Which type of contract gives both the seller and the buyer flexibility to deviate from performance with financial incentives?
Answer(s): B
Fixed Price Incentive Fee Contracts (FPIF). This fixed-price arrangement gives the buyer and seller some flexibility in that it allows for deviation from performance, with financial incentives tied to achieving agreed upon metrics. Typically such financial incentives are related to cost, schedule, or technical performance of the seller. Performance targets are established at the outset, and the final contract price is determined after completion of all work based on the seller’s performance. Under FPIF contracts, a price ceiling is set, and all costs above the price ceiling are the responsibility of the seller, who is obligated to complete the work.
What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?
Answer(s): C
Estimate to completion calculates how much more of the budget is needed to complete the project if everything continues at the current level of performance.EAC ‘atypical’ = AC + BAC - EVEAC ‘typical’ = AC + ((BAC - EV) / CPI)
The business needs, assumptions, and constraints and the understanding of the customers’ needs and high- level requirements are documented in the:
Which Process Group and Knowledge Area include the Sequence Activities process?
Knowledge Areas1. 4. Project Integration Management2. 5. Project Scope Management3. 6. Project Time Management4. 7. Project Cost Management5. 8. Project Quality Management6. 9. Project Human Resource Management7. 10.Project Communications Management8. 11.Project Risk Management9. 12.Project Procurement Management10. 13.Project Stakeholder ManagementPlanning Process Group4.2 Develop Project Management Plan5.1 Plan Scope Management5.2 Collect Requirements5.3 Define Scope5.4 Create WBS6.1 Plan Schedule Management6.2 Define Activities6.3 Sequence Activities6.4 Estimate Activity Resources6.5 Estimate Activity Durations6.6 Develop Schedule7.1 Plan Cost Management7.2 Estimate Costs7.3 Determine Budget8.1 Plan Quality Management9.1 Plan Human Resource Management10.1 Plan Communications Management11.1 Plan Risk Management11.2 Identify Risks11.3 Perform Qualitative Risk Analysis11.4 Perform Quantitative Risk Analysis11.5 Plan Risk Responses12.1 Plan Procurement Management13.2 Plan Stakeholder Management
In the Plan Stakeholder Management process, expert judgment is used to:
Answer(s): D
4.1.2.1 Expert JudgmentExpert judgment is often used to assess the inputs used to develop the project charter. Expert judgment is applied to all technical and management details during this process. Such expertise is provided by any group or individual with specialized knowledge or training and is available from many sources, including:Other units within the organization, Consultants,Stakeholders, including customers or sponsors, Professional and technical associations, Industry groups,Subject matter experts (SME), and Project management office (PMO).Process: 13.2 Plan Stakeholder ManagementDefinition: Stakeholder Management is the process of developing appropriate management strategies to effectively engage stakeholders throughout the project life cycle, based on the analysis of their needs, interests, and potential impact on project success.Key Benefit: The key benefit of this process is that it provides a clear, actionable plan to interact with project stakeholders to support the project’s interests.Inputs1. Project management plan2. Stakeholder register3. Enterprise environmental factors4. Organizational process assetsTools & Techniques1. Expert judgment2. Meetings3. Analytical techniquesOutputsStakeholder management plan Project documents updates
Share your comments for PMI PMI-100 exam with other users:
password lockout being the correct answer for question 37 does not make sense. it should be geofencing.
for question 4, the righr answer is :recover automatically from failures
question number 4s answer is 3, option c. i
very good questions
i am confused about the answers to the questions. are the answers correct?
very usefull
need certification.
great exam prep
i require dump
good morning, could you please upload this exam again,
hi can you please upload the dumps for sap contingent module. thanks
good questions
looking forward to the real exam
good ones for exam preparation
this is a good experience
hi everyone
waiting for the dump. please upload.
upload cks exam questions
awesome training material
where is dump
q. 289 - the correct answer should be b not d, since the question asks for the most secure way to provide access to a s3 bucket (a single one), and by principle of the least privilege you should not be giving access to all buckets.
please i need if possible h12-831,
good collection of questions and solution for pl500 certification
i would like to appear the exam.
i am very happy as i cleared my comptia a+ 220-1101 exam. i studied from as it has all exam dumps and mock tests available. i got 91% on the test.
need this dump
its really good to eventuate knowledge before appearing for the actual exam.
this is great
please i want the questions to pass the exam
i need to pass exam
great, i appreciate it.
please could you upload (isc)2 certified in cybersecurity (cc) exam questions
good questions, wrong answers
im preparing for exams