Which input to the Plan Risk Management process provides information on high-level risks?

  1. Project charter
  2. Enterprise environmental factors
  3. Stakeholder register
  4. Organizational process assets

Answer(s): A

Explanation:

4.1.3.1 Project Charter
The project charter is the document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities. It documents the business needs, assumptions, constraints, the understanding of the customer’s needs and high-level requirements, and the new product, service, or result that it is intended to satisfy, such as:
Project purpose or justification,
Measurable project objectives and related success criteria, High-level requirements,
Assumptions and constraints,
High-level project description and boundaries,
High-level risks,
Summary milestone schedule, Summary budget, Stakeholder list,
Project approval requirements (i.e., what constitutes project success, who decides the project is successful, and who signs off on the project),
Assigned project manager, responsibility, and authority level, and
Name and authority of the sponsor or other person(s) authorizing the project charter.

Process: 11.1 Plan Risk Management
Definition: The process of defining how to conduct risk management activities for a project.
Key Benefit: The key benefit of this process is it ensures that the degree, type, and visibility of risk management are commensurate with both the risks and the importance of the project to the organization. The risk management plan is vital to communicate with and obtain agreement and support from all stakeholders to ensure the risk management process is supported and performed effectively over the project life cycle.

Inputs
1. Project management plan
2. Project charter

3. Stakeholder register
4. Enterprise environmental factors
5. Organizational process assets

Tools & Techniques
1. Analytical techniques
2. Expert judgment
3. Meetings

Outputs
1. Risk management plan



Which input may influence quality assurance work and should be monitored within the context of a system for configuration management?

  1. Work performance data
  2. Project documents
  3. Scope baseline
  4. Requirements documentation

Answer(s): B

Explanation:

Configuration control is focused on the specification of both the deliverables and the processes; while change control is focused on identifying, documenting, and approving or rejecting changes to the project documents, deliverables, or baselines.
Some of the configuration management activities included in the Perform Integrated Change Control process are as follows:

Configuration identification. Identification and selection of a configuration item to provide the basis for which the product configuration is defined and verified, products and documents are labeled, changes are managed, and accountability is maintained.
Configuration status accounting. Information is recorded and reported as to when appropriate data about the configuration item should be provided. This information includes a listing of approved configuration identification, status of proposed changes to the configuration, and the implementation status of approved changes.

Configuration verification and audit. Configuration verification and configuration audits ensure the composition of a project’s configuration items is correct and that corresponding changes are registered, assessed, approved, tracked, and correctly implemented. This ensures the functional requirements defined in the configuration documentation have been met.



Change requests are processed for review and disposition according to which process?

  1. Control Quality
  2. Control Scope
  3. Monitor and Control Project Work
  4. Perform Integrated Change Control

Answer(s): D

Explanation:

Process: 4.5 Perform Integrated Change Control
Perform Integrated Change Control is the process of reviewing all change requests; approving changes and managing changes to deliverables, organizational process assets, project documents, and the project management plan; and communicating their disposition. It reviews all requests for changes or modifications to project documents, deliverables, baselines, or the project management plan and approves or rejects the changes.
Key Benefit: The key benefit of this process is that it allows for documented changes within the project to be considered in an integrated fashion while reducing project risk, which often arises from changes made without consideration to the overall project objectives or plans.

Inputs
1. Project management plan
2. Work performance reports
3. Change requests
4. Enterprise environmental factors
5. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Meetings
3. Change control tools

Outputs
1. Approved change requests
2. Change log
3. Project management plan updates
4. Project documents updates



The review of a sellers progress toward achieving the goals of scope and quality within cost and schedule compared to the contract is known as:

  1. Work performance information.
  2. Inspections and audits.
  3. Payment systems.
  4. Procurement performance reviews.

Answer(s): D

Explanation:

Process: 12.3 Control Procurements
Definition: The process of managing procurement relationships, monitoring contract performance, and making changes and corrections as appropriate.
Key Benefit: The key benefit of this process is that it ensures that both the seller’s and buyer’s performance meets procurement requirements according to the terms of the legal agreement.

Inputs
1. Project management plan
2. Procurement documents
3. Agreements
4. Approved change requests
5. Work performance reports

6. Work performance data

Tools & Techniques
1. Contract change control system
2. Procurement performance reviews
3. Inspections and audits
4. Performance reporting
5. Payment systems
6. Claims administration
7. Records management system

Outputs
1. Work performance information
2. Change requests
3. Project management plan updates
4. Project documents updates
5. Organizational process assets updates



The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?

  1. Project Communications Management
  2. Project Integration Management
  3. Project Risk Management
  4. Project Scope Management

Answer(s): B



Share your comments for PMI PMI-002 exam with other users:

A
anonymous
1/11/2024 4:50:00 AM

good questions

A
Anjum
9/23/2023 6:22:00 PM

well explained

T
Thakor
6/7/2023 11:52:00 PM

i got the full version and it helped me pass the exam. pdf version is very good.

S
sartaj
7/18/2023 11:36:00 AM

provide the download link, please

L
loso
7/25/2023 5:18:00 AM

please upload thank.

P
Paul
6/23/2023 7:12:00 AM

please can you share 1z0-1055-22 dump pls

E
exampei
10/7/2023 8:14:00 AM

i will wait impatiently. thank youu

P
Prince
10/31/2023 9:09:00 PM

is it possible to clear the exam if we focus on only these 156 questions instead of 623 questions? kindly help!

A
Ali Azam
12/7/2023 1:51:00 AM

really helped with preparation of my scrum exam

J
Jerman
9/29/2023 8:46:00 AM

very informative and through explanations

J
Jimmy
11/4/2023 12:11:00 PM

prep for exam

A
Abhi
9/19/2023 1:22:00 PM

thanks for helping us

M
mrtom33
11/20/2023 4:51:00 AM

i prepared for the eccouncil 350-401 exam. i scored 92% on the test.

J
JUAN
6/28/2023 2:12:00 AM

aba questions to practice

L
LK
1/2/2024 11:56:00 AM

great content

S
Srijeeta
10/8/2023 6:24:00 AM

how do i get the remaining questions?

J
Jovanne
7/26/2022 11:42:00 PM

well formatted pdf and the test engine software is free. well worth the money i sept.

C
CHINIMILLI SATISH
8/29/2023 6:22:00 AM

looking for 1z0-116

P
Pedro Afonso
1/15/2024 8:01:00 AM

in question 22, shouldnt be in the data (option a) layer?

P
Pushkar
11/7/2022 12:12:00 AM

the questions are incredibly close to real exam. you people are amazing.

A
Ankit S
11/13/2023 3:58:00 AM

q15. answer is b. simple

S
S. R
12/8/2023 9:41:00 AM

great practice

M
Mungara
3/14/2023 12:10:00 AM

thanks to this exam dumps, i felt confident and passed my exam with ease.

A
Anonymous
7/25/2023 2:55:00 AM

need 1z0-1105-22 exam

N
Nigora
5/31/2022 10:05:00 PM

this is a beautiful tool. passed after a week of studying.

A
Av dey
8/16/2023 2:35:00 PM

can you please upload the dumps for 1z0-1096-23 for oracle

M
Mayur Shermale
11/23/2023 12:22:00 AM

its intresting, i would like to learn more abouth this

J
JM
12/19/2023 2:23:00 PM

q252: dns poisoning is the correct answer, not locator redirection. beaconing is detected from a host. this indicates that the system has been infected with malware, which could be the source of local dns poisoning. location redirection works by either embedding the redirection in the original websites code or having a user click on a url that has an embedded redirect. since users at a different office are not getting redirected, it isnt an embedded redirection on the original website and since the user is manually typing in the url and not clicking a link, it isnt a modified link.

F
Freddie
12/12/2023 12:37:00 PM

helpful dump questions

D
Da Costa
8/25/2023 7:30:00 AM

question 423 eigrp uses metric

B
Bsmaind
8/20/2023 9:22:00 AM

hello nice dumps

B
beau
1/12/2024 4:53:00 PM

good resource for learning

S
Sandeep
12/29/2023 4:07:00 AM

very useful

K
kevin
9/29/2023 8:04:00 AM

physical tempering techniques

AI Tutor 👋 I’m here to help!