Which process is conducted from project inception through completion and is ultimately the responsibility of the project manager?

  1. Control Quality
  2. Monitor and Control Project Work
  3. Control Scope
  4. Perform Integrated Change Control

Answer(s): D

Explanation:

Process: 4.5 Perform Integrated Change Control
Definition: Perform Integrated Change Control is the process of reviewing all change requests; approving changes and managing changes to deliverables, organizational process assets, project documents, and the project management plan; and communicating their disposition. It reviews all requests for changes or modifications to project documents, deliverables, baselines, or the project management plan and approves or rejects the changes.
Key Benefit: The key benefit of this process is that it allows for documented changes within the project to be considered in an integrated fashion while reducing project risk, which often arises from changes made without consideration to the overall project objectives or plans.

Inputs
1. Project management plan
2. Work performance reports
3. Change requests
4. Enterprise environmental factors
5. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Meetings
3. Change control tools

Outputs

1. Approved change requests
2. Change log
3. Project management plan updates
4. Project documents updates



Project management processes ensure the:

  1. alignment with organizational strategy
  2. efficient means to achieve the project objectives
  3. performance of the project team
  4. effective flow of the project throughout its life cycle

Answer(s): D

Explanation:

Project management processes. These processes ensure the effective flow of the project throughout its life cycle. These processes encompass the tools and techniques involved in applying the skills and capabilities described in the Knowledge Areas (Sections 4 through 13)



An element of the modern quality management approach used to achieve compatibility with the International Organization for Standardization (ISO) is known as:

  1. Forecasting,
  2. Brainstorming.
  3. Historical databases.
  4. Cost of quality.

Answer(s): D

Explanation:

Cost of quality (COQ). Cost of quality refers to the total cost of the conformance work and the nonconformance work that should be done as a compensatory effort because, on the first attempt to perform that work, the potential exists that some portion of the required work effort may be done or has been done incorrectly. The costs for quality work may be incurred throughout the deliverable’s life cycle.
For example, decisions made by the project team can impact the operational costs associated with using a completed deliverable. Post-project quality costs may be incurred because of product returns, warranty claims, and recall campaigns. Therefore, because of the temporary nature of projects and the potential benefits that may be derived from reducing the post-project cost of quality, sponsoring organizations may choose to invest in product quality improvement. These investments generally are made in the areas of conformance work that act to prevent defects or act to mitigate the costs of defects by inspecting out nonconforming units.



Which items are components of a project management plan?

  1. Change management plan, process improvement plan, and scope management plan
  2. Agreements, procurement management plan, and work performance information
  3. Schedule management plan, project schedule, and resource calendars
  4. Scope baseline, project statement of work, and requirements traceability matrix

Answer(s): A



Which project document is updated in the Control Stakeholder Engagement process?

  1. Project reports
  2. Issue log
  3. Lessons learned documentation
  4. Work performance information

Answer(s): B

Explanation:

13.4.1.2 Issue Log
Described in Section 13.3.3.1. The issue log is updated as new issues are identified and current issues are resolved.
9.4.1.4 Issue Log
Issues arise in the course of managing the project team. An issue log can be used to document and monitor who is responsible for resolving specific issues by a target date.

Process: 13.4 Control Stakeholder Engagement
Definition: The process of monitoring overall project stakeholder relationships and adjusting strategies and plans for engaging stakeholders.
Key Benefit: The key benefit of this process is that it will maintain or increase the efficiency and effectiveness of stakeholder engagement activities as the project evolves and its environment changes.

Inputs
1. Project management plan
2. Issue log
3. Work performance data
4. Project documents

Tools & Techniques
1. Information management systems
2. Expert judgment
3. Meetings

Outputs
1. Work performance information
2. Change requests
3. Project management plan updates
4. Project documents updates
5. Organizational process assets updates



Share your comments for PMI PMI-100 exam with other users:

K
Kettie
10/12/2023 1:18:00 AM

this is very helpful content

S
SB
7/21/2023 3:18:00 AM

please provide the dumps

D
David
8/2/2023 8:20:00 AM

it is amazing

U
User
8/3/2023 3:32:00 AM

quesion 178 about "a banking system that predicts whether a loan will be repaid is an example of the" the answer is classification. not regresion, you should fix it.

Q
quen
7/26/2023 10:39:00 AM

please upload apache spark dumps

E
Erineo
11/2/2023 5:34:00 PM

q14 is b&c to reduce you will switch off mail for every single alert and you will switch on daily digest to get a mail once per day, you might even skip the empty digest mail but i see this as a part of the daily digest adjustment

P
Paul
10/21/2023 8:25:00 AM

i think it is good question

U
Unknown
8/15/2023 5:09:00 AM

good for students who wish to give certification.

C
Ch
11/20/2023 10:56:00 PM

is there a google drive link to the images? the links in questions are not working.

J
Joey
5/16/2023 5:25:00 AM

very promising, looks great, so much wow!

A
alaska
10/24/2023 5:48:00 AM

i scored 87% on the az-204 exam. thanks! i always trust

N
nnn
7/9/2023 11:09:00 PM

good need more

U
User-sfdc
12/29/2023 7:21:00 AM

sample questions seems good

T
Tamer dam
8/4/2023 10:21:00 AM

huawei is ok

Y
YK
12/11/2023 1:10:00 AM

good one nice

D
de
8/28/2023 2:38:00 AM

please continue

D
DMZ
6/25/2023 11:56:00 PM

this exam dumps just did the job. i donot want to ruffle your feathers but your exam dumps and mock test engine is amazing.

J
Jose
8/30/2023 6:14:00 AM

nice questions

T
Tar01
7/24/2023 7:07:00 PM

the explanation are really helpful

D
DaveG
12/15/2023 4:50:00 PM

just passed my exam yesterday on my first attempt. these dumps were extremely helpful in passing first time. the questions were very, very similar to these questions!

A
A.K.
6/30/2023 6:34:00 AM

cosmos db is paas not saas

S
S Roychowdhury
6/26/2023 5:27:00 PM

what is the percentage of common questions in gcp exam compared to 197 dump questions? are they 100% matching with real gcp exam?

B
Bella
7/22/2023 2:05:00 AM

not able to see questions

S
Scott
9/8/2023 7:19:00 AM

by far one of the best sites for free questions. i have pass 2 exams with the help of this website.

D
donald
8/19/2023 11:05:00 AM

excellent question bank.

A
Ashwini
8/22/2023 5:13:00 AM

it really helped

S
sk
5/13/2023 2:07:00 AM

excelent material

C
Christopher
9/5/2022 10:54:00 PM

the new versoin of this exam which i downloaded has all the latest questions from the exam. i only saw 3 new questions in the exam which was not in this dump.

S
Sam
9/7/2023 6:51:00 AM

question 8 - can cloudtrail be used for storing jobs? based on aws - aws cloudtrail is used for governance, compliance and investigating api usage across all of our aws accounts. every action that is taken by a user or script is an api call so this is logged to [aws] cloudtrail. something seems incorrect here.

T
Tanvi Rajput
8/14/2023 10:55:00 AM

question 13 tda - c01 answer : quick table calculation -> percentage of total , compute using table down

P
PMSAGAR
9/19/2023 2:48:00 AM

pls share teh dump

Z
zazza
6/16/2023 10:47:00 AM

question 44 answer is user risk

P
Prasana
6/23/2023 1:59:00 AM

please post the questions for preparation

T
test user
9/24/2023 3:15:00 AM

thanks for the questions

AI Tutor 👋 I’m here to help!