You are the program manager for your organization. You are examining the order of the activities in your program schedule and would like to change some of the ordering to alleviate scheduling conflicts, risks, and based on your experience with the discipline the program uses. Some of the activities you can rearrange while some of the activities must be completed in a particular order. What term describes the activities that can happen in any order?

  1. Finish on constraints
  2. Discretionary dependencies
  3. Mandatory dependencies
  4. Benefits management dependencies

Answer(s): C



You are the program manager for your organization and are planning the roles and responsibilities in your program. You would like to create a RACI chart for the program work. What does RACI mean?

  1. It is a roles and responsibilities chart that uses responsible, accountable, consult, and inform responsibilities as the chart legend.
  2. It is a roles and responsibilities chart that uses responsible, action, consult, and interest responsibilities as the chart legend.
  3. It is a roles and responsibilities chart that uses resource, action, contribute, inform responsibilities as the chart legend.
  4. It is a roles and responsibilities chart that uses responsible, accountable, contribute, and inform responsibilities as the chart legend.

Answer(s): A



You are the program manager of the OFE Program. You are working with your program team and project managers to ensure that there is consistency in the execution of the program plan. You stress that the work has been planned and now the team must accurately complete the work. You want to ensure that the work is done correctly the first time in the program. What type of process are you stressing to your program team and project managers?

  1. Quality assurance
  2. Scope verification
  3. Quality control
  4. Process improvement

Answer(s): A



You are the program manager for your company and are monitoring and controlling several aspects of your program. You want to make certain that you're including all areas that need to be monitored and controlled. Which one of the following is not something you'll have to monitor and control as a program manager?

  1. Materials required by the program
  2. Equipment your program uses
  3. Susan the application developer in your program
  4. Stakeholder identification

Answer(s): D



A program has a budget at completion of $1,250,000 and has already spent $425,000. The program is running late due to some vendor delays; the program is only 30 percent complete though it was scheduled to be 45 percent at this time. Based on this information how much more money will this program need to finish?

  1. $978,445
  2. $919,325
  3. $991,667
  4. $987,544

Answer(s): C



Your program has a budget at completion of $1,550,000 and is expected to last one year.
Currently your program is 45 percent complete and has spent $725,000. According to the program schedule you are actually to be fifty percent complete by this time, but due to some vendor delays your program is running just a bit late. Based on this information which is performing worse, the cost or schedule?

  1. The schedule is performing worse because the SPI is .90
  2. The cost is performing worse because the EAC is $1,611,111.
  3. The schedule is performing worse because the SV is -$27,500.
  4. The cost is performing worse because the CPI is .96.

Answer(s): A



Which of the following is not a template element that is designed to make the project more effective?

  1. Description of the work packages
  2. Required resources and skills
  3. Required actions to complete the project scope
  4. Contract file

Answer(s): D



You are coaching Tammy, a project manager in your program, on the benefits of program management. She is stumped as to why you would create a program so you're sharing with her all the difference benefits of a program. Which one of the following is a benefit of creating a program?

  1. Programs always cost less than multiple projects in an organization.
  2. Project management is centralized to the program manager.
  3. Programs provide centralized risk management.
  4. Program management makes communication easier among the project managers and project team.

Answer(s): C



Viewing Page 6 of 79



Share your comments for PMI PGMP exam with other users:

ED SHAW 7/31/2023 10:34:00 AM

please allow to download
UNITED STATES


AD 7/22/2023 11:29:00 AM

please provide dumps
UNITED STATES


Ayyjayy 11/6/2023 7:29:00 AM

is the answer to question 15 correct ? i feel like the answer should be b
BAHRAIN


Blessious Phiri 8/12/2023 11:56:00 AM

its getting more technical
Anonymous


Jeanine J 7/11/2023 3:04:00 PM

i think these questions are what i need.
UNITED STATES


Aderonke 10/23/2023 2:13:00 PM

helpful assessment
UNITED KINGDOM


Tom 1/5/2024 2:32:00 AM

i am confused about the answers to the questions. do you know if the answers are correct?
KOREA REPUBLIC OF


Vinit N. 8/28/2023 2:33:00 AM

hi, please make the dumps available for my upcoming examination.
UNITED STATES


Sanyog Deshpande 9/14/2023 7:05:00 AM

good practice
UNITED STATES


Tyron 9/8/2023 12:12:00 AM

so far it is really informative
Anonymous


beast 7/30/2023 2:22:00 PM

hi i want it please please upload it
Anonymous


Mirex 5/26/2023 3:45:00 AM

am preparing for exam ,just nice questions
Anonymous


exampei 8/7/2023 8:05:00 AM

please upload c_tadm_23 exam
TURKEY


Anonymous 9/12/2023 12:50:00 PM

can we get tdvan4 vantage data engineering pdf?
UNITED STATES


Aish 10/11/2023 5:51:00 AM

want to clear the exam.
INDIA


Smaranika 6/22/2023 8:42:00 AM

could you please upload the dumps of sap c_sac_2302
INDIA


Blessious Phiri 8/15/2023 1:56:00 PM

asm management configuration is about storage
Anonymous


Lewis 7/6/2023 8:49:00 PM

kool thumb up
UNITED STATES


Moreece 5/15/2023 8:44:00 AM

just passed the az-500 exam this last friday. most of the questions in this exam dumps are in the exam. i bought the full version and noticed some of the questions which were answered wrong in the free version are all corrected in the full version. this site is good but i wish the had it in an interactive version like a test engine simulator.
Anonymous


Terry 5/24/2023 4:41:00 PM

i can practice for exam
Anonymous


Emerys 7/29/2023 6:55:00 AM

please i need this exam.
Anonymous


Goni Mala 9/2/2023 12:27:00 PM

i need the dump
Anonymous


Lenny 9/29/2023 11:30:00 AM

i want it bad, even if cs6 maybe retired, i want to learn cs6
HONG KONG


MilfSlayer 12/28/2023 8:32:00 PM

i hate comptia with all my heart with their "choose the best" answer format as an argument could be made on every question. they say "the "comptia way", lmao no this right here boys is the comptia way 100%. take it from someone whos failed this exam twice but can configure an entire complex network that these are the questions that are on the test 100% no questions asked. the pbqs are dead on! nice work
Anonymous


Swati Raj 11/14/2023 6:28:00 AM

very good materials
UNITED STATES


Ko Htet 10/17/2023 1:28:00 AM

thanks for your support.
Anonymous


Philippe 1/22/2023 10:24:00 AM

iam impressed with the quality of these dumps. they questions and answers were easy to understand and the xengine app was very helpful to use.
CANADA


Sam 8/31/2023 10:32:00 AM

not bad but you question database from isaca
MALAYSIA


Brijesh kr 6/29/2023 4:07:00 AM

awesome contents
INDIA


JM 12/19/2023 1:22:00 PM

answer to 134 is casb. while data loss prevention is the goal, in order to implement dlp in cloud applications you need to deploy a casb.
UNITED STATES


Neo 7/26/2023 9:36:00 AM

are these brain dumps sufficient enough to go write exam after practicing them? or does one need more material this wont be enough?
SOUTH AFRICA


Bilal 8/22/2023 6:33:00 AM

i did attend the required cources and i need to be sure that i am ready to take the exam, i would ask you please to share the questions, to be sure that i am fit to proceed with taking the exam.
Anonymous


John 11/12/2023 8:48:00 PM

why only give explanations on some, and not all questions and their respective answers?
UNITED STATES


Biswa 11/20/2023 8:50:00 AM

refresh db knowledge
Anonymous