Which process involves monitoring the status of the project to update the project costs and managing changes to the cost baseline?

  1. Estimate Costs
  2. Control Costs
  3. Determine Budget
  4. Plan Cost Management

Answer(s): B

Explanation:

7.3.3.1 Cost Baseline
The cost baseline is the approved version of the time-phased project budget, excluding any management reserves, which can only be changed through formal change control procedures and is used as a basis for comparison to actual results. It is developed as a summation of the approved budgets for the different schedule activities.

7.4 Control Costs
Definition: The process of monitoring the status of the project to update the project costs and managing changes to the cost baseline.
Key Benefit: The key benefit of this process is that it determines the cost baseline against which project performance can be monitored and controlled.

Inputs
1. Project management plan
2. Project funding requirements
3. Work performance data
4. Organizational process assets

Tools & Techniques
1. Earned value management
2. Forecasting
3. To-complete performance index (TCPI)
4. Performance reviews
5. Project management software
6. Reserve analysis

Outputs
1. Work performance information
2. Cost forecasts
3. Change requests
4. Project management plan updates
5. Project documents updates
6. Organizational process assets updates



Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?

  1. Project team
  2. Focus group
  3. Change control board
  4. Project stakeholders

Answer(s): C

Explanation:

Change Control Board (CCB). A formally chartered group responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project, and for recording and communicating such decisions.



Plan Schedule Management is a process in which Knowledge Area?

  1. Project Scope Management
  2. Project Human Resource Management
  3. Project Integration Management
  4. Project Time Management

Answer(s): D

Explanation:

Schedule -> Time Management Easy question



An output of the Validate Scope process is:

  1. A requirements traceability matrix.
  2. The scope management plan.
  3. Work performance reports.
  4. Change requests.

Answer(s): D

Explanation:

Process: 5.5 Validate Scope
Definition: The process of formalizing acceptance of the completed project deliverables.
Key Benefit: The key benefit of this process is that it brings objectivity to the acceptance process and increases the chance of final product, service, or result acceptance by validating each deliverable.

Inputs
1. Project management plan
2. Requirements documentation
3. Requirements traceability matrix
4. Verified deliverables
5. Work performance data

Tools & Techniques
1. Inspection
2. Group decision-making techniques

Outputs
1. Accepted deliverables
2. Change requests
3. Work performance information
4. Project documents updates



The Perform Integrated Change Control process occurs in which Process Group?

  1. Initiating
  2. Executing
  3. Monitoring and Controlling
  4. Planning

Answer(s): C

Explanation:

Monitoring and Controlling Process Group
4.4 Monitor and Control Project Work
4.5 Perform Integrated Change Control
5.5 Validate Scope
5.6Control Scope
6.7 Control Schedule
7.4 Control Costs
8.3 Control Quality
10.3 Control Communications
11.6 Control Risks
12.3 Control Procurements
13.4 Control Stakeholder Engagement



Share your comments for PMI PMI-002 exam with other users:

N
Naveed
8/28/2023 2:48:00 AM

good questions with simple explanation

C
cert
9/24/2023 4:53:00 PM

admin guide (windows) respond to malicious causality chains. when the cortex xdr agent identifies a remote network connection that attempts to perform malicious activity—such as encrypting endpoint files—the agent can automatically block the ip address to close all existing communication and block new connections from this ip address to the endpoint. when cortex xdrblocks an ip address per endpoint, that address remains blocked throughout all agent profiles and policies, including any host-firewall policy rules. you can view the list of all blocked ip addresses per endpoint from the action center, as well as unblock them to re-enable communication as appropriate. this module is supported with cortex xdr agent 7.3.0 and later. select the action mode to take when the cortex xdr agent detects remote malicious causality chains: enabled (default)—terminate connection and block ip address of the remote connection. disabled—do not block remote ip addresses. to allow specific and known s

Y
Yves
8/29/2023 8:46:00 PM

very inciting

M
Miguel
10/16/2023 11:18:00 AM

question 5, it seems a instead of d, because: - care plan = case - patient = person account - product = product2;

B
Byset
9/25/2023 12:49:00 AM

it look like real one

D
Debabrata Das
8/28/2023 8:42:00 AM

i am taking oracle fcc certification test next two days, pls share question dumps

N
nITA KALE
8/22/2023 1:57:00 AM

i need dumps

C
CV
9/9/2023 1:54:00 PM

its time to comptia sec+

S
SkepticReader
8/1/2023 8:51:00 AM

question 35 has an answer for a different question. i believe the answer is "a" because it shut off the firewall. "0" in registry data means that its false (aka off).

N
Nabin
10/16/2023 4:58:00 AM

helpful content

B
Blessious Phiri
8/15/2023 3:19:00 PM

oracle 19c is complex db

S
Sreenivas
10/24/2023 12:59:00 AM

helpful for practice

L
Liz
9/11/2022 11:27:00 PM

support team is fast and deeply knowledgeable. i appreciate that a lot.

N
Namrata
7/15/2023 2:22:00 AM

helpful questions

L
lipsa
11/8/2023 12:54:00 PM

thanks for question

E
Eli
6/18/2023 11:27:00 PM

the software is provided for free so this is a big change. all other sites are charging for that. also that fucking examtopic site that says free is not free at all. you are hit with a pay-wall.

O
open2exam
10/29/2023 1:14:00 PM

i need exam questions nca 6.5 any help please ?

G
Gerald
9/11/2023 12:22:00 PM

just took the comptia cybersecurity analyst (cysa+) - wished id seeing this before my exam

R
ryo
9/10/2023 2:27:00 PM

very helpful

J
Jamshed
6/20/2023 4:32:00 AM

i need this exam

R
Roberto Capra
6/14/2023 12:04:00 PM

nice questions... are these questions the same of the exam?

S
Synt
5/23/2023 9:33:00 PM

need to view

V
Vey
5/27/2023 12:06:00 AM

highly appreciate for your sharing.

T
Tshepang
8/18/2023 4:41:00 AM

kindly share this dump. thank you

J
Jay
9/26/2023 8:00:00 AM

link plz for download

L
Leo
10/30/2023 1:11:00 PM

data quality oecd

B
Blessious Phiri
8/13/2023 9:35:00 AM

rman is one good recovery technology

D
DiligentSam
9/30/2023 10:26:00 AM

need it thx

V
Vani
8/10/2023 8:11:00 PM

good questions

F
Fares
9/11/2023 5:00:00 AM

good one nice revision

L
Lingaraj
10/26/2023 1:27:00 AM

i love this thank you i need

M
Muhammad Rawish Siddiqui
12/5/2023 12:38:00 PM

question # 142: data governance is not one of the deliverables in the document and content management context diagram.

A
al
6/7/2023 10:25:00 AM

most answers not correct here

B
Bano
1/19/2024 2:29:00 AM

what % of questions do we get in the real exam?

AI Tutor 👋 I’m here to help!