A project's first iteration contains item A, and its second iteration contains item B. The first iteration is behind schedule, which will impact the second iteration.
Since items A and B are similar, a team member suggests beginning the design of item B.
What should the agile practitioner do?
- Defer starting the design of item B until the second iteration is being planned
- Proceed with the design of item B, since it will hasten the second iteration
- Escalate the issue to the customer, and obtain their approval before starting the design of item B
- Log the issue in the risk register, and request change control board (CCB) approval.