is sixty percent complete. Fred has crashed the project, which has driven the project costs to date to $1,525,140, but his project is five percent more complete than what was planned.
What is the cost variance for this project that Fred needs to report to management?

  1. $122,845
  2. -$51,000
  3. -$85,000
  4. Zero

Answer(s): B

Explanation:

The cost variance for the project is -$51,000. You can find the cost variance by using the formula earned value minus planned value. In this instance, it is: CV = EV - AC = (0.60* 2,456,900) - 1,525,140 = -51,000
Answer option C is incorrect. -$85,000 is the project's variance at completion.
Answer option A is incorrect. $122,845 is the project's schedule variance.
Answer option D is incorrect. There is a cost variance on this project of -$51,000.



You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be at your second milestone which accounts for half of the project completion. There have been some errors in the project which has caused you to spend $2,073,654.
What is this project's schedule performance index?

  1. 1.02
  2. 0.98
  3. 0.90
  4. -$108,120

Answer(s): C

Explanation:

The schedule performance index shows how well the project is performing on its schedule goals. The SPI can be found by dividing the earned value by the planned value. In this instance, it is $2,025,000 divided by $2,250,000 for .90. The closer to 1, the better the performance. Schedule performance index (SPI) is the measure of schedule efficiency on a project. It is used in trend analysis to predict future performance. SPI is the ratio of earned value to planned value. The SPI is calculated based on the following formula: SPI = Earned Value (EV) / Planned Value (PV) If the SPI value is greater than 1, it indicates better than expected performance, whereas if the value is less than 1, it shows poor performance. The SPI value of 1 indicates that the project is right on target.
Answer option B is incorrect. 0.98 is the cost performance index.
Answer option A is incorrect. 1.02 is the to-complete performance index.
Answer option D is incorrect. -$108,120 is the variance at completion based on current performance.



Holly is the project manager for her organization. She is creating the activity list and would like to tag those activities that are comprised of discrete effort.
What is discrete effort?

  1. It is a term used to describe activities whose effort cannot be directly measured to the project objectives.
  2. It is a term used to describe activities whose effort can be directly measured and linked to the project objectives.
  3. It is a term used to describe activities that are supportive of the project work, but not linked to the project deliverables.
  4. It is a term used to describe activities that are core project management processes, but not core project activities.

Answer(s): B

Explanation:

Discrete effort is a term used to describe the work that can be measured and traced to the components in the work packages. It is the actual work to create the project deliverables.

Discrete effort refers to the particular work effort that can be identified and traced as having a direct tie to the final completion of the project- related work breakdown structure components and the deliverables. It is necessary that all the efforts have a specific measurable end product or end result. Answer options A, D, and C are incorrect. These are not valid definitions of discrete effort.



Lily works as a project manager for Blue Well Inc. She has recorded the following duration estimates for an activity in her project: optimistic 35, most likely 50, and pessimistic 95.
What time will she record for this activity?

  1. 48
  2. 55
  3. 54
  4. 40

Answer(s): B

Explanation:

This is an example of three-point estimate. A three-point estimate records the optimistic, most likely, and the pessimistic duration and then records an average for the predicted duration Three-point estimate is a way to enhance the accuracy of activity duration estimates. This concept is originated with the Program Evaluation and Review Technique (PERT). PERT charts the following three estimates: Most likely (TM): The duration of activity based on realistic factors such as resources assigned, interruptions, etc. Optimistic (TO): The activity duration based on the best-case scenario Pessimistic (TP): The activity duration based on the worst-case scenario The expected (TE) activity duration is a weighted average of these three estimates: TE = (TO + 4TM + TP) / 6 Duration estimates based on the above equations (sometimes simple average of the three estimates is also used) provide more accuracy. Here, it is, TE = ( 35 + 50*4 + 95) / 6 = 330/6 = 55



Nancy is the project manager of the JJJ Project. This project has recently been approved by the project customer as complete so Nancy must now finalize the administrative closure. Nancy needs to create the final project report to report the successes and failures in the project. Who should Nancy deliver this final project report to if she is participating in a projectized structure?

  1. Functional Management
  2. Project sponsor
  3. Whomever the communications management plan directs her to
  4. Project customer

Answer(s): C

Explanation:

The communications management plan will define who will receive what information.
Answer option B is incorrect. The project sponsor may be a recipient but the project communications management plan is the best selection.
Answer option A is incorrect. Functional management is not the best choice in a projectile structure.
Answer option D is incorrect. The project customer may receive a copy of the report, but the project communications management plan should direct the communications.



Viewing Page 12 of 67



Share your comments for PMI PMI-SP exam with other users:

abuti 7/21/2023 6:10:00 PM

are they truely latest
Anonymous


Curtis Nakawaki 7/5/2023 8:46:00 PM

questions appear contemporary.
UNITED STATES


Vv 12/2/2023 6:31:00 AM

good to prepare in this site
UNITED STATES


praveenkumar 11/20/2023 11:57:00 AM

very helpful to crack first attempt
Anonymous


asad Raza 5/15/2023 5:38:00 AM

please upload this exam
CHINA


Reeta 7/17/2023 5:22:00 PM

please upload the c_activate22 dump questions with answer
SWEDEN


Wong 12/20/2023 11:34:00 AM

q10 - the answer should be a. if its c, the criteria will meet if either the prospect is not part of the suppression lists or if the job title contains vice president
MALAYSIA


david 12/12/2023 12:38:00 PM

this was on the exam as of 1211/2023
Anonymous


Tink 7/24/2023 9:23:00 AM

great for prep
GERMANY


Jaro 12/18/2023 3:12:00 PM

i think in question 7 the first answer should be power bi portal (not power bi)
Anonymous


9eagles 4/7/2023 10:04:00 AM

on question 10 and so far 2 wrong answers as evident in the included reference link.
Anonymous


Tai 8/28/2023 5:28:00 AM

wonderful material
SOUTH AFRICA


VoiceofMidnight 12/29/2023 4:48:00 PM

i passed!! ...but barely! got 728, but needed 720 to pass. the exam hit me with labs right out of the gate! then it went to multiple choice. protip: study the labs!
UNITED STATES


A K 8/3/2023 11:56:00 AM

correct answer for question 92 is c -aws shield
Anonymous


Nitin Mindhe 11/27/2023 6:12:00 AM

great !! it is really good
IRELAND


BailleyOne 11/22/2023 1:45:00 AM

explanations for the answers are to the point.
Anonymous


patel 10/25/2023 8:17:00 AM

how can rea next
INDIA


MortonG 10/19/2023 6:32:00 PM

question: 128 d is the wrong answer...should be c
EUROPEAN UNION


Jayant 11/2/2023 3:15:00 AM

thanks for az 700 dumps
Anonymous


Bipul Mishra 12/14/2023 7:12:00 AM

thank you for this tableau dumps . it will helpfull for tableau certification
UNITED STATES


hello 10/31/2023 12:07:00 PM

good content
Anonymous


Matheus 9/3/2023 2:14:00 PM

just testing if the comments are real
UNITED STATES


yenvti2@gmail.com 8/12/2023 7:56:00 PM

very helpful for exam preparation
Anonymous


Miguel 10/5/2023 12:16:00 PM

question 11: https://help.salesforce.com/s/articleview?id=sf.admin_lead_to_patient_setup_overview.htm&type=5
SPAIN


Noushin 11/28/2023 4:52:00 PM

i think the answer to question 42 is b not c
CANADA


susan sandivore 8/28/2023 1:00:00 AM

thanks for the dump
Anonymous


Aderonke 10/31/2023 12:51:00 AM

fantastic assessments
Anonymous


Priscila 7/22/2022 9:59:00 AM

i find the xengine test engine simulator to be more fun than reading from pdf.
GERMANY


suresh 12/16/2023 10:54:00 PM

nice document
Anonymous


Wali 6/4/2023 10:07:00 PM

thank you for making the questions and answers intractive and selectable.
UNITED STATES


Nawaz 7/18/2023 1:10:00 AM

answers are correct?
UNITED STATES


das 6/23/2023 7:57:00 AM

can i belive this dump
INDIA


Sanjay 10/15/2023 1:34:00 PM

great site to practice for sitecore exam
INDIA


jaya 12/17/2023 8:36:00 AM

good for students
UNITED STATES