AACE International Planning & Scheduling Professional (PSP) AACE-PSP Exam Questions in PDF

Free AACE International AACE-PSP Dumps Questions (page: 5)

Which of the following is NOT required when performing weekly or monthly schedule updates?

  1. Percent complete.
  2. Remaining duration of activities.
  3. Actual finish of activities.
  4. Original duration of activities.

Answer(s): B



Which of the following will always describe the critical path? The path with

  1. The longest duration through the network.
  2. Zero float.
  3. Negative float.
  4. The shortest duration and negative float.

Answer(s): B



Of the following update procedures, which is the least important in achieving an accurate forecast for completion of a construction schedule?

  1. Estimating remaining durations of activities.
  2. The correct recording of actual start dates.
  3. Making "downstream" logic revisions as required.
  4. Entering the time impacts of delays and change orders.

Answer(s): C



What method would be the best way to determine the most likely as-built critical path of a project that is underway, and the schedule of which has been partially progressed?

  1. Use the progressed portion of the critical path of all the updates previous to the current update.
  2. Use the progressed portion of the critical path of the baseline schedule.
  3. Interview the project personnel for their perceptions and opinions because the schedule is usually inadequate.
  4. Use the forward-looking critical path of the most current updates.

Answer(s): A



An earned value-based project control system can use either of which two budgets as the basis of its calculations?

  1. Labor hours or dollars.
  2. Direct or indirect cost.
  3. Earned or budgeted cost yearly.
  4. Linear feet or dollars.

Answer(s): A



Share your comments for AACE International AACE-PSP exam with other users:

U
unanimous
12/15/2023 6:38:00 AM

very nice very nice

A
akminocha
9/28/2023 10:36:00 AM

please help us with 1z0-1107-2 dumps

J
Jefi
9/4/2023 8:15:00 AM

please upload the practice questions

T
Thembelani
5/30/2023 2:45:00 AM

need this dumps

A
Abduraimov
4/19/2023 12:43:00 AM

preparing for this exam is overwhelming. you cannot pass without the help of these exam dumps.

P
Puneeth
10/5/2023 2:06:00 AM

new to this site but i feel it is good

A
Ashok Kumar
1/2/2024 6:53:00 AM

the correct answer to q8 is b. explanation since the mule app has a dependency, it is necessary to include project modules and dependencies to make sure the app will run successfully on the runtime on any other machine. source code of the component that the mule app is dependent of does not need to be included in the exported jar file, because the source code is not being used while executing an app. compiled code is being used instead.

M
Merry
7/30/2023 6:57:00 AM

good questions

V
VoiceofMidnight
12/17/2023 4:07:00 PM

Delayed the exam until December 29th.

U
Umar Ali
8/29/2023 2:59:00 PM

A and D are True

V
vel
8/28/2023 9:17:09 AM

good one with explanation

G
Gurdeep
1/18/2024 4:00:15 PM

This is one of the most useful study guides I have ever used.

AI Tutor 👋 I’m here to help!