PMI Certified Associate in Project Management (-100) PMI-002 Dumps in PDF

Free PMI PMI-002 Real Questions (page: 30)

Which type of contract gives both the seller and the buyer flexibility to deviate from performance with financial incentives?

  1. Cost Plus Incentive Fee (CPIF)
  2. Fixed Price Incentive Fee (FPIF)
  3. Cost Pius Award Fee (CPAF)
  4. Time and Material (T&M)

Answer(s): B

Explanation:

Fixed Price Incentive Fee Contracts (FPIF). This fixed-price arrangement gives the buyer and seller some flexibility in that it allows for deviation from performance, with financial incentives tied to achieving agreed upon metrics. Typically such financial incentives are related to cost, schedule, or technical performance of the seller. Performance targets are established at the outset, and the final contract price is determined after completion of all work based on the seller’s performance. Under FPIF contracts, a price ceiling is set, and all costs above the price ceiling are the responsibility of the seller, who is obligated to complete the work.



What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?

  1. $50
  2. $100
  3. $125
  4. $175

Answer(s): C

Explanation:

Estimate to completion calculates how much more of the budget is needed to complete the project if everything continues at the current level of performance.
EAC ‘atypical’ = AC + BAC - EV
EAC ‘typical’ = AC + ((BAC - EV) / CPI)



The business needs, assumptions, and constraints and the understanding of the customers’ needs and high- level requirements are documented in the:

  1. Project management plan.
  2. Project charter.
  3. Work breakdown structure.
  4. Stakeholder register.

Answer(s): B



Which Process Group and Knowledge Area include the Sequence Activities process?

  1. Executing Process Group and Project Time Management
  2. Executing Process Group and Project Cost Management
  3. Planning Process Group and Project Time Management
  4. Planning Process Group and Project Cost Management

Answer(s): C

Explanation:

Knowledge Areas

1. 4. Project Integration Management
2. 5. Project Scope Management
3. 6. Project Time Management
4. 7. Project Cost Management
5. 8. Project Quality Management
6. 9. Project Human Resource Management
7. 10.Project Communications Management
8. 11.Project Risk Management
9. 12.Project Procurement Management
10. 13.Project Stakeholder Management

Planning Process Group
4.2 Develop Project Management Plan
5.1 Plan Scope Management
5.2 Collect Requirements
5.3 Define Scope
5.4 Create WBS
6.1 Plan Schedule Management
6.2 Define Activities
6.3 Sequence Activities
6.4 Estimate Activity Resources
6.5 Estimate Activity Durations
6.6 Develop Schedule
7.1 Plan Cost Management
7.2 Estimate Costs
7.3 Determine Budget
8.1 Plan Quality Management
9.1 Plan Human Resource Management
10.1 Plan Communications Management
11.1 Plan Risk Management
11.2 Identify Risks
11.3 Perform Qualitative Risk Analysis
11.4 Perform Quantitative Risk Analysis
11.5 Plan Risk Responses
12.1 Plan Procurement Management
13.2 Plan Stakeholder Management



In the Plan Stakeholder Management process, expert judgment is used to:

  1. Provide information needed to plan appropriate ways to engage project stakeholders.
  2. Ensure comprehensive identification and listing of new stakeholders.
  3. Analyze the information needed to develop the project scope statement.
  4. Decide the level of engagement of the stakeholders at each required stage.

Answer(s): D

Explanation:

4.1.2.1 Expert Judgment
Expert judgment is often used to assess the inputs used to develop the project charter. Expert judgment is applied to all technical and management details during this process. Such expertise is provided by any group or individual with specialized knowledge or training and is available from many sources, including:
Other units within the organization, Consultants,
Stakeholders, including customers or sponsors, Professional and technical associations, Industry groups,
Subject matter experts (SME), and Project management office (PMO).

Process: 13.2 Plan Stakeholder Management
Definition: Stakeholder Management is the process of developing appropriate management strategies to effectively engage stakeholders throughout the project life cycle, based on the analysis of their needs, interests, and potential impact on project success.
Key Benefit: The key benefit of this process is that it provides a clear, actionable plan to interact with project stakeholders to support the project’s interests.

Inputs
1. Project management plan
2. Stakeholder register
3. Enterprise environmental factors
4. Organizational process assets
Tools & Techniques
1. Expert judgment
2. Meetings
3. Analytical techniques

Outputs
Stakeholder management plan Project documents updates



Share your comments for PMI PMI-002 exam with other users:

V
Vinit N.
8/28/2023 2:33:00 AM

hi, please make the dumps available for my upcoming examination.

S
Sanyog Deshpande
9/14/2023 7:05:00 AM

good practice

T
Tyron
9/8/2023 12:12:00 AM

so far it is really informative

B
beast
7/30/2023 2:22:00 PM

hi i want it please please upload it

M
Mirex
5/26/2023 3:45:00 AM

am preparing for exam ,just nice questions

E
exampei
8/7/2023 8:05:00 AM

please upload c_tadm_23 exam

A
Anonymous
9/12/2023 12:50:00 PM

can we get tdvan4 vantage data engineering pdf?

A
Aish
10/11/2023 5:51:00 AM

want to clear the exam.

S
Smaranika
6/22/2023 8:42:00 AM

could you please upload the dumps of sap c_sac_2302

B
Blessious Phiri
8/15/2023 1:56:00 PM

asm management configuration is about storage

L
Lewis
7/6/2023 8:49:00 PM

kool thumb up

M
Moreece
5/15/2023 8:44:00 AM

just passed the az-500 exam this last friday. most of the questions in this exam dumps are in the exam. i bought the full version and noticed some of the questions which were answered wrong in the free version are all corrected in the full version. this site is good but i wish the had it in an interactive version like a test engine simulator.

T
Terry
5/24/2023 4:41:00 PM

i can practice for exam

E
Emerys
7/29/2023 6:55:00 AM

please i need this exam.

G
Goni Mala
9/2/2023 12:27:00 PM

i need the dump

L
Lenny
9/29/2023 11:30:00 AM

i want it bad, even if cs6 maybe retired, i want to learn cs6

M
MilfSlayer
12/28/2023 8:32:00 PM

i hate comptia with all my heart with their "choose the best" answer format as an argument could be made on every question. they say "the "comptia way", lmao no this right here boys is the comptia way 100%. take it from someone whos failed this exam twice but can configure an entire complex network that these are the questions that are on the test 100% no questions asked. the pbqs are dead on! nice work

S
Swati Raj
11/14/2023 6:28:00 AM

very good materials

K
Ko Htet
10/17/2023 1:28:00 AM

thanks for your support.

P
Philippe
1/22/2023 10:24:00 AM

iam impressed with the quality of these dumps. they questions and answers were easy to understand and the xengine app was very helpful to use.

S
Sam
8/31/2023 10:32:00 AM

not bad but you question database from isaca

B
Brijesh kr
6/29/2023 4:07:00 AM

awesome contents

J
JM
12/19/2023 1:22:00 PM

answer to 134 is casb. while data loss prevention is the goal, in order to implement dlp in cloud applications you need to deploy a casb.

N
Neo
7/26/2023 9:36:00 AM

are these brain dumps sufficient enough to go write exam after practicing them? or does one need more material this wont be enough?

B
Bilal
8/22/2023 6:33:00 AM

i did attend the required cources and i need to be sure that i am ready to take the exam, i would ask you please to share the questions, to be sure that i am fit to proceed with taking the exam.

J
John
11/12/2023 8:48:00 PM

why only give explanations on some, and not all questions and their respective answers?

B
Biswa
11/20/2023 8:50:00 AM

refresh db knowledge

S
Shalini Sharma
10/17/2023 8:29:00 AM

interested for sap certification

E
ethan
9/24/2023 12:38:00 PM

could you please upload practice questions for scr exam ?

V
vijay joshi
8/19/2023 3:15:00 AM

please upload free oracle cloud infrastructure 2023 foundations associate exam braindumps

A
Ayodele Talabi
8/25/2023 9:25:00 PM

sweating! they are tricky

R
Romero
3/23/2022 4:20:00 PM

i never use these dumps sites but i had to do it for this exam as it is impossible to pass without using these question dumps.

J
John Kennedy
9/20/2023 3:33:00 AM

good practice and well sites.

N
Nenad
7/12/2022 11:05:00 PM

passed my first exam last week and pass the second exam this morning. thank you sir for all the help and these brian dumps.

AI Tutor 👋 I’m here to help!