Which process is triggered towards the end of the final stage when all the assigned work has been completed?

  1. Managing a Stage Boundary
  2. Managing Product Delivery
  3. Closing a Project
  4. Controlling a Stage

Answer(s): C

Explanation:

The Closing a Project process in PRINCE2 is triggered towards the end of the final stage when all assigned work has been completed. This process is designed to ensure that all project objectives have been achieved, all products have been delivered, and the project can be formally closed and evaluated for success and areas of improvement.


Reference:

PRINCE2 Foundation manual, PRINCE2 official resources



Which is a purpose of the Controlling a Stage process?

  1. Assign work to be done and take corrective action to ensure that the stage remains within tolerance
  2. Provide a fixed reference point at which acceptance for the project product is confirmed
  3. Enable the Project Board to be provided with sufficient information to authorize the next stage
  4. Enable the organization to understand the work that needs to be done to deliver the project's products

Answer(s): A

Explanation:

The purpose of the Controlling a Stage process in PRINCE2® is to monitor and control a stage within its authorized tolerances. During this process, the Project Manager assigns work, monitors work progress, deals with issues, reports stage status to the Project Board, and takes necessary corrective actions to stay within the stage's tolerances.


Reference:

PRINCE2® Foundation official documentation and study materials.



What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?

  1. Directing a Project
  2. Controlling a Stage
  3. Managing a Stage Boundary
  4. Managing Product Delivery

Answer(s): B

Explanation:

The Controlling a Stage process is used by the Project Manager to maintain focus on the delivery of the stage's products within the agreed tolerances. This involves assigning work, monitoring such work, managing issues and risks, and ensuring that the stage remains on track in terms of time, cost, quality, scope, risk, and benefit performance.


Reference:

PRINCE2® Foundation official documentation and study materials.



In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?

  1. Product Description
  2. Team Plan
  3. Work Package
  4. Stage Plan

Answer(s): C

Explanation:

In PRINCE2®, a Work Package is the document where the Project Manager defines the time and cost tolerances for the work assigned to a Team Manager. The Work Package provides detailed information on the products to be delivered, the reporting requirements, and the tolerances within which the Team Manager operates.


Reference:

PRINCE2® Foundation official documentation and study materials.



Which is a purpose of the Directing a Project process?

  1. Create and authorize the project mandate
  2. Ensure that work on products allocated to the team is authorized and agreed
  3. Control the day-to-day running of the project
  4. Delegate day-to-day management of the project to the Project Manager

Answer(s): D

Explanation:

The purpose of the Directing a Project process is for the Project Board to delegate the day-to-day management of the project to the Project Manager, providing the overall direction and management of the project lifecycle. This process is critical for enabling the Project Manager to run the project on behalf of the Project Board within the constraints set out by them.


Reference:

PRINCE2® Foundation official documentation and study materials.



Viewing Page 6 of 94



Share your comments for PRINCE2 PRINCE2 Foundation exam with other users:

PAYAL 10/17/2023 7:14:00 AM

17 should be d ,for morequery its scale out
Anonymous


Karthik 10/12/2023 10:51:00 AM

nice question
Anonymous


Godmode 5/7/2023 10:52:00 AM

yes.
NETHERLANDS


Bhuddhiman 7/30/2023 1:18:00 AM

good mateial
Anonymous


KJ 11/17/2023 3:50:00 PM

good practice exam
Anonymous


sowm 10/29/2023 2:44:00 PM

impressivre qustion
Anonymous


CW 7/6/2023 7:06:00 PM

questions seem helpful
Anonymous


luke 9/26/2023 10:52:00 AM

good content
Anonymous


zazza 6/16/2023 9:08:00 AM

question 21 answer is alerts
ITALY


Abwoch Peter 7/4/2023 3:08:00 AM

am preparing for exam
Anonymous


mohamed 9/12/2023 5:26:00 AM

good one thanks
EGYPT


Mfc 10/23/2023 3:35:00 PM

only got thru 5 questions, need more to evaluate
Anonymous


Whizzle 7/24/2023 6:19:00 AM

q26 should be b
Anonymous


sarra 1/17/2024 3:44:00 AM

the aaa triad in information security is authentication, accounting and authorisation so the answer should be d 1, 3 and 5.
UNITED KINGDOM


DBS 5/14/2023 12:56:00 PM

need to attend this
UNITED STATES


Da_costa 8/1/2023 5:28:00 PM

these are free brain dumps i understand, how can one get free pdf
Anonymous


vikas 10/28/2023 6:57:00 AM

provide access
EUROPEAN UNION


Abdullah 9/29/2023 2:06:00 AM

good morning
Anonymous


Raj 6/26/2023 3:12:00 PM

please upload the ncp-mci 6.5 dumps, really need to practice this one. thanks guys
Anonymous


Miguel 10/5/2023 12:21:00 PM

question 16: https://help.salesforce.com/s/articleview?id=sf.care_console_overview.htm&type=5
SPAIN


Hiren Ladva 7/8/2023 10:34:00 PM

yes i m prepared exam
Anonymous


oliverjames 10/24/2023 5:37:00 AM

my experience was great with this site as i studied for the ms-900 from here and got 900/1000 on the test. my main focus was on the tutorials which were provided and practice questions. thanks!
GERMANY


Bhuddhiman 7/20/2023 11:52:00 AM

great course
UNITED STATES


Anuj 1/14/2024 4:07:00 PM

very good question
Anonymous


Saravana Kumar TS 12/8/2023 9:49:00 AM

question: 93 which statement is true regarding the result? sales contain 6 columns and values contain 7 columns so c is not right answer.
INDIA


Lue 3/30/2023 11:43:00 PM

highly recommend just passed my exam.
CANADA


DC 1/7/2024 10:17:00 AM

great practice! thanks
UNITED STATES


Anonymus 11/9/2023 5:41:00 AM

anyone who wrote this exam recently?
SOUTH AFRICA


Khalid Javid 11/17/2023 3:46:00 PM

kindly share the dump
Anonymous


Na 8/9/2023 8:39:00 AM

could you please upload cfe fraud prevention and deterrence questions? it will be very much helpful.
Anonymous


shime 10/23/2023 10:03:00 AM

this is really very very helpful for mcd level 1
ETHIOPIA


Vnu 6/3/2023 2:39:00 AM

very helpful!
Anonymous


Steve 8/17/2023 2:19:00 PM

question #18s answer should be a, not d. this should be corrected. it should be minvalidityperiod
CANADA


RITEISH 12/24/2023 4:33:00 AM

thanks for the exact solution
Anonymous