An agile project is running its third iteration with a duration of 2 weeks. A new operations director, who only has a predictive background, started working at the company. In the first meeting with the project manager, the director demands a weekly project status report.
What should the project manager do?
- Invite the director to attend the daily standup meetings.
- Share this with the team and ask them to develop reports for the director.
- Introduce the agile aspect to the director and agree on a solution.
- Explain to the director that agile projects have live reports.