Which step in the issue and change control procedure considers alternative options for responding to an issue that is being managed formally?

  1. Capture
  2. Examine
  3. Propose
  4. Decide

Answer(s): B

Explanation:

In the issue and change control procedure within PRINCE2, the "Examine" step involves considering alternative options to address an issue that is being managed formally. This step is crucial for evaluating the possible responses to an issue before making a decision on the best course of action.


Reference:

PRINCE2 Foundation manual, PRINCE2 official resources



A product can NOT be supplied to meet all of the requirements in its baselined Product Description.
What first action should be taken?

  1. Raise a request for change
  2. Raise an off-specification
  3. Write an Exception Report
  4. Amend the Work Package

Answer(s): B

Explanation:

When a product cannot meet all the requirements specified in its baselined Product Description, the first action to take is to raise an off-specification. An off-specification is used in PRINCE2 to formally identify any forecasted deviation from the agreed product requirements or quality expectations.


Reference:

PRINCE2 Foundation manual, PRINCE2 official resources



Which of the following statements about the Closing a Project process are true?

1. The Closing a Project process provides a fixed point for the receipt of completed Work Packages for the work performed in the final stage.

2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved.

  1. Only 1 is true
  2. Only 2 is true
  3. Both 1 and 2 are true
  4. Neither 1 or 2 are true

Answer(s): B

Explanation:

The statement that "The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved" is true. This process is crucial for ensuring that the project has met its objectives and that all remaining project deliverables are acceptable to stakeholders. The first statement is incorrect as the receipt of completed Work Packages is typically handled during the 'Managing a Stage Boundary' process rather than in the 'Closing a Project' process.


Reference:

PRINCE2 Foundation manual, PRINCE2 official resources



What takes place during the Closing a Project process?

  1. The post-project benefits reviews are performed
  2. Ownership of the project's products is transferred to the customer
  3. An End Stage Report is prepared for the final stage
  4. The project closure notification is reviewed and approved

Answer(s): B

Explanation:

During the Closing a Project process in PRINCE2®, the ownership of the project's products is formally transferred to the customer, ensuring that all deliverables have been accepted and are ready for operational use. This transfer marks the formal completion of the project.


Reference:

PRINCE2® Foundation official study guide and materials.



Which is an objective of the Closing a Project process?

  1. Prepare the plan for the next stage
  2. Assess any benefits that have already been realized
  3. Produce a Benefits Review Plan to identify what benefits are expected
  4. Check that all benefits are realized before closing a project

Answer(s): C

Explanation:

One of the objectives of the Closing a Project process is to produce a Benefits Review Plan. This plan outlines how the benefits of the project will be measured and reviewed after the project has been closed. It is crucial for ensuring that the benefits expected from the project are tracked and assessed in the post-project phase.


Reference:

PRINCE2® Foundation official study guide and materials.



Viewing Page 4 of 94



Share your comments for PRINCE2 PRINCE2 Foundation exam with other users:

Andy 12/26/2023 9:35:00 PM

plan to take theaws certified developer - associate dva-c02 in the next few weeks
SINGAPORE


siva 5/17/2023 12:32:00 AM

very helpfull
Anonymous


mouna 9/27/2023 8:53:00 AM

good questions
Anonymous


Bhavya 9/12/2023 7:18:00 AM

help to practice csa exam
Anonymous


Malik 9/28/2023 1:09:00 PM

nice tip and well documented
Anonymous


rodrigo 6/22/2023 7:55:00 AM

i need the exam
Anonymous


Dan 6/29/2023 1:53:00 PM

please upload
Anonymous


Ale M 11/22/2023 6:38:00 PM

prepping for fsc exam
AUSTRALIA


ahmad hassan 9/6/2023 3:26:00 AM

pd1 with great experience
Anonymous


Žarko 9/5/2023 3:35:00 AM

@t it seems like azure service bus message quesues could be the best solution
UNITED KINGDOM


Shiji 10/15/2023 1:08:00 PM

helpful to check your understanding.
INDIA


Da Costa 8/27/2023 11:43:00 AM

question 128 the answer should be static not auto
Anonymous


bot 7/26/2023 6:45:00 PM

more comments here
UNITED STATES


Kaleemullah 12/31/2023 1:35:00 AM

great support to appear for exams
Anonymous


Bsmaind 8/20/2023 9:26:00 AM

useful dumps
Anonymous


Blessious Phiri 8/13/2023 8:37:00 AM

making progress
Anonymous


Nabla 9/17/2023 10:20:00 AM

q31 answer should be d i think
FRANCE


vladputin 7/20/2023 5:00:00 AM

is this real?
UNITED STATES


Nick W 9/29/2023 7:32:00 AM

q10: c and f are also true. q11: this is outdated. you no longer need ownership on a pipe to operate it
Anonymous


Naveed 8/28/2023 2:48:00 AM

good questions with simple explanation
UNITED STATES


cert 9/24/2023 4:53:00 PM

admin guide (windows) respond to malicious causality chains. when the cortex xdr agent identifies a remote network connection that attempts to perform malicious activity—such as encrypting endpoint files—the agent can automatically block the ip address to close all existing communication and block new connections from this ip address to the endpoint. when cortex xdrblocks an ip address per endpoint, that address remains blocked throughout all agent profiles and policies, including any host-firewall policy rules. you can view the list of all blocked ip addresses per endpoint from the action center, as well as unblock them to re-enable communication as appropriate. this module is supported with cortex xdr agent 7.3.0 and later. select the action mode to take when the cortex xdr agent detects remote malicious causality chains: enabled (default)—terminate connection and block ip address of the remote connection. disabled—do not block remote ip addresses. to allow specific and known s
Anonymous


Yves 8/29/2023 8:46:00 PM

very inciting
Anonymous


Miguel 10/16/2023 11:18:00 AM

question 5, it seems a instead of d, because: - care plan = case - patient = person account - product = product2;
SPAIN


Byset 9/25/2023 12:49:00 AM

it look like real one
Anonymous


Debabrata Das 8/28/2023 8:42:00 AM

i am taking oracle fcc certification test next two days, pls share question dumps
Anonymous


nITA KALE 8/22/2023 1:57:00 AM

i need dumps
Anonymous


CV 9/9/2023 1:54:00 PM

its time to comptia sec+
GREECE


SkepticReader 8/1/2023 8:51:00 AM

question 35 has an answer for a different question. i believe the answer is "a" because it shut off the firewall. "0" in registry data means that its false (aka off).
UNITED STATES


Nabin 10/16/2023 4:58:00 AM

helpful content
MALAYSIA


Blessious Phiri 8/15/2023 3:19:00 PM

oracle 19c is complex db
Anonymous


Sreenivas 10/24/2023 12:59:00 AM

helpful for practice
Anonymous


Liz 9/11/2022 11:27:00 PM

support team is fast and deeply knowledgeable. i appreciate that a lot.
UNITED STATES


Namrata 7/15/2023 2:22:00 AM

helpful questions
Anonymous


lipsa 11/8/2023 12:54:00 PM

thanks for question
Anonymous