PMI Certified Associate in Project Management (-100) PMI-100 Dumps in PDF

Free PMI PMI-100 Real Questions (page: 30)

Which type of contract gives both the seller and the buyer flexibility to deviate from performance with financial incentives?

  1. Cost Plus Incentive Fee (CPIF)
  2. Fixed Price Incentive Fee (FPIF)
  3. Cost Pius Award Fee (CPAF)
  4. Time and Material (T&M)

Answer(s): B

Explanation:

Fixed Price Incentive Fee Contracts (FPIF). This fixed-price arrangement gives the buyer and seller some flexibility in that it allows for deviation from performance, with financial incentives tied to achieving agreed upon metrics. Typically such financial incentives are related to cost, schedule, or technical performance of the seller. Performance targets are established at the outset, and the final contract price is determined after completion of all work based on the seller’s performance. Under FPIF contracts, a price ceiling is set, and all costs above the price ceiling are the responsibility of the seller, who is obligated to complete the work.



What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?

  1. $50
  2. $100
  3. $125
  4. $175

Answer(s): C

Explanation:

Estimate to completion calculates how much more of the budget is needed to complete the project if everything continues at the current level of performance.
EAC ‘atypical’ = AC + BAC - EV
EAC ‘typical’ = AC + ((BAC - EV) / CPI)



The business needs, assumptions, and constraints and the understanding of the customers’ needs and high- level requirements are documented in the:

  1. Project management plan.
  2. Project charter.
  3. Work breakdown structure.
  4. Stakeholder register.

Answer(s): B



Which Process Group and Knowledge Area include the Sequence Activities process?

  1. Executing Process Group and Project Time Management
  2. Executing Process Group and Project Cost Management
  3. Planning Process Group and Project Time Management
  4. Planning Process Group and Project Cost Management

Answer(s): C

Explanation:

Knowledge Areas

1. 4. Project Integration Management
2. 5. Project Scope Management
3. 6. Project Time Management
4. 7. Project Cost Management
5. 8. Project Quality Management
6. 9. Project Human Resource Management
7. 10.Project Communications Management
8. 11.Project Risk Management
9. 12.Project Procurement Management
10. 13.Project Stakeholder Management

Planning Process Group
4.2 Develop Project Management Plan
5.1 Plan Scope Management
5.2 Collect Requirements
5.3 Define Scope
5.4 Create WBS
6.1 Plan Schedule Management
6.2 Define Activities
6.3 Sequence Activities
6.4 Estimate Activity Resources
6.5 Estimate Activity Durations
6.6 Develop Schedule
7.1 Plan Cost Management
7.2 Estimate Costs
7.3 Determine Budget
8.1 Plan Quality Management
9.1 Plan Human Resource Management
10.1 Plan Communications Management
11.1 Plan Risk Management
11.2 Identify Risks
11.3 Perform Qualitative Risk Analysis
11.4 Perform Quantitative Risk Analysis
11.5 Plan Risk Responses
12.1 Plan Procurement Management
13.2 Plan Stakeholder Management



In the Plan Stakeholder Management process, expert judgment is used to:

  1. Provide information needed to plan appropriate ways to engage project stakeholders.
  2. Ensure comprehensive identification and listing of new stakeholders.
  3. Analyze the information needed to develop the project scope statement.
  4. Decide the level of engagement of the stakeholders at each required stage.

Answer(s): D

Explanation:

4.1.2.1 Expert Judgment
Expert judgment is often used to assess the inputs used to develop the project charter. Expert judgment is applied to all technical and management details during this process. Such expertise is provided by any group or individual with specialized knowledge or training and is available from many sources, including:
Other units within the organization, Consultants,
Stakeholders, including customers or sponsors, Professional and technical associations, Industry groups,
Subject matter experts (SME), and Project management office (PMO).

Process: 13.2 Plan Stakeholder Management
Definition: Stakeholder Management is the process of developing appropriate management strategies to effectively engage stakeholders throughout the project life cycle, based on the analysis of their needs, interests, and potential impact on project success.
Key Benefit: The key benefit of this process is that it provides a clear, actionable plan to interact with project stakeholders to support the project’s interests.

Inputs
1. Project management plan
2. Stakeholder register
3. Enterprise environmental factors
4. Organizational process assets
Tools & Techniques
1. Expert judgment
2. Meetings
3. Analytical techniques

Outputs
Stakeholder management plan Project documents updates



Share your comments for PMI PMI-100 exam with other users:

J
Japles
5/23/2023 9:46:00 PM

password lockout being the correct answer for question 37 does not make sense. it should be geofencing.

F
Faritha
8/10/2023 6:00:00 PM

for question 4, the righr answer is :recover automatically from failures

A
Anonymous
9/14/2023 4:27:00 AM

question number 4s answer is 3, option c. i

P
p das
12/7/2023 11:41:00 PM

very good questions

A
Anna
1/5/2024 1:12:00 AM

i am confused about the answers to the questions. are the answers correct?

B
Bhavya
9/13/2023 10:15:00 AM

very usefull

R
Rahul Kumar
8/31/2023 12:30:00 PM

need certification.

D
Diran Ole
9/17/2023 5:15:00 PM

great exam prep

V
Venkata Subbarao Bandaru
6/24/2023 8:45:00 AM

i require dump

D
D
7/15/2023 1:38:00 AM

good morning, could you please upload this exam again,

A
Ann
9/15/2023 5:39:00 PM

hi can you please upload the dumps for sap contingent module. thanks

S
Sridhar
1/16/2024 9:19:00 PM

good questions

S
Summer
10/4/2023 9:57:00 PM

looking forward to the real exam

V
vv
12/2/2023 2:45:00 PM

good ones for exam preparation

D
Danny Zas
9/15/2023 4:45:00 AM

this is a good experience

S
SM 1211
10/12/2023 10:06:00 PM

hi everyone

A
A
10/2/2023 6:08:00 PM

waiting for the dump. please upload.

A
Anonymous
7/16/2023 11:05:00 AM

upload cks exam questions

J
Johan
12/13/2023 8:16:00 AM

awesome training material

P
PC
7/28/2023 3:49:00 PM

where is dump

Y
YoloStar Yoloing
10/22/2023 9:58:00 PM

q. 289 - the correct answer should be b not d, since the question asks for the most secure way to provide access to a s3 bucket (a single one), and by principle of the least privilege you should not be giving access to all buckets.

Z
Zelalem Nega
5/14/2023 12:45:00 PM

please i need if possible h12-831,

U
unknown-R
11/23/2023 7:36:00 AM

good collection of questions and solution for pl500 certification

S
Swaminathan
5/11/2023 9:59:00 AM

i would like to appear the exam.

V
Veenu
10/24/2023 6:26:00 AM

i am very happy as i cleared my comptia a+ 220-1101 exam. i studied from as it has all exam dumps and mock tests available. i got 91% on the test.

K
Karan
5/17/2023 4:26:00 AM

need this dump

R
Ramesh Kutumbaka
12/30/2023 11:17:00 PM

its really good to eventuate knowledge before appearing for the actual exam.

A
anonymous
7/20/2023 10:31:00 PM

this is great

X
Xenofon
6/26/2023 9:35:00 AM

please i want the questions to pass the exam

D
Diego
1/21/2024 8:21:00 PM

i need to pass exam

V
Vichhai
12/25/2023 3:25:00 AM

great, i appreciate it.

P
P Simon
8/25/2023 2:39:00 AM

please could you upload (isc)2 certified in cybersecurity (cc) exam questions

K
Karim
10/8/2023 8:34:00 PM

good questions, wrong answers

I
Itumeleng
1/6/2024 12:53:00 PM

im preparing for exams

AI Tutor 👋 I’m here to help!