A project scope statement has been approved, and the project manager and core team have been assigned to the project. Suddenly, the project manager takes a temporary leave of absence due to a medical emergency.
While the project manager is on leave, the team develops the project schedule.
When the project manager returns, a detailed schedule is almost complete.
What should the project manager do?
- Ensure that the schedule is aligned with the vision and objectives.
- Escalate the compliance issue to the project management office (PMO).
- Congratulate the team and move on to the execution phase.
- Develop a new detailed schedule with the team and project sponsor.