Which type of contract gives both the seller and the buyer flexibility to deviate from performance with financial incentives?
Answer(s): B
Fixed Price Incentive Fee Contracts (FPIF). This fixed-price arrangement gives the buyer and seller some flexibility in that it allows for deviation from performance, with financial incentives tied to achieving agreed upon metrics. Typically such financial incentives are related to cost, schedule, or technical performance of the seller. Performance targets are established at the outset, and the final contract price is determined after completion of all work based on the seller’s performance. Under FPIF contracts, a price ceiling is set, and all costs above the price ceiling are the responsibility of the seller, who is obligated to complete the work.
What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?
Answer(s): C
Estimate to completion calculates how much more of the budget is needed to complete the project if everything continues at the current level of performance.EAC ‘atypical’ = AC + BAC - EVEAC ‘typical’ = AC + ((BAC - EV) / CPI)
The business needs, assumptions, and constraints and the understanding of the customers’ needs and high- level requirements are documented in the:
Which Process Group and Knowledge Area include the Sequence Activities process?
Knowledge Areas1. 4. Project Integration Management2. 5. Project Scope Management3. 6. Project Time Management4. 7. Project Cost Management5. 8. Project Quality Management6. 9. Project Human Resource Management7. 10.Project Communications Management8. 11.Project Risk Management9. 12.Project Procurement Management10. 13.Project Stakeholder ManagementPlanning Process Group4.2 Develop Project Management Plan5.1 Plan Scope Management5.2 Collect Requirements5.3 Define Scope5.4 Create WBS6.1 Plan Schedule Management6.2 Define Activities6.3 Sequence Activities6.4 Estimate Activity Resources6.5 Estimate Activity Durations6.6 Develop Schedule7.1 Plan Cost Management7.2 Estimate Costs7.3 Determine Budget8.1 Plan Quality Management9.1 Plan Human Resource Management10.1 Plan Communications Management11.1 Plan Risk Management11.2 Identify Risks11.3 Perform Qualitative Risk Analysis11.4 Perform Quantitative Risk Analysis11.5 Plan Risk Responses12.1 Plan Procurement Management13.2 Plan Stakeholder Management
In the Plan Stakeholder Management process, expert judgment is used to:
Answer(s): D
4.1.2.1 Expert JudgmentExpert judgment is often used to assess the inputs used to develop the project charter. Expert judgment is applied to all technical and management details during this process. Such expertise is provided by any group or individual with specialized knowledge or training and is available from many sources, including:Other units within the organization, Consultants,Stakeholders, including customers or sponsors, Professional and technical associations, Industry groups,Subject matter experts (SME), and Project management office (PMO).Process: 13.2 Plan Stakeholder ManagementDefinition: Stakeholder Management is the process of developing appropriate management strategies to effectively engage stakeholders throughout the project life cycle, based on the analysis of their needs, interests, and potential impact on project success.Key Benefit: The key benefit of this process is that it provides a clear, actionable plan to interact with project stakeholders to support the project’s interests.Inputs1. Project management plan2. Stakeholder register3. Enterprise environmental factors4. Organizational process assetsTools & Techniques1. Expert judgment2. Meetings3. Analytical techniquesOutputsStakeholder management plan Project documents updates
Share your comments for PMI PMI-002 exam with other users:
good morning
please upload the ncp-mci 6.5 dumps, really need to practice this one. thanks guys
question 16: https://help.salesforce.com/s/articleview?id=sf.care_console_overview.htm&type=5
yes i m prepared exam
my experience was great with this site as i studied for the ms-900 from here and got 900/1000 on the test. my main focus was on the tutorials which were provided and practice questions. thanks!
great course
very good question
question: 93 which statement is true regarding the result? sales contain 6 columns and values contain 7 columns so c is not right answer.
highly recommend just passed my exam.
great practice! thanks
anyone who wrote this exam recently?
kindly share the dump
could you please upload cfe fraud prevention and deterrence questions? it will be very much helpful.
this is really very very helpful for mcd level 1
very helpful!
question #18s answer should be a, not d. this should be corrected. it should be minvalidityperiod
thanks for the exact solution
need to refer the questions and have to give the exam
i need it right now if it was possible please
i need it very much please share it in the fastest time.
correct answer is d for student.java program
q:37 c is correct
q6 exam topic: terramearth, c: correct answer: copy 1petabyte to encrypted usb device ???
explained answers
plan to take theaws certified developer - associate dva-c02 in the next few weeks
very helpfull
good questions
help to practice csa exam
nice tip and well documented
i need the exam
please upload
prepping for fsc exam
pd1 with great experience
@t it seems like azure service bus message quesues could be the best solution