A new team member asks what changes could accelerate a change to the project plan.
What should be the proper response?

  1. Competitors joined forces with the team
  2. The customer changed requirements
  3. Project team members obtained additional certifications
  4. Technology which did not interfere with the final product

Answer(s): B



Midway through an iteration, an agile team learns that a team member will be unavailable for the next two iterations.
As a high-performance team, what should the team do?

  1. Raise an impediment that resource tasks will be blocked and notify the product owner
  2. Ask the delivery manager for a temporary resource
  3. Ask the scrum master to assign that team member's tasks to the next available resource
  4. Assume the team member's tasks to meet iteration goals, and notify the product owner

Answer(s): D



An agile practitioner wants to ensure that stakeholders have current information about a project's progress.
What should the agile practitioner do?

  1. Regularly circulate an updated, detailed version of the project plan
  2. Frequently update the online project management office (PMO) repository site
  3. Invite the stakeholders to daily stand ups
  4. Post a project board in an area where all can view it

Answer(s): D



A company has decided to combine two similar products consisting of multiple teams into one product. Engaged customers want to know how the company is looking at re-organizing its teams.
What strategy should be employed to re-organize the teams?

  1. All the teams from both products should be simultaneously called together and allowed to completely self-manage
  2. Teams that worked on similar components in the separate products should be combined to minimize disruption and capitalize on synergies
  3. After grouping individuals by role, multi-discipline teams should be created that are comprised of one member from each role
  4. Features should be prioritized and then teams should be organized around those priorities

Answer(s): A



A client states that a product is not being built as requested.
How should the agile team address this?

  1. Conduct an internal review to validate functionality before shipping
  2. Audit the quality control process to ensure that the product adheres to requirements
  3. Lengthen iterations to ensure there is sufficient time to build functionality
  4. Hold product review sessions with the client to obtain product acceptance

Answer(s): D



Viewing Page 3 of 66



Share your comments for PMI PMI-ACP exam with other users:

Divya 8/27/2023 12:31:00 PM

all the best
UNITED STATES


KY 1/1/2024 11:01:00 PM

very usefull document
Anonymous


Arun 9/20/2023 4:52:00 PM

nice and helpful questions
INDIA


Joseph J 7/11/2023 2:53:00 PM

i found the questions helpful
UNITED STATES


Meg 10/12/2023 8:02:00 AM

q 105 . ans is d
INDIA


Navaneeth S 7/14/2023 7:57:00 AM

i have interest to get a sybase iq dba certification
UNITED STATES


Aish 10/11/2023 5:27:00 AM

want to pass exm.
INDIA


Anonymous 6/12/2023 7:23:00 AM

are the answers correct?
INDIA


Kris 7/7/2023 9:43:00 AM

good morning, could you please upload this exam again, i need it to test my knowledge in sd-wan with version 7.0.
Anonymous


Meghraj mali 10/7/2023 1:47:00 PM

very nice question
CANADA


Noel 11/1/2022 9:14:00 PM

i have learning disability and this exam dumps allowed me to focus on the actual questions and not worry about notes and the those other study materials.
SOUTH AFRICA


Jas 10/25/2023 6:01:00 PM

165 should be apt
UNITED STATES


Neetu 6/22/2023 8:41:00 AM

please upload the dumps, real need of them
Anonymous


Mark 10/24/2023 1:34:00 AM

any recent feeedback?
UNITED STATES


Gopinadh 8/9/2023 4:05:00 AM

question number 2 is indicating you are giving proper questions. observe and change properly.
Anonymous


Santhi 1/1/2024 8:23:00 AM

passed today.40% questions were new.litwere case study,lots of new questions on afd,ratelimit,tm,lb,app gatway.got 2 set series of questions which are not present here.questions on azure cyclecloud, no.of vnet/vms required for implimentation,blueprints assignment/management group etc
INDIA


Raviraj Magadum 1/12/2024 11:39:00 AM

practice test
INDIA


sivaramakrishnan 7/27/2023 8:12:00 AM

want the dumps for emc content management server programming(cmsp)
Anonymous


Aderonke 10/23/2023 1:52:00 PM

brilliant and helpful
UNITED KINGDOM


Az 9/16/2023 2:43:00 PM

q75. azure files is pass
SWITZERLAND


ketty 11/9/2023 8:10:00 AM

very helpful
Anonymous


Sonail 5/2/2022 1:36:00 PM

thank you for these questions. it helped a lot.
UNITED STATES


Shariq 7/28/2023 8:00:00 AM

how do i get the h12-724 dumps
Anonymous


adi 10/30/2023 11:51:00 PM

nice data dumps
Anonymous


EDITH NCUBE 7/25/2023 7:28:00 AM

answers are correct
SOUTH AFRICA


Raja 6/20/2023 4:38:00 AM

good explanation
UNITED STATES


BigMouthDog 1/22/2022 8:17:00 PM

hi team just want to know if there is any update version of the exam 350-401
AUSTRALIA


francesco 10/30/2023 11:08:00 AM

helpful on 2017 scrum guide
EUROPEAN UNION


Amitabha Roy 10/5/2023 3:16:00 AM

planning to attempt for the exam.
Anonymous


Prem Yadav 7/29/2023 6:20:00 AM

pleaseee upload
INDIA


Ahmed Hashi 7/6/2023 5:40:00 PM

thanks ly so i have information cia
EUROPEAN UNION


mansi 5/31/2023 7:58:00 AM

hello team, i need sap qm dumps for practice
INDIA


Jamil aljamil 12/4/2023 4:47:00 AM

it’s good but not senatios based
UNITED KINGDOM


Cath 10/10/2023 10:19:00 AM

q.119 - the correct answer is b - they are not captured in an update set as theyre data.
VIET NAM