When prioritizing features to be delivered in an iteration, on what should an agile team defer work?

  1. High-risk and high-value
  2. High-risk and low-value
  3. Low-risk and low-value
  4. Low-risk and high value

Answer(s): C



On an agile project, some of the development team is struggling to understand how the tasks and user stories fit into the overall product.
How should this be addressed?

  1. Review the iteration goals and have the team each describe the work to create shared understanding
  2. Create a story map for the minimal viable product (MVP) functionality
  3. Capture this as a task in the retrospective and ensure there is more details provided at the next planning session
  4. Have the product owner explain the product vision and review the release plan with the team

Answer(s): D



The customer needs assistance in determining the efficiency of a set of process activities within the solution.
What should the agile team do?

  1. Discuss the efficiency at the next iteration retrospective
  2. Review the process value stream to determine potential improvements
  3. Review the value the customer receives from the user story to determine backlog priority
  4. Discuss the performance of the solution at the next sprint review

Answer(s): B



A new agile project manager accepts an assignment to manage a well-established team. Many team members have worked together on this product for several years. During a meeting, the project manager notices that team members offer little vocal interaction, yet all required tasks are completed on time.
What type of behaviour does this describe?

  1. Synchronous
  2. Collaborative
  3. Passive-aggressive
  4. Random

Answer(s): B



Following a successful product release, senior management asks an agile team how to improve the value of the product for the next release.
What should the team do?

  1. Conduct frequent demos and obtain feedback from users throughout the development of the next release
  2. Inform senior management that since the product was successfully released, the project is considered delivered and should be closed
  3. Request additional budget to implement a Scrum of Scrums approach to scale the teams and add capacity
  4. Implement a better definition of done to ensure that continuous integration processes are managed effectively

Answer(s): A



Viewing Page 7 of 66



Share your comments for PMI PMI-ACP exam with other users:

Lingaraj 10/26/2023 1:27:00 AM

i love this thank you i need
Anonymous


Muhammad Rawish Siddiqui 12/5/2023 12:38:00 PM

question # 142: data governance is not one of the deliverables in the document and content management context diagram.
SAUDI ARABIA


al 6/7/2023 10:25:00 AM

most answers not correct here
Anonymous


Bano 1/19/2024 2:29:00 AM

what % of questions do we get in the real exam?
UNITED STATES


Oliviajames 10/25/2023 5:31:00 AM

i just want to tell you. i took my microsoft az-104 exam and passed it. your program was awesome. i especially liked your detailed questions and answers and practice tests that made me well-prepared for the exam. thanks to this website!!!
UNITED STATES


Divya 8/27/2023 12:31:00 PM

all the best
UNITED STATES


KY 1/1/2024 11:01:00 PM

very usefull document
Anonymous


Arun 9/20/2023 4:52:00 PM

nice and helpful questions
INDIA


Joseph J 7/11/2023 2:53:00 PM

i found the questions helpful
UNITED STATES


Meg 10/12/2023 8:02:00 AM

q 105 . ans is d
INDIA


Navaneeth S 7/14/2023 7:57:00 AM

i have interest to get a sybase iq dba certification
UNITED STATES


Aish 10/11/2023 5:27:00 AM

want to pass exm.
INDIA


Anonymous 6/12/2023 7:23:00 AM

are the answers correct?
INDIA


Kris 7/7/2023 9:43:00 AM

good morning, could you please upload this exam again, i need it to test my knowledge in sd-wan with version 7.0.
Anonymous


Meghraj mali 10/7/2023 1:47:00 PM

very nice question
CANADA


Noel 11/1/2022 9:14:00 PM

i have learning disability and this exam dumps allowed me to focus on the actual questions and not worry about notes and the those other study materials.
SOUTH AFRICA


Jas 10/25/2023 6:01:00 PM

165 should be apt
UNITED STATES


Neetu 6/22/2023 8:41:00 AM

please upload the dumps, real need of them
Anonymous


Mark 10/24/2023 1:34:00 AM

any recent feeedback?
UNITED STATES


Gopinadh 8/9/2023 4:05:00 AM

question number 2 is indicating you are giving proper questions. observe and change properly.
Anonymous


Santhi 1/1/2024 8:23:00 AM

passed today.40% questions were new.litwere case study,lots of new questions on afd,ratelimit,tm,lb,app gatway.got 2 set series of questions which are not present here.questions on azure cyclecloud, no.of vnet/vms required for implimentation,blueprints assignment/management group etc
INDIA


Raviraj Magadum 1/12/2024 11:39:00 AM

practice test
INDIA


sivaramakrishnan 7/27/2023 8:12:00 AM

want the dumps for emc content management server programming(cmsp)
Anonymous


Aderonke 10/23/2023 1:52:00 PM

brilliant and helpful
UNITED KINGDOM


Az 9/16/2023 2:43:00 PM

q75. azure files is pass
SWITZERLAND


ketty 11/9/2023 8:10:00 AM

very helpful
Anonymous


Sonail 5/2/2022 1:36:00 PM

thank you for these questions. it helped a lot.
UNITED STATES


Shariq 7/28/2023 8:00:00 AM

how do i get the h12-724 dumps
Anonymous


adi 10/30/2023 11:51:00 PM

nice data dumps
Anonymous


EDITH NCUBE 7/25/2023 7:28:00 AM

answers are correct
SOUTH AFRICA


Raja 6/20/2023 4:38:00 AM

good explanation
UNITED STATES


BigMouthDog 1/22/2022 8:17:00 PM

hi team just want to know if there is any update version of the exam 350-401
AUSTRALIA


francesco 10/30/2023 11:08:00 AM

helpful on 2017 scrum guide
EUROPEAN UNION


Amitabha Roy 10/5/2023 3:16:00 AM

planning to attempt for the exam.
Anonymous