The degree, amount, or volume of risk that an organization or individual will withstand is known as its risk:
Answer(s): C
11 PROJECT RISK MANAGEMENT[..]Organizations perceive risk as the effect of uncertainty on projects and organizational objectives. Organizations and stakeholders are willing to accept varying degrees of risk depending on their risk attitude. The risk attitudes of both the organization and the stakeholders may be influenced by a number of factors, which are broadly classified into three themes:Risk appetite, which is the degree of uncertainty an entity is willing to take on in anticipation of a reward.Risk tolerance, which is the degree, amount, or volume of risk that an organization or individual will withstand.Risk threshold, which refers to measures along the level of uncertainty or the level of impact at which a stakeholder may have a specific interest. Below that risk threshold, the organization will accept the risk. Above that risk threshold, the organization will not tolerate the risk.For example, an organization’s risk attitude may include its appetite for uncertainty, its threshold for risk levels that are unacceptable, or its risk tolerance at which point the organization may select a different risk response. Positive and negative risks are commonly referred to as opportunities and threats. The project may be accepted if the risks are within tolerances and are in balance with the rewards that may be gained by taking the risks. Positive risks that offer opportunities within the limits of risk tolerances may be pursued in order to generate enhanced value. For example, adopting an aggressive resource optimization technique is a risk taken in anticipation of a reward for using fewer resources.
Project deliverables that have been completed and checked for correctness through the Control Quality process are known as:
Answer(s): A
Process: 8.3 Control QualityDefinition: The process of monitoring and recording results of executing the quality activities to assess performance and recommend necessary changes.Key Benefit: The key benefits of this process include: (1) identifying the causes of poor process or product quality and recommending and/or taking action to eliminate them; and (2) validating that project deliverables and work meet the requirements specified by key stakeholders necessary for final acceptance.Inputs1. Project management plan2. Quality metrics3. Quality checklists4. Work performance data5. Approved change requests6. Deliverables7. Project documents8. Organizational process assets Tools & Techniques1. Seven basic quality tools2. Statistical sampling3. Inspection4. Approved change requests reviewOutputs1. Quality control measurements2. Validated changes3. Verified deliverables4. Work performance information5. Change requests6. Project management plan updates7. Project documents updates8. Organizational process assets updates
An output of the Perform Integrated Change Control process is:
4.5.3.2 Change LogA change log is used to document changes that occur during a project. These changes and their impact to the project in terms of time, cost, and risk, are communicated to the appropriate stakeholders. Rejected change requests are also captured in the change log.Process: 4.5 Perform Integrated Change ControlPerform Integrated Change Control is the process of reviewing all change requests; approving changes and managing changes to deliverables, organizational process assets, project documents, and the project management plan; and communicating their disposition. It reviews all requests for changes or modifications to project documents, deliverables, baselines, or the project management plan and approves or rejects the changes.Key Benefit: The key benefit of this process is that it allows for documented changes within the project to be considered in an integrated fashion while reducing project risk, which often arises from changes made without consideration to the overall project objectives or plans.Inputs1. Project management plan2. Work performance reports3. Change requests4. Enterprise environmental factors5. Organizational process assetsTools & Techniques1. Expert judgment2. Meetings3. Change control tools Outputs 1. Approved change requests2. Change log3. Project management plan updates4. Project documents updates
During which process does the project team receive bids and proposals?
Process: 12.2 Conduct ProcurementsDefinition: The process of obtaining seller responses, selecting a seller, and awarding a contract.Key Benefit: The key benefit of this process is that it provides alignment of internal and external stakeholder expectations through established agreements.Inputs1. Procurement management plan2. Procurement documents3. Source selection criteria4. Seller proposals5. Project documents6. Make-or-buy decisions7. Procurement statement of work8. Organizational process assetsTools & Techniques1. Bidder conference2. Proposal evaluation techniques3. Independent estimates4. Expert judgment5. Advertising6. Analytical techniques7. Procurement negotiationsOutputs1. .Selected sellers2. .Agreements3. .Resource calendars4. .Change requests5. .Project management plan updates6. .Project documents updates
The process of monitoring the status of the project and product scope as well as managing the changes to the scope baseline is known as:
5.4.3.1 Scope BaselineThe scope baseline is the approved version of a scope statement, work breakdown structure (WBS), and its associated WBS dictionary, that can be changed only through formal change control procedures and is used as a basis for comparison. It is a component of the project management plan. Components of the scope baseline include:Project scope statement. The project scope statement includes the description of the project scope, major deliverables, assumptions, and constraints.WBS. The WBS is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables. Each descending level of the WBS represents an increasingly detailed definition of the project work. The WBS is finalized by assigning each work package to a control account and establishing a unique identifier for that work package from a code of accounts. These identifiers provide a structure for hierarchical summation of costs, schedule, and resource information. A control account is a management control point where scope, budget, actual cost, and schedule are integrated and compared to the earned value for performance measurement. Control accounts are placed at selected management points in the WBS. Each control account may include one or more work packages, but each of the work packages should be associated with only one control account. A control account may include one or more planning packages. A planning package is a work breakdown structure component below the control account with known work content but without detailed schedule activities.WBS dictionary. The WBS dictionary is a document that provides detailed deliverable, activity, and scheduling information about each component in the WBS. The WBS dictionary is a document that supports the WBS. Information in the WBS dictionary may include, but is not limited to:○ Code of account identifier,○ Description of work,○ Assumptions and constraints,○ Responsible organization,○ Schedule milestones,○ Associated schedule activities,○ Resources required,○ Cost estimates,○ Quality requirements,○ Acceptance criteria,○ Technical references, and○ Agreement informationProcess: 5.6 Control ScopeDefinition: The process of monitoring the status of the project and product scope and managing changes to the scope baseline.Key Benefit: The key benefit of this process is that it brings objectivity to the acceptance process and increases the chance of final product, service, or result acceptance by validating each deliverable.Inputs1. Project management plan2. Requirements documentation3. Requirements traceability matrix4. Work performance data5. Organizational process assetsTools & Techniques1. Variance analysisOutputs1. Work performance information 2. Change requests3. Project management plan updates4. Project documents updates5. Organizational process assets updates
Share your comments for PMI PMI-002 exam with other users:
good ones for exam preparation
this is a good experience
hi everyone
waiting for the dump. please upload.
upload cks exam questions
awesome training material
where is dump
q. 289 - the correct answer should be b not d, since the question asks for the most secure way to provide access to a s3 bucket (a single one), and by principle of the least privilege you should not be giving access to all buckets.
please i need if possible h12-831,
good collection of questions and solution for pl500 certification
i would like to appear the exam.
i am very happy as i cleared my comptia a+ 220-1101 exam. i studied from as it has all exam dumps and mock tests available. i got 91% on the test.
need this dump
its really good to eventuate knowledge before appearing for the actual exam.
this is great
please i want the questions to pass the exam
i need to pass exam
great, i appreciate it.
please could you upload (isc)2 certified in cybersecurity (cc) exam questions
good questions, wrong answers
im preparing for exams
question no: 42 isnt azure vm an iaas solution? so, shouldnt the answer be "no"?
im study azure
i need this now
i took the aws saa-c03 test and scored 935/1000. it has all the exam dumps and important info.
good questions
well explained
i got the full version and it helped me pass the exam. pdf version is very good.
provide the download link, please
please upload thank.
please can you share 1z0-1055-22 dump pls
i will wait impatiently. thank youu
is it possible to clear the exam if we focus on only these 156 questions instead of 623 questions? kindly help!
really helped with preparation of my scrum exam