You are the program manager of the HNG Program. This program has a budget at completion of $2,345,900 and is expected to last two years. The program is currently 30 percent complete and you have spent $789,000. The program is supposed to be 35 percent complete but do to some delays you're slightly behind schedule.
Based on this information, what is the schedule variance (SV) of this program?

  1. -$85,230
  2. $821,065
  3. -$284,100
  4. -$117,295

Answer(s): D



Which of the following documents provides the mandate to execute the program within a certain timeline and also presents milestones for the delivery of products or incremental benefits?

  1. Program architecture baseline
  2. Program risk register
  3. Program WBS
  4. Program charter

Answer(s): D



In which of the following processes is the program charter created?

  1. Establish Program Financial Framework
  2. Plan Program Scope
  3. Initiate Program
  4. Develop Program Management Plan

Answer(s): C



You are the program manager of the HNG Program. This program has a budget at completion of $2,345,900 and is expected to last two years. The program is currently 30 percent complete and you have spent $789,000. The program is supposed to be 35 percent complete but do to some delays you're slightly behind schedule.
Based on this information, how many pennies is the program losing per dollar invested in the program work?

  1. 17
  2. 11
  3. 15
  4. 14

Answer(s): B



You are the program manager for your organization. You have created a program that will create things for the organization throughout the program not only at program closure. All of the following are elements that you may transfer to the organization throughout the program's life cycle except for which one?

  1. Benefits
  2. Risk management outcomes
  3. Program personnel
  4. Outputs from team development

Answer(s): C



You are the program manager for your organization and are planning the program. One of the plans you need to create will define how you'll transfer the benefits of the program to the operations of your organization.
Which program management plan defines this process?

  1. Operational transfer plan
  2. Program transition plan
  3. Benefits transfer plan
  4. Program closure plan

Answer(s): B



A program has a BAC of $1,750,000 and is expected to last two years. The program is currently at the third milestone which represents 35 percent of the program work. As it happens, this program has already spent
$620,000 of the budget. Management is concerned that the program may also be slipping on schedule because the program should be forty percent complete by this time. Based on this information which type of performing is present in this scenario?

  1. Schedule, because the program's planned value is only $700,000.
  2. Cost, because the program has a cost variance of -7,500
  3. Schedule, because the program has a schedule performance index of .88.
  4. Cost, because the program has an estimate to complete of $1,151,429.

Answer(s): C



You are the program manager for your organization. Your current program is to create a new recreational facility in your city. Franklin, the Chief Executive Officer, is concerned about meeting all of the financial and schedule requirements of the proposed program. Martina, the mayor of your town, wants to make certain the program meets all safety requirements and building codes. Your supervisor, Mary Ann, is the Program Director, and she is concerned about the start date of your program. Another stakeholder, Hal, is worried that your resources may be spread thin on the program as some of the resources are on multiple projects in your program.
To whom will you report to in this program?

  1. Franklin
  2. Martina
  3. Hal
  4. Mary Ann

Answer(s): D



Viewing Page 8 of 79



Share your comments for PMI PGMP exam with other users:

tumz 1/16/2024 10:30:00 AM

very helpful
UNITED STATES


NRI 8/27/2023 10:05:00 AM

will post once the exam is finished
UNITED STATES


kent 11/3/2023 10:45:00 AM

relevant questions
Anonymous


Qasim 6/11/2022 9:43:00 AM

just clear exam on 10/06/2202 dumps is valid all questions are came same in dumps only 2 new questions total 46 questions 1 case study with 5 question no lab/simulation in my exam please check the answers best of luck
Anonymous


Cath 10/10/2023 10:09:00 AM

q.112 - correct answer is c - the event registry is a module that provides event definitions. answer a - not correct as it is the definition of event log
VIET NAM


Shiji 10/15/2023 1:31:00 PM

good and useful.
INDIA


Ade 6/25/2023 1:14:00 PM

good questions
Anonymous


Praveen P 11/8/2023 5:18:00 AM

good content
UNITED STATES


Anastasiia 12/28/2023 9:06:00 AM

totally not correct answers. 21. you have one gcp account running in your default region and zone and another account running in a non-default region and zone. you want to start a new compute engine instance in these two google cloud platform accounts using the command line interface. what should you do? correct: create two configurations using gcloud config configurations create [name]. run gcloud config configurations activate [name] to switch between accounts when running the commands to start the compute engine instances.
Anonymous


Priyanka 7/24/2023 2:26:00 AM

kindly upload the dumps
Anonymous


Nabeel 7/25/2023 4:11:00 PM

still learning
Anonymous


gure 7/26/2023 5:10:00 PM

excellent way to learn
UNITED STATES


ciken 8/24/2023 2:55:00 PM

help so much
Anonymous


Biswa 11/20/2023 9:28:00 AM

understand sql col.
Anonymous


Saint Pierre 10/24/2023 6:21:00 AM

i would give 5 stars to this website as i studied for az-800 exam from here. it has all the relevant material available for preparation. i got 890/1000 on the test.
Anonymous


Rose 7/24/2023 2:16:00 PM

this is nice.
Anonymous


anon 10/15/2023 12:21:00 PM

q55- the ridac workflow can be modified using flow designer, correct answer is d not a
UNITED STATES


NanoTek3 6/13/2022 10:44:00 PM

by far this is the most accurate exam dumps i have ever purchased. all questions are in the exam. i saw almost 90% of the questions word by word.
UNITED STATES


eriy 11/9/2023 5:12:00 AM

i cleared the az-104 exam by scoring 930/1000 on the exam. it was all possible due to this platform as it provides premium quality service. thank you!
UNITED STATES


Muhammad Rawish Siddiqui 12/8/2023 8:12:00 PM

question # 232: accessibility, privacy, and innovation are not data quality dimensions.
SAUDI ARABIA


Venkat 12/27/2023 9:04:00 AM

looks wrong answer for 443 question, please check and update
Anonymous


Varun 10/29/2023 9:11:00 PM

great question
Anonymous


Doc 10/29/2023 9:36:00 PM

question: a user wants to start a recruiting posting job posting. what must occur before the posting process can begin? 3 ans: comment- option e is incorrect reason: as part of enablement steps, sap recommends that to be able to post jobs to a job board, a user need to have the correct permission and secondly, be associated with one posting profile at minimum
UNITED KINGDOM


It‘s not A 9/17/2023 5:31:00 PM

answer to question 72 is d [sys_user_role]
Anonymous


indira m 8/14/2023 12:15:00 PM

please provide the pdf
UNITED STATES


ribrahim 8/1/2023 6:05:00 AM

hey guys, just to let you all know that i cleared my 312-38 today within 1 hr with 100 questions and passed. thank you so much brain-dumps.net all the questions that ive studied in this dump came out exactly the same word for word "verbatim". you rock brain-dumps.net!!! section name total score gained score network perimeter protection 16 11 incident response 10 8 enterprise virtual, cloud, and wireless network protection 12 8 application and data protection 13 10 network défense management 10 9 endpoint protection 15 12 incident d
SINGAPORE


Andrew 8/23/2023 6:02:00 PM

very helpful
Anonymous


latha 9/7/2023 8:14:00 AM

useful questions
GERMANY


ibrahim 11/9/2023 7:57:00 AM

page :20 https://exam-dumps.com/snowflake/free-cof-c02-braindumps.html?p=20#collapse_453 q 74: true or false: pipes can be suspended and resumed. true. desc.: pausing or resuming pipes in addition to the pipe owner, a role that has the following minimum permissions can pause or resume the pipe https://docs.snowflake.com/en/user-guide/data-load-snowpipe-intro
FINLAND


Franklin Allagoa 7/5/2023 5:16:00 AM

i want hcia exam dumps
Anonymous


SSA 12/24/2023 1:18:00 PM

good training
Anonymous


BK 8/11/2023 12:23:00 PM

very useful
INDIA


Deepika Narayanan 7/13/2023 11:05:00 PM

yes need this exam dumps
Anonymous


Blessious Phiri 8/15/2023 3:31:00 PM

these questions are a great eye opener
Anonymous