PMI Certified Associate in Project Management (-100) PMI-002 Dumps in PDF

Free PMI PMI-002 Real Questions (page: 10)

Market conditions and published commercial information are examples of which input to the Estimate Costs process?

  1. Scope baseline
  2. Organizational process assets
  3. Enterprise environmental factors
  4. Risk register

Answer(s): C

Explanation:

7.2.1.6 Enterprise Environmental Factors
Described in Section 2.1.5. The enterprise environmental factors that influence the Estimate Costs process include, but are not limited to:
Market conditions. These conditions describe what products, services, and results are available in the market, from whom, and under what terms and conditions. Regional and/or global supply and demand conditions greatly influence resource costs.
Published commercial information. Resource cost rate information is often available from commercial databases that track skills and human resource costs, and provide standard costs for material and equipment.

Published seller price lists are another source of information.

Process: 7.2 Estimate Costs
Definition: The process of developing an approximation of the monetary resources needed to complete project activities.
Key Benefit: The key benefit of this process is that it determines the amount of cost required to complete project work.

Inputs
1. Cost management plan
2. Human resource management plan
3. Scope baseline
4. Project schedule
5. Risk register
6. Enterprise environmental factors
7. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Analogous estimating
3. Parametric estimating
4. Bottom-up estimating
5. Three-point estimating
6. Reserve analysis
7. Cost of quality
8. Project management software
9. Vendor bid analysis
10. Group decision-making techniques

Outputs
1. Activity cost estimates
2. Basis of estimates
3. Project documents updates



An output of the Develop Project Team process is:

  1. Organizational process assets.
  2. Enterprise environmental factors updates.
  3. Project staff assignments.
  4. Organizational charts and position descriptions.

Answer(s): B



The process of confirming human resource availability and obtaining the team necessary to complete project activities is known as:

  1. Plan Human Resource Management.
  2. Acquire Project Team.
  3. Manage Project Team.
  4. Develop Project Team.

Answer(s): B

Explanation:

Process: 9.2 Acquire Project Team
Definition: The process of confirming human resource availability and obtaining the team necessary to complete project activities.
Key Benefit: The key benefit of this process consists of outlining and guiding the team selection and responsibility assignment to obtain a successful team.
Inputs
1. Human resource management plan
2. Enterprise environmental factors
3. Organizational process assets

Tools & Techniques
1. Pre-assignment
2. Negotiation
3. Acquisition
4. Virtual teams
5. Multi-criteria decision analysis

Outputs
1. Project staff assignments
2. Resource calendars
3. Project management plan updates



Which item is an example of personnel assessment?

  1. Resource calendar
  2. Tight matrix
  3. Team-building activity
  4. Focus group

Answer(s): D



The Plan Stakeholder Management process belongs to which Process Group?

  1. Executing
  2. Initiating
  3. Planning
  4. Monitoring and Controlling

Answer(s): C

Explanation:

Planning Process Group
4.2 Develop Project Management Plan
5.1 Plan Scope Management
5.2 Collect Requirements
5.3 Define Scope
5.4 Create WBS
6.1 Plan Schedule Management
6.2 Define Activities
6.3 Sequence Activities
6.4 Estimate Activity Resources
6.5 Estimate Activity Durations
6.6 Develop Schedule
7.1 Plan Cost Management
7.2 Estimate Costs
7.3 Determine Budget
8.1 Plan Quality Management
9.1 Plan Human Resource Management
10.1 Plan Communications Management
11.1 Plan Risk Management
11.2 Identify Risks
11.3 Perform Qualitative Risk Analysis
11.4 Perform Quantitative Risk Analysis
11.5 Plan Risk Responses
12.1 Plan Procurement Management
13.2 Plan Stakeholder Management



Share your comments for PMI PMI-002 exam with other users:

R
Ranjith
8/21/2023 3:39:00 PM

for question #118, the answer is option c. the screen shot is showing the drop down, but the answer is marked incorrectly please update . thanks for sharing such nice questions.

E
Eduardo Ramírez
12/11/2023 9:55:00 PM

the correct answer for the question 29 is d.

D
Dass
11/2/2023 7:43:00 AM

question no 22: correct answers: bc, 1 per session 1 per page 1 per component always

R
Reddy
12/14/2023 2:42:00 AM

these are pretty useful

D
Daisy Delgado
1/9/2023 1:05:00 PM

awesome

A
Atif
6/13/2023 4:09:00 AM

yes please upload

X
Xunil
6/12/2023 3:04:00 PM

great job whoever put this together, for the greater good! thanks!

L
Lakshmi
10/2/2023 5:26:00 AM

just started to view all questions for the exam

R
rani
1/19/2024 11:52:00 AM

helpful material

G
Greg
11/16/2023 6:59:00 AM

hope for the best

H
hi
10/5/2023 4:00:00 AM

will post exam has finished

V
Vmotu
8/24/2023 11:14:00 AM

really correct and good analyze!

H
hicham
5/30/2023 8:57:00 AM

excellent thanks a lot

S
Suman C
7/7/2023 8:13:00 AM

will post once pass the cka exam

R
Ram
11/3/2023 5:10:00 AM

good content

N
Nagendra Pedipina
7/13/2023 2:12:00 AM

q:32 answer has to be option c

T
Tamer Barakat
12/7/2023 5:17:00 PM

nice questions

D
Daryl
8/1/2022 11:33:00 PM

i really like the support team in this website. they are fast in communication and very helpful.

C
Curtis Nakawaki
6/29/2023 9:13:00 PM

a good contemporary exam review

X
x-men
5/23/2023 1:02:00 AM

q23, its an array, isnt it? starts with [ and end with ]. its an array of objects, not object.

A
abuti
7/21/2023 6:24:00 PM

cool very helpfull

K
Krishneel
3/17/2023 10:34:00 AM

i just passed. this exam dumps is the same one from prepaway and examcollection. it has all the real test questions.

R
Regor
12/4/2023 2:01:00 PM

is this a valid prince2 practitioner dumps?

A
asl
9/14/2023 3:59:00 PM

all are relatable questions

S
Siyya
1/19/2024 8:30:00 PM

might help me to prepare for the exam

T
Ted
6/21/2023 11:11:00 PM

just paid and downlaod the 2 exams using the 50% sale discount. so far i was able to download the pdf and the test engine. all looks good.

P
Paul K
11/27/2023 2:28:00 AM

i think it should be a,c. option d goes against the principle of building anything custom unless there are no work arounds available

P
ph
6/16/2023 12:41:00 AM

very legible

S
sephs2001
7/31/2023 10:42:00 PM

is this exam accurate or helpful?

A
ash
7/11/2023 3:00:00 AM

please upload dump, i have exam in 2 days

S
Sneha
8/17/2023 6:29:00 PM

this is useful

S
sachin
12/27/2023 2:45:00 PM

question 232 answer should be perimeter not netowrk layer. wrong answer selected

T
tomAws
7/18/2023 5:05:00 AM

nice questions

R
Rahul
6/11/2023 2:07:00 AM

hi team, could you please provide this dump ?

AI Tutor 👋 I’m here to help!