During an agile project, a project manager lost one of the resources, and at the same time, uncovered new requirements, which were added to the backlog.
What should the project manager do next?
- Reevaluate the backlog priority with the product owner since the velocity has been impacted.
- Reevaluate the scope of the current iteration to keep the same velocity and timeline.
- Reevaluate the velocity as the iteration duration will be impacted by new requirements.
- Reevaluate the project schedule as the velocity will be impacted by the loss of resources.