An earned value-based project control system can use either of which two budgets as the basis of its calculations?
Answer(s): A
An earned value management (EVM) system can base its calculations on labor hours or monetary values, depending on the nature of the project. Both methods are valid for tracking performance and forecasting outcomes.Option B (direct or indirect cost) does not align with EVM's focus on performance metrics.Option C confuses timeframes with budgeting principles.Option D (linear feet or dollars) applies to physical progress tracking but not directly to EVM systems.This is consistent with EVM principles as outlined in project control methodologies within the PSP materials.
Which letter of the alphabet best approximates the graphical shape of a project's cumulative cost baseline, or budgeted cost of work scheduled?
Answer(s): C
The cumulative cost baseline typically forms an "S" curve, reflecting slow initial expenditures, accelerating progress during peak activities, and tapering off as the project concludes.Option A, B, and D do not represent the characteristic shape of a project's cost curve.The PSP Study Guide highlights the "S" curve as a standard graphical representation of cumulative project costs over time.
Under which circumstance should one perform resource-leveling calculations?
Answer(s): B
Resource-leveling is used when resource constraints such as labor, materials, or equipment availability might prevent schedule logic from being followed.Option A references float-banking, unrelated to resource leveling.Option C suggests never performing leveling unless required, which overlooks the need to address actual resource limitations.Option D is incorrect as a resource-loaded schedule may still need leveling for optimization.Resource management principles in the PSP Study Guide discuss when and why to apply resource leveling.
Resource planning must take all of the following into account except for:
Resource planning focuses on identifying and allocating the required materials, equipment, labor, and financial resources.Option A, C, and D are integral to resource planning.Option B (earned value techniques) is a project control mechanism, not a resource planning factor.This is consistent with the scope of resource planning as described in the PSP Study Gu
When resource leveling craft labor for a critical path schedule, the scheduler
Resource Leveling:Resource leveling adjusts start and finish dates of activities to resolve resource conflicts or constraints, balancing availability and demand.In construction projects, breaks in continuity of work for subcontractors can result in increased costs due to remobilization and demobilization.PSP Study Guide Reference:The PSP guide explains that resource leveling must be carefully analyzed to avoid disruptions in work continuity.Conclusion: The correct answer is A, as the scheduler must account for potential cost implications of resource leveling on subcontractors.
Project delays are best analyzed
Delay Analysis:Analyzing delays contemporaneously ensures accurate understanding of their causes and effects, helping stakeholders mitigate impacts in real time.Waiting until after the project introduces risks of incomplete or inaccurate records.PSP Study Guide Reference:Contemporary delay analysis is highlighted as a best practice for effective delay resolution and management.Conclusion: The correct answer is B, as contemporaneous analysis is the most effective way to address project delays.
All the following describe the critical path of a schedule EXCEPT:
Critical Path Characteristics:The critical path is the longest path through the network, defining the minimum project completion time. It cannot be the shortest path.PSP Study Guide Reference:Critical path analysis emphasizes that it is determined by network logic and represents the chain of activities controlling the project duration.Analysis for Selection:Option A, C, and D: Accurately describe the critical path.Option B: Incorrect; the critical path is not the shortest path.Conclusion: The correct answer is B, as the critical path is the longest path, not the shortest.
In analyzing a logical chain of activities in a critical path method (CPM) schedule, what do differing total float values within that chain typically indicate?
Impact of Calendars on Total Float:Differing calendars (e.g., working days, holidays, or shifts) assigned to activities can result in varying total float values within a logical chain.Total float measures the flexibility of an activity and is calculated based on its calendar and logical dependencies.PSP Study Guide Reference:The guide covers how calendar assignments influence float calculations and their potential to create disparities in a critical path.Conclusion: The correct answer is B, as differing total float values typically indicate the use of different calendars for activities in the chain.
Share your comments for AACE International AACE-PSP exam with other users:
thank you for the test materials!
its very helpful
good questions
good questons
i need the dumb of the hcip security v4.0 exam
upload the dump please
yes, iam looking this
please upload cima e2 managing performance dumps
wonderful questions
i used this site since 2000, still great to support my career
why is the answer to "which of the following is required by scrum?" all of the following stated below since most of them are not mandatory? sprint retrospective. members must be stand up at the daily scrum. sprint burndown chart. release planning.
great job. hope this helps out.
upload please. many thanks!
this is so interesting
great material thanks
anyone who wrote this exam recently
ok they re good
relevant questions
please post
q:42 there has to be a image in the question to choose what does it mean from the options
looking for cphq dumps, where can i find these for free? please and thank you.
@aarun , thanks for the information. it would be great help if you share your email
1z0-1078-23 need this dumps
i gave the microsoft azure az-500 tests and prepared from this site as it has latest mock tests available which helped me evaluate my performance and score 919/1000
i cannot see the button to go to the questions
q-6 ans-b correct. https://docs.paloaltonetworks.com/pan-os/9-1/pan-os-cli-quick-start/use-the-cli/commit-configuration-changes
very nice very nice
please help us with 1z0-1107-2 dumps
please upload the practice questions
need this dumps
preparing for this exam is overwhelming. you cannot pass without the help of these exam dumps.
new to this site but i feel it is good
the correct answer to q8 is b. explanation since the mule app has a dependency, it is necessary to include project modules and dependencies to make sure the app will run successfully on the runtime on any other machine. source code of the component that the mule app is dependent of does not need to be included in the exported jar file, because the source code is not being used while executing an app. compiled code is being used instead.