You are the program manager for your organization. You are examining the order of the activities in your program schedule and would like to change some of the ordering to alleviate scheduling conflicts, risks, and based on your experience with the discipline the program uses. Some of the activities you can rearrange while some of the activities must be completed in a particular order. What term describes the activities that can happen in any order?

  1. Finish on constraints
  2. Discretionary dependencies
  3. Mandatory dependencies
  4. Benefits management dependencies

Answer(s): C



You are the program manager for your organization and are planning the roles and responsibilities in your program. You would like to create a RACI chart for the program work. What does RACI mean?

  1. It is a roles and responsibilities chart that uses responsible, accountable, consult, and inform responsibilities as the chart legend.
  2. It is a roles and responsibilities chart that uses responsible, action, consult, and interest responsibilities as the chart legend.
  3. It is a roles and responsibilities chart that uses resource, action, contribute, inform responsibilities as the chart legend.
  4. It is a roles and responsibilities chart that uses responsible, accountable, contribute, and inform responsibilities as the chart legend.

Answer(s): A



You are the program manager of the OFE Program. You are working with your program team and project managers to ensure that there is consistency in the execution of the program plan. You stress that the work has been planned and now the team must accurately complete the work. You want to ensure that the work is done correctly the first time in the program. What type of process are you stressing to your program team and project managers?

  1. Quality assurance
  2. Scope verification
  3. Quality control
  4. Process improvement

Answer(s): A



You are the program manager for your company and are monitoring and controlling several aspects of your program. You want to make certain that you're including all areas that need to be monitored and controlled. Which one of the following is not something you'll have to monitor and control as a program manager?

  1. Materials required by the program
  2. Equipment your program uses
  3. Susan the application developer in your program
  4. Stakeholder identification

Answer(s): D



A program has a budget at completion of $1,250,000 and has already spent $425,000. The program is running late due to some vendor delays; the program is only 30 percent complete though it was scheduled to be 45 percent at this time. Based on this information how much more money will this program need to finish?

  1. $978,445
  2. $919,325
  3. $991,667
  4. $987,544

Answer(s): C



Your program has a budget at completion of $1,550,000 and is expected to last one year.
Currently your program is 45 percent complete and has spent $725,000. According to the program schedule you are actually to be fifty percent complete by this time, but due to some vendor delays your program is running just a bit late. Based on this information which is performing worse, the cost or schedule?

  1. The schedule is performing worse because the SPI is .90
  2. The cost is performing worse because the EAC is $1,611,111.
  3. The schedule is performing worse because the SV is -$27,500.
  4. The cost is performing worse because the CPI is .96.

Answer(s): A



Which of the following is not a template element that is designed to make the project more effective?

  1. Description of the work packages
  2. Required resources and skills
  3. Required actions to complete the project scope
  4. Contract file

Answer(s): D



You are coaching Tammy, a project manager in your program, on the benefits of program management. She is stumped as to why you would create a program so you're sharing with her all the difference benefits of a program. Which one of the following is a benefit of creating a program?

  1. Programs always cost less than multiple projects in an organization.
  2. Project management is centralized to the program manager.
  3. Programs provide centralized risk management.
  4. Program management makes communication easier among the project managers and project team.

Answer(s): C



Share your comments for PMI PGMP exam with other users:

L
Luis
11/16/2023 1:39:00 PM

can anyone tell me if this is for rhel8 or rhel9?

H
hik
1/19/2024 1:47:00 PM

good content

B
Blessious Phiri
8/15/2023 2:18:00 PM

pdb and cdb are critical to the database

Z
Zuned
10/22/2023 4:39:00 AM

till 104 questions are free, lets see how it helps me in my exam today.

M
Muhammad Rawish Siddiqui
12/3/2023 12:11:00 PM

question # 56, answer is true not false.

A
Amaresh Vashishtha
8/27/2023 1:33:00 AM

i would be requiring dumps to prepare for certification exam

A
Asad
9/8/2023 1:01:00 AM

very helpful

B
Blessious Phiri
8/13/2023 3:10:00 PM

control file is the heart of rman backup

S
Senthil
9/19/2023 5:47:00 AM

hi could you please upload the ibm c2090-543 dumps

H
Harry
6/27/2023 7:20:00 AM

appriciate if you could upload this again

A
Anonymous
7/10/2023 4:10:00 AM

please upload the dump

R
Raja
6/20/2023 5:30:00 AM

i found some questions answers mismatch with explanation answers. please properly update

D
Doora
11/30/2023 4:20:00 AM

nothing to mention

D
deally
1/19/2024 3:41:00 PM

knowable questions

S
Sonia
7/23/2023 4:03:00 PM

very helpfull

B
binEY
10/6/2023 5:15:00 AM

good questions

N
Neha
9/28/2023 1:58:00 PM

its helpful

D
Desmond
1/5/2023 9:11:00 PM

i just took my oracle exam and let me tell you, this exam dumps was a lifesaver! without them, iam not sure i would have passed. the questions were tricky and the answers were obscure, but the exam dumps had everything i needed. i would recommend to anyone looking to pass their oracle exams with flying colors (and a little bit of cheating) lol.

D
Davidson OZ
9/9/2023 6:37:00 PM

22. if you need to make sure that one computer in your hot-spot network can access the internet without hot-spot authentication, which menu allows you to do this? answer is ip binding and not wall garden. wall garden allows specified websites to be accessed with users authentication to the hotspot

3
381
9/2/2023 4:31:00 PM

is question 1 correct?

L
Laurent
10/6/2023 5:09:00 PM

good content

S
Sniper69
5/9/2022 11:04:00 PM

manged to pass the exam with this exam dumps.

D
Deepak
12/27/2023 2:37:00 AM

good questions

D
dba
9/23/2023 3:10:00 AM

can we please have the latest exam questions?

P
Prasad
9/29/2023 7:27:00 AM

please help with jn0-649 latest dumps

G
GTI9982
7/31/2023 10:15:00 PM

please i need this dump. thanks

E
Elton Riva
12/12/2023 8:20:00 PM

i have to take the aws certified developer - associate dva-c02 in the next few weeks and i wanted to know if the questions on your website are the same as the official exam.

B
Berihun Desalegn Wonde
7/13/2023 11:00:00 AM

all questions are more important

G
gr
7/2/2023 7:03:00 AM

ques 4 answer should be c ie automatically recover from failure

R
RS
7/27/2023 7:17:00 AM

very very useful page

B
Blessious Phiri
8/12/2023 11:47:00 AM

the exams are giving me an eye opener

A
AD
10/22/2023 9:08:00 AM

3rd so far, need to cover more

M
Matt
11/18/2023 2:32:00 AM

aligns with the pecd notes

S
Sri
10/15/2023 4:38:00 PM

question 4: b securityadmin is the correct answer. https://docs.snowflake.com/en/user-guide/security-access-control-overview#access-control-framework

AI Tutor 👋 I’m here to help!