You are the program manager for your organization. You are examining the order of the activities in your program schedule and would like to change some of the ordering to alleviate scheduling conflicts, risks, and based on your experience with the discipline the program uses. Some of the activities you can rearrange while some of the activities must be completed in a particular order. What term describes the activities that can happen in any order?

  1. Finish on constraints
  2. Discretionary dependencies
  3. Mandatory dependencies
  4. Benefits management dependencies

Answer(s): C



You are the program manager for your organization and are planning the roles and responsibilities in your program. You would like to create a RACI chart for the program work. What does RACI mean?

  1. It is a roles and responsibilities chart that uses responsible, accountable, consult, and inform responsibilities as the chart legend.
  2. It is a roles and responsibilities chart that uses responsible, action, consult, and interest responsibilities as the chart legend.
  3. It is a roles and responsibilities chart that uses resource, action, contribute, inform responsibilities as the chart legend.
  4. It is a roles and responsibilities chart that uses responsible, accountable, contribute, and inform responsibilities as the chart legend.

Answer(s): A



You are the program manager of the OFE Program. You are working with your program team and project managers to ensure that there is consistency in the execution of the program plan. You stress that the work has been planned and now the team must accurately complete the work. You want to ensure that the work is done correctly the first time in the program. What type of process are you stressing to your program team and project managers?

  1. Quality assurance
  2. Scope verification
  3. Quality control
  4. Process improvement

Answer(s): A



You are the program manager for your company and are monitoring and controlling several aspects of your program. You want to make certain that you're including all areas that need to be monitored and controlled. Which one of the following is not something you'll have to monitor and control as a program manager?

  1. Materials required by the program
  2. Equipment your program uses
  3. Susan the application developer in your program
  4. Stakeholder identification

Answer(s): D



A program has a budget at completion of $1,250,000 and has already spent $425,000. The program is running late due to some vendor delays; the program is only 30 percent complete though it was scheduled to be 45 percent at this time. Based on this information how much more money will this program need to finish?

  1. $978,445
  2. $919,325
  3. $991,667
  4. $987,544

Answer(s): C



Your program has a budget at completion of $1,550,000 and is expected to last one year.
Currently your program is 45 percent complete and has spent $725,000. According to the program schedule you are actually to be fifty percent complete by this time, but due to some vendor delays your program is running just a bit late. Based on this information which is performing worse, the cost or schedule?

  1. The schedule is performing worse because the SPI is .90
  2. The cost is performing worse because the EAC is $1,611,111.
  3. The schedule is performing worse because the SV is -$27,500.
  4. The cost is performing worse because the CPI is .96.

Answer(s): A



Which of the following is not a template element that is designed to make the project more effective?

  1. Description of the work packages
  2. Required resources and skills
  3. Required actions to complete the project scope
  4. Contract file

Answer(s): D



You are coaching Tammy, a project manager in your program, on the benefits of program management. She is stumped as to why you would create a program so you're sharing with her all the difference benefits of a program. Which one of the following is a benefit of creating a program?

  1. Programs always cost less than multiple projects in an organization.
  2. Project management is centralized to the program manager.
  3. Programs provide centralized risk management.
  4. Program management makes communication easier among the project managers and project team.

Answer(s): C



Share your comments for PMI PGMP exam with other users:

S
sachin
6/27/2023 1:22:00 PM

can you share the pdf

B
Blessious Phiri
8/13/2023 10:26:00 AM

admin ii is real technical stuff

L
Luis Manuel
7/13/2023 9:30:00 PM

could you post the link

V
vijendra
8/18/2023 7:54:00 AM

hello send me dumps

S
Simeneh
7/9/2023 8:46:00 AM

it is very nice

J
john
11/16/2023 5:13:00 PM

i gave the amazon dva-c02 tests today and passed. very helpful.

T
Tao
11/20/2023 8:53:00 AM

there is an incorrect word in the problem statement. for example, in question 1, there is the word "speci c". this is "specific. in the other question, there is the word "noti cation". this is "notification. these mistakes make this site difficult for me to use.

P
patricks
10/24/2023 6:02:00 AM

passed my az-120 certification exam today with 90% marks. studied using the dumps highly recommended to all.

A
Ananya
9/14/2023 5:17:00 AM

i need it, plz make it available

J
JM
12/19/2023 2:41:00 PM

q47: intrusion prevention system is the correct answer, not patch management. by definition, there are no patches available for a zero-day vulnerability. the way to prevent an attacker from exploiting a zero-day vulnerability is to use an ips.

R
Ronke
8/18/2023 10:39:00 AM

this is simple but tiugh as well

C
CesarPA
7/12/2023 10:36:00 PM

questão 4, segundo meu compilador local e o site https://www.jdoodle.com/online-java-compiler/, a resposta correta é "c" !

J
Jeya
9/13/2023 7:50:00 AM

its very useful

T
Tracy
10/24/2023 6:28:00 AM

i mastered my skills and aced the comptia 220-1102 exam with a score of 920/1000. i give the credit to for my success.

J
James
8/17/2023 4:33:00 PM

real questions

A
Aderonke
10/23/2023 1:07:00 PM

very helpful assessments

S
Simmi
8/24/2023 7:25:00 AM

hi there, i would like to get dumps for this exam

J
johnson
10/24/2023 5:47:00 AM

i studied for the microsoft azure az-204 exam through it has 100% real questions available for practice along with various mock tests. i scored 900/1000.

M
Manas
9/9/2023 1:48:00 AM

please upload 1z0-1072-23 exam dups

S
SB
9/12/2023 5:15:00 AM

i was hoping if you could please share the pdf as i’m currently preparing to give the exam.

J
Jagjit
8/26/2023 5:01:00 PM

i am looking for oracle 1z0-116 exam

S
S Mallik
11/27/2023 12:32:00 AM

where we can get the answer to the questions

P
PiPi Li
12/12/2023 8:32:00 PM

nice questions

D
Dan
8/10/2023 4:19:00 PM

question 129 is completely wrong.

G
gayathiri
7/6/2023 12:10:00 AM

i need dump

D
Deb
8/15/2023 8:28:00 PM

love the site.

M
Michelle
6/23/2023 4:08:00 AM

can you please upload it back?

A
Ajay
10/3/2023 12:17:00 PM

could you please re-upload this exam? thanks a lot!

H
him
9/30/2023 2:38:00 AM

great about shared quiz

S
San
11/14/2023 12:46:00 AM

goood helping

W
Wang
6/9/2022 10:05:00 PM

pay attention to questions. they are very tricky. i waould say about 80 to 85% of the questions are in this exam dump.

M
Mary
5/16/2023 4:50:00 AM

wish you would allow more free questions

T
thomas
9/12/2023 4:28:00 AM

great simulation

S
Sandhya
12/9/2023 12:57:00 AM

very g inood

AI Tutor 👋 I’m here to help!