AACE International AACE-PSP Exam (page: 3)
AACE International Planning & Scheduling Professional (PSP)
Updated on: 25-Dec-2025

Viewing Page 3 of 25

Time-scaled logic diagrams are

  1. Only calculated using a computer.
  2. The same as a pure-logic diagram.
  3. Used to calculate the most probable activity duration.
  4. Logic networks that are drawn to match the calendar.

Answer(s): C



Activity durations are normally estimated in an intuitive and subjective way. All of the following will improve duration accuracy EXCEPT

  1. Use gross building square footages. The pluses and minuses all average out.
  2. Look at each activity independently and don't follow specific logic paths when assigning activity durations.
  3. Divide activities into smaller activities. This will increase activity detail and duration estimate accuracy.
  4. Use the people responsible for performing the work as a resource to assign activity durations.

Answer(s): A



You are developing a detailed critical path schedule for a proposed petrochemical plant. The schedule will become a part of the project baseline document, which will be sent to the company's board of directors for its consideration.
What document or resource is likely to be MOST valuable in determining the schedule's work activity durations?

  1. Industry publications.
  2. Critical path schedules prepared by you for similar completed projects.
  3. The Petrochemical Industry New Plant Task Duration Handbook.
  4. The cost estimate for the plant prepared by your firm's estimating department.

Answer(s): B



Free float is the

  1. Difference between the early dates and late dates of an activity.
  2. Amount of time the early start of an activity can be delayed without impacting the early start of the successor activity.
  3. Difference between the early finish dates and late finish dates of an activity.
  4. Difference In float value of the critical path activities and the float value of the specific activity being analyzed.

Answer(s): B



What is a key first step in developing a critical path method schedule?

  1. Drawing a bar chart of the key phrases of the work.
  2. Defining the execution plan to meet the required scope of work.
  3. Setting out the resource to be used and its limitations.
  4. Drawing the logic diagram.

Answer(s): D



Viewing Page 3 of 25



Share your comments for AACE International AACE-PSP exam with other users:

Mchal 7/20/2023 3:38:00 AM

some questions are wrongly answered but its good nonetheless
POLAND


Sonbir 8/8/2023 1:04:00 PM

how to get system serial number using intune
Anonymous


Manju 10/19/2023 1:19:00 PM

is it really helpful to pass the exam
Anonymous


LeAnne Hair 8/24/2023 12:47:00 PM

#229 in incorrect - all the customers require an annual review
UNITED STATES


Abdul SK 9/28/2023 11:42:00 PM

kindy upload
Anonymous


Aderonke 10/23/2023 12:53:00 PM

fantastic assessment on psm 1
UNITED KINGDOM


SAJI 7/20/2023 2:51:00 AM

56 question correct answer a,b
Anonymous


Raj Kumar 10/23/2023 8:52:00 PM

thank you for providing the q bank
CANADA


piyush keshari 7/7/2023 9:46:00 PM

true quesstions
Anonymous


B.A.J 11/6/2023 7:01:00 AM

i can´t believe ms asks things like this, seems to be only marketing material.
Anonymous


Guss 5/23/2023 12:28:00 PM

hi, could you please add the last update of ns0-527
Anonymous


Rond65 8/22/2023 4:39:00 PM

question #3 refers to vnet4 and vnet5. however, there is no vnet5 listed in the case study (testlet 2).
UNITED STATES


Cheers 12/13/2023 9:55:00 AM

sometimes it may be good some times it may be
GERMANY


Sumita Bose 7/21/2023 1:01:00 AM

qs 4 answer seems wrong- please check
AUSTRALIA


Amit 9/7/2023 12:53:00 AM

very detailed explanation !
HONG KONG


FisherGirl 5/16/2022 10:36:00 PM

the interactive nature of the test engine application makes the preparation process less boring.
NETHERLANDS


Chiranthaka 9/20/2023 11:15:00 AM

very useful.
Anonymous


SK 7/15/2023 3:51:00 AM

complete question dump should be made available for practice.
Anonymous


Gamerrr420 5/25/2022 9:38:00 PM

i just passed my first exam. i got 2 exam dumps as part of the 50% sale. my second exam is under work. once i write that exam i report my result. but so far i am confident.
AUSTRALIA


Kudu hgeur 9/21/2023 5:58:00 PM

nice create dewey stefen
CZECH REPUBLIC


Anorag 9/6/2023 9:24:00 AM

i just wrote this exam and it is still valid. the questions are exactly the same but there are about 4 or 5 questions that are answered incorrectly. so watch out for those. best of luck with your exam.
CANADA


Nathan 1/10/2023 3:54:00 PM

passed my exam today. this is a good start to 2023.
UNITED STATES


1 10/28/2023 7:32:00 AM

great sharing
Anonymous


Anand 1/20/2024 10:36:00 AM

very helpful
UNITED STATES


Kumar 6/23/2023 1:07:00 PM

thanks.. very helpful
FRANCE


User random 11/15/2023 3:01:00 AM

i registered for 1z0-1047-23 but dumps qre available for 1z0-1047-22. help me with this...
UNITED STATES


kk 1/17/2024 3:00:00 PM

very helpful
UNITED STATES


Raj 7/24/2023 10:20:00 AM

please upload oracle 1z0-1110-22 exam pdf
INDIA


Blessious Phiri 8/13/2023 11:58:00 AM

becoming interesting on the logical part of the cdbs and pdbs
Anonymous


LOL what a joke 9/10/2023 9:09:00 AM

some of the answers are incorrect, i would be wary of using this until an admin goes back and reviews all the answers
UNITED STATES


Muhammad Rawish Siddiqui 12/9/2023 7:40:00 AM

question # 267: federated operating model is also correct.
SAUDI ARABIA


Mayar 9/22/2023 4:58:00 AM

its helpful alot.
Anonymous


Sandeep 7/25/2022 11:58:00 PM

the questiosn from this braindumps are same as in the real exam. my passing mark was 84%.
INDIA


Eman Sawalha 6/10/2023 6:09:00 AM

it is an exam that measures your understanding of cloud computing resources provided by aws. these resources are aligned under 6 categories: storage, compute, database, infrastructure, pricing and network. with all of the services and typees of services under each category
GREECE