PMI Agile Certified Practitioner PMI-ACP Exam Questions in PDF

Free PMI PMI-ACP Dumps Questions (page: 1)

A newly formed development team experienced difficulty with accurately estimating product backlog items. As a result, the team failed to deliver all of the features in the sprint backlog for the past two iterations.
What should the team do to improve the accuracy of their estimates?

  1. Decrease the sprint time box until the team is able to deliver the entire agreed-upon sprint backlog in a single sprint
  2. Discuss estimating techniques in the daily scrum meeting
  3. Increase the size of the development team until the team is able to deliver the entire agreed-upon sprint backlog in a single sprint
  4. Begin tracking estimated effort metrics as an input to performance evaluation

Answer(s): D



Midway through a sprint, the scrum master identifies that reassigning a certain task could help the team meet its sprint's goals.
What should the scrum master do next?

  1. Alert the team that sprint goals might not be met and create an alternative plan
  2. Obtain team buy-in to perform modifications to the sprint backlog
  3. Have the sprint proceed as planned
  4. Ask the team to decide if the task should be reassigned

Answer(s): D



During the iteration planning of a newly on boarded agile team, the product owner adds a set of high priority user stories into the iteration backlog.
What should the team do first to define the tasks need to implement the user stories?

  1. Self-organize
  2. Assign tasks to each team member
  3. Meet with the customer
  4. Identify the scrum master

Answer(s): A



A project's first iteration contains item A, and its second iteration contains item B. The first iteration is behind schedule, which will impact the second iteration.
Since items A and B are similar, a team member suggests beginning the design of item B.
What should the agile practitioner do?

  1. Defer starting the design of item B until the second iteration is being planned
  2. Proceed with the design of item B, since it will hasten the second iteration
  3. Escalate the issue to the customer, and obtain their approval before starting the design of item B
  4. Log the issue in the risk register, and request change control board (CCB) approval.

Answer(s): A



An Agile team is under pressure to deliver an application. The product owner anticipates many change requests from customers once the product is released.
What should the agile team do?

  1. Demand frequent product reviews by the product owner
  2. Continuously work with the product owner to do backlog refinement and product reviews
  3. Have the product owner provide detailed requirement specifications to ensure the proper features are delivered
  4. During the planning session, ensure the team is committed to deliver within the specifications

Answer(s): B



Share your comments for PMI PMI-ACP exam with other users:

A
Abdullah
9/29/2023 2:06:00 AM

good morning

R
Raj
6/26/2023 3:12:00 PM

please upload the ncp-mci 6.5 dumps, really need to practice this one. thanks guys

M
Miguel
10/5/2023 12:21:00 PM

question 16: https://help.salesforce.com/s/articleview?id=sf.care_console_overview.htm&type=5

H
Hiren Ladva
7/8/2023 10:34:00 PM

yes i m prepared exam

O
oliverjames
10/24/2023 5:37:00 AM

my experience was great with this site as i studied for the ms-900 from here and got 900/1000 on the test. my main focus was on the tutorials which were provided and practice questions. thanks!

B
Bhuddhiman
7/20/2023 11:52:00 AM

great course

A
Anuj
1/14/2024 4:07:00 PM

very good question

S
Saravana Kumar TS
12/8/2023 9:49:00 AM

question: 93 which statement is true regarding the result? sales contain 6 columns and values contain 7 columns so c is not right answer.

L
Lue
3/30/2023 11:43:00 PM

highly recommend just passed my exam.

D
DC
1/7/2024 10:17:00 AM

great practice! thanks

A
Anonymus
11/9/2023 5:41:00 AM

anyone who wrote this exam recently?

K
Khalid Javid
11/17/2023 3:46:00 PM

kindly share the dump

N
Na
8/9/2023 8:39:00 AM

could you please upload cfe fraud prevention and deterrence questions? it will be very much helpful.

S
shime
10/23/2023 10:03:00 AM

this is really very very helpful for mcd level 1

V
Vnu
6/3/2023 2:39:00 AM

very helpful!

S
Steve
8/17/2023 2:19:00 PM

question #18s answer should be a, not d. this should be corrected. it should be minvalidityperiod

R
RITEISH
12/24/2023 4:33:00 AM

thanks for the exact solution

S
SB
10/15/2023 7:58:00 AM

need to refer the questions and have to give the exam

M
Mike Derfalem
7/16/2023 7:59:00 PM

i need it right now if it was possible please

I
Isak
7/6/2023 3:21:00 AM

i need it very much please share it in the fastest time.

M
Maria
6/23/2023 11:40:00 AM

correct answer is d for student.java program

N
Nagendra Pedipina
7/12/2023 9:10:00 AM

q:37 c is correct

J
John
9/16/2023 9:37:00 PM

q6 exam topic: terramearth, c: correct answer: copy 1petabyte to encrypted usb device ???

S
SAM
12/4/2023 12:56:00 AM

explained answers

A
Andy
12/26/2023 9:35:00 PM

plan to take theaws certified developer - associate dva-c02 in the next few weeks

S
siva
5/17/2023 12:32:00 AM

very helpfull

M
mouna
9/27/2023 8:53:00 AM

good questions

B
Bhavya
9/12/2023 7:18:00 AM

help to practice csa exam

M
Malik
9/28/2023 1:09:00 PM

nice tip and well documented

R
rodrigo
6/22/2023 7:55:00 AM

i need the exam

D
Dan
6/29/2023 1:53:00 PM

please upload

A
Ale M
11/22/2023 6:38:00 PM

prepping for fsc exam

A
ahmad hassan
9/6/2023 3:26:00 AM

pd1 with great experience

Ž
Žarko
9/5/2023 3:35:00 AM

@t it seems like azure service bus message quesues could be the best solution

AI Tutor 👋 I’m here to help!