An earned value-based project control system can use either of which two budgets as the basis of its calculations?
Answer(s): A
An earned value management (EVM) system can base its calculations on labor hours or monetary values, depending on the nature of the project. Both methods are valid for tracking performance and forecasting outcomes.Option B (direct or indirect cost) does not align with EVM's focus on performance metrics.Option C confuses timeframes with budgeting principles.Option D (linear feet or dollars) applies to physical progress tracking but not directly to EVM systems.This is consistent with EVM principles as outlined in project control methodologies within the PSP materials.
Which letter of the alphabet best approximates the graphical shape of a project's cumulative cost baseline, or budgeted cost of work scheduled?
Answer(s): C
The cumulative cost baseline typically forms an "S" curve, reflecting slow initial expenditures, accelerating progress during peak activities, and tapering off as the project concludes.Option A, B, and D do not represent the characteristic shape of a project's cost curve.The PSP Study Guide highlights the "S" curve as a standard graphical representation of cumulative project costs over time.
Under which circumstance should one perform resource-leveling calculations?
Answer(s): B
Resource-leveling is used when resource constraints such as labor, materials, or equipment availability might prevent schedule logic from being followed.Option A references float-banking, unrelated to resource leveling.Option C suggests never performing leveling unless required, which overlooks the need to address actual resource limitations.Option D is incorrect as a resource-loaded schedule may still need leveling for optimization.Resource management principles in the PSP Study Guide discuss when and why to apply resource leveling.
Resource planning must take all of the following into account except for:
Resource planning focuses on identifying and allocating the required materials, equipment, labor, and financial resources.Option A, C, and D are integral to resource planning.Option B (earned value techniques) is a project control mechanism, not a resource planning factor.This is consistent with the scope of resource planning as described in the PSP Study Gu
When resource leveling craft labor for a critical path schedule, the scheduler
Resource Leveling:Resource leveling adjusts start and finish dates of activities to resolve resource conflicts or constraints, balancing availability and demand.In construction projects, breaks in continuity of work for subcontractors can result in increased costs due to remobilization and demobilization.PSP Study Guide Reference:The PSP guide explains that resource leveling must be carefully analyzed to avoid disruptions in work continuity.Conclusion: The correct answer is A, as the scheduler must account for potential cost implications of resource leveling on subcontractors.
Project delays are best analyzed
Delay Analysis:Analyzing delays contemporaneously ensures accurate understanding of their causes and effects, helping stakeholders mitigate impacts in real time.Waiting until after the project introduces risks of incomplete or inaccurate records.PSP Study Guide Reference:Contemporary delay analysis is highlighted as a best practice for effective delay resolution and management.Conclusion: The correct answer is B, as contemporaneous analysis is the most effective way to address project delays.
All the following describe the critical path of a schedule EXCEPT:
Critical Path Characteristics:The critical path is the longest path through the network, defining the minimum project completion time. It cannot be the shortest path.PSP Study Guide Reference:Critical path analysis emphasizes that it is determined by network logic and represents the chain of activities controlling the project duration.Analysis for Selection:Option A, C, and D: Accurately describe the critical path.Option B: Incorrect; the critical path is not the shortest path.Conclusion: The correct answer is B, as the critical path is the longest path, not the shortest.
In analyzing a logical chain of activities in a critical path method (CPM) schedule, what do differing total float values within that chain typically indicate?
Impact of Calendars on Total Float:Differing calendars (e.g., working days, holidays, or shifts) assigned to activities can result in varying total float values within a logical chain.Total float measures the flexibility of an activity and is calculated based on its calendar and logical dependencies.PSP Study Guide Reference:The guide covers how calendar assignments influence float calculations and their potential to create disparities in a critical path.Conclusion: The correct answer is B, as differing total float values typically indicate the use of different calendars for activities in the chain.
Share your comments for AACE International AACE-PSP exam with other users:
very helpful
good source
my 3rd test and passed on first try. hats off to this brain dumps site.
please upload it
does anybody know if are these real exam questions?
are these questions similar to actual questions in the exam? because they seem to be too easy
i have a lot of experience but what comes in the exam is totally different from the practical day to day tasks. so i thought i would rather rely on these brain dumps rather failing the exam.
good questions
valied exam dumps. they were very helpful and i got a pretty good score. i am very grateful for this service and exam questions
will it help?
very useful to verify knowledge before exam
good stuffs
question 17 : responses arent b and c ?
just passed the exam on my first try using these dumps.
these questions look good.
this is very helpful content
please provide the dumps
it is amazing
quesion 178 about "a banking system that predicts whether a loan will be repaid is an example of the" the answer is classification. not regresion, you should fix it.
please upload apache spark dumps
q14 is b&c to reduce you will switch off mail for every single alert and you will switch on daily digest to get a mail once per day, you might even skip the empty digest mail but i see this as a part of the daily digest adjustment
i think it is good question
good for students who wish to give certification.
is there a google drive link to the images? the links in questions are not working.
very promising, looks great, so much wow!
i scored 87% on the az-204 exam. thanks! i always trust
good need more
sample questions seems good
huawei is ok
good one nice
please continue
this exam dumps just did the job. i donot want to ruffle your feathers but your exam dumps and mock test engine is amazing.
nice questions