Each of the following accurately describes total float in a schedule EXCEPT:
Answer(s): C
Total float measures the flexibility in an activity’s timing within a schedule. It is defined as the amount of time an activity can be delayed without affecting the project’s overall completion date or the completion date of any of its successors.Option A, B, and D accurately describe total float: it is calculated as the difference between early and late start/finish dates, can be positive or negative, and is associated with project completion.Option C describes free float, not total float, and thus is incorrect.
The amount of time that an activity can be delayed from its early start date without delaying project completion is called:
The time an activity can be delayed from its early start without impacting the overall project completion date is called total float.Option A (negative float) refers to delays beyond permissible limits.Option B (free float) refers to delays without affecting the early start of any successor.Option D (interfering float) is a lesser-used term denoting the time available without delaying the project completion but affecting a successor’s float.
In its simplest form, what is the main drawback of critical path method scheduling?
Answer(s): B
A fundamental limitation of Critical Path Method (CPM) scheduling is its assumption of unlimited resources, meaning it does not account for resource constraints when calculating schedules.Option A (backward pass) is a standard part of the CPM process.Option C is incorrect as CPM considers activity dependencies.Option D refers to flexibility in diagramming methods, not a drawback.The PSP Study Guide highlights resource constraints as a significant challenge in CPM application.
If after calculating a schedule an activity exhibits negative total float, which of the following is certain? The activity
Answer(s): D
Negative total float occurs when an activity’s scheduled completion date extends beyond the project deadline due to constraints. This condition indicates that the activity is still pending and needs immediate attention to avoid further delays.Option A (milestone) is unrelated.Option B (critical path) is not necessarily true, as activities with negative float can exist off the critical path under certain constraints.Option C (completed in the past) is incorrect as negative float applies only to future or ongoing activities.
Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?
Total float is influenced by factors like multiple calendars, start/finish constraints, and preferential logic because these directly affect the calculation of early and late dates.Option D (front end loading), which involves distributing work to earlier project phases, does not inherently affect float calculations as it primarily pertains to resource or phase management strategies.
You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay.Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?
As-Planned vs. As-Built (APAB) Analysis:A simple APAB compares the planned schedule to the actual schedule to identify deviations.It does not involve inserting delaying events or re-forecasting the schedule, which makes it unsuitable for detailed analysis.Limitations of APAB:Unsuitable for complex projects (A).Inserting delays is not part of APAB (B).Accuracy diminishes for long projects (C) or those requiring granular mid-project analyses (D).Conclusion: The correct answer is B, as inserting delays into the as-planned schedule is not a feature of simple APAB analysis.
Which statement is true?
Compensability and Excusability:Excusable delays are those beyond the contractor’s control, while compensable delays are excusable delays for which the owner bears responsibility.If a delay is compensable, it inherently qualifies as excusable.PSP Study Guide Reference:The relationship between excusability and compensability is clarified in delay analysis discussions.Conclusion: The correct answer is D, as compensability implies excusability.
Which of the following phases does NOT describe the commonly accepted construction life cycle?
Answer(s): A
Construction Life Cycle Phases:Common phases: planning and design, installation (execution), and turnover/start-up.Claims and disputes may arise during the project but are not a defined phase of the construction life cycle.PSP Study Guide Reference:The study guide outlines standard phases without including claims and disputes as a formal phase.Conclusion: The correct answer is A, as claims and disputes are not an inherent phase of the construction life cycle.
Share your comments for AACE International AACE-PSP exam with other users:
thanks for providing these questions
interesting
these dumps are pretty good.
good questions
dbua is used for upgrading oracle database
i am thrilled to say that i passed my amazon web services mls-c01 exam, thanks to study materials. they were comprehensive and well-structured, making my preparation efficient.
please upload latest ibm ace c1000-056 dumps
if only explanations were provided...
yes .. i need the dump if you can help me
good morning, could you please upload this exam again?
hi please upload sre foundation and practitioner exam questions
the exam is listed as 80 questions with a pass mark of 70%, how is your 50 questions related?
all questions are so important and covers all ccna modules
q 44. ans:- b (goto setup > order settings > select enable optional price books for orders) reference link --> https://resources.docs.salesforce.com/latest/latest/en-us/sfdc/pdf/sfom_impl_b2b_b2b2c.pdf(decide whether you want to enable the optional price books feature. if so, select enable optional price books for orders. you can use orders in salesforce while managing price books in an external platform. if you’re using d2c commerce, you must select enable optional price books for orders.)
"cost of replacing data if it were lost" is also correct.
pls upload the questions
question 182 - correct answer is d. ethernet frame length is 64 - 1518b. length of user data containing is that frame: 46 - 1500b.
i need this exam pls
its required for me, please make it enable to access. thanks
seems good..
took the test last week, i did have about 15 - 20 word for word from this site on the test. (only was able to cram 600 of the questions from this site so maybe more were there i didnt review) had 4 labs, bgp, lacp, vrf with tunnels and actually had to skip a lab due to time. lots of automation syntax questions.
no comments
nice questions bring out the best in you.
really helpful
question #50 and question #81 are exactly the same questions, azure site recovery provides________for virtual machines. the first says that it is fault tolerance is the answer and second says disater recovery. from my research, it says it should be disaster recovery. can anybody explain to me why? thank you
iam thankful for these exam dumps questions, i would not have passed without this exam dumps.
some of the answers seem to be inaccurate. q10 for example shouldnt it be an m custom column?
are the question real or fake?
thank you for providing such assistance.
nice questions
my 3rd purcahse from this site. these exam dumps are helpful. very helpful.
found it good
excellent material
Keeping this site free takes real effort. We constantly battle automated scraping and unauthorized content copying. A quick account helps us protect the community and keep the site free.
To continue studying for your AACE-PSP, please sign in or create a free account.