PMI Certified Associate in Project Management (-100) PMI-100 Exam Questions in PDF

Free PMI PMI-100 Dumps Questions (page: 29)

An input to the Identify Stakeholders process is:

  1. The project management plan.
  2. The stakeholder register.
  3. Procurement documents.
  4. Stakeholder analysis.

Answer(s): C

Explanation:

12.1.3.3 Procurement Documents
Procurement documents are used to solicit proposals from prospective sellers. Terms such as bid, tender, or quotation are generally used when the seller selection decision will be based on price (as when buying commercial or standard items), while a term such as proposal is generally used when other considerations, such as technical capability or technical approach are paramount. Common terms are in use for different types of procurement documents and may include request for information (RFI), invitation for bid (IFB), request for proposal (RFP), request for quotation (RFQ), tender notice, invitation for negotiation, and invitation for seller’s initial response. Specific procurement terminology used may vary by industry and location of the procurement. The buyer structures procurement documents to facilitate an accurate and complete response from each prospective seller and to facilitate easy evaluation of the responses. These documents include a description of the desired form of the response, the relevant procurement statement of work (SOW) and any required contractual provisions. With government contracting, some or all of the content and structure of procurement documents may be defined by regulation.

The complexity and level of detail of the procurement documents should be consistent with the value of, and risks associated with, the planned procurement. Procurement documents are required to be sufficient to ensure consistent, appropriate responses, but flexible enough to allow consideration of any seller suggestions for better ways to satisfy the same requirements.
Issuing a procurement request to potential sellers to submit a proposal or bid is normally done in accordance with the policies of the buyer’s organization, which can include publication of the request in public newspapers, in trade journals, in public registries, or on the internet.

Process: 13.1 Identify Stakeholders
Definition: The process of identifying the people, groups, or organizations that could impact or be impacted by a decision, activity, or outcome of the project; and analyzing and documenting relevant information regarding their interests, involvement, interdependencies, influence, and potential impact on project success.
Key Benefit: The key benefit of this process is that it allows the project manager to identify the appropriate focus for each stakeholder or group of stakeholders.

Inputs
1. Project charter
2. Procurement documents
3. Enterprise environmental factors
4. Organizational process assets

Tools & Techniques
1. Stakeholder analysis
2. Expert judgment
3. Meetings

Outputs
1. Stakeholder register



Identify Risks is part of which Process Group?

  1. Planning
  2. Executing
  3. Closing
  4. Initiating

Answer(s): A

Explanation:

Planning Process Group
4.2 Develop Project Management Plan
5.1 Plan Scope Management
5.2 Collect Requirements

5.3 Define Scope
5.4 Create WBS
6.1 Plan Schedule Management
6.2 Define Activities
6.3 Sequence Activities
6.4 Estimate Activity Resources
6.5 Estimate Activity Durations
6.6 Develop Schedule
7.1 Plan Cost Management
7.2 Estimate Costs
7.3 Determine Budget
8.1 Plan Quality Management
9.1 Plan Human Resource Management
10.1 Plan Communications Management
11.1 Plan Risk Management
11.2 Identify Risks
11.3 Perform Qualitative Risk Analysis
11.4 Perform Quantitative Risk Analysis
11.5 Plan Risk Responses
12.1 Plan Procurement Management
13.2 Plan Stakeholder Management



Which conflict resolution technique searches for solutions that bring some degree of satisfaction to all parties in order to temporarily or partially resolve the conflict?

  1. Force/direct
  2. Withdraw/avoid
  3. Compromise/reconcile
  4. Collaborate/problem solve

Answer(s): C



Which tool or technique is used in the Perform Integrated Change Control process?

  1. Decomposition
  2. Modeling techniques
  3. Resource optimization
  4. Meetings

Answer(s): D

Explanation:

4.3.2.3 Meetings
Meetings are used to discuss and address pertinent topics of the project when directing and managing project work. Attendees at the meetings may include the project manager, the project team and appropriate stakeholders involved or affected by the topics addressed. Each attendee should have a defined role to ensure appropriate participation. Meetings tend to be one of three types:

Information exchange;
Brainstorming, option evaluation, or design; or Decision making.
Meeting types should not be mixed as a best practice. Meetings should be prepared with a well-defined agenda, purpose, objective, and time frame and should be appropriately documented with meeting minutes and action items. Meeting minutes should be stored as defined in the project management plan. Meetings are most effective when all participants can be face-to-face in the same location. Virtual meetings can be held using audio and/or video conferencing tools, but generally require additional preparation and organization to achieve the same effectiveness of a face-to-face meeting.

Process: 4.5 Perform Integrated Change Control
Perform Integrated Change Control is the process of reviewing all change requests; approving changes and managing changes to deliverables, organizational process assets, project documents, and the project management plan; and communicating their disposition. It reviews all requests for changes or modifications to project documents, deliverables, baselines, or the project management plan and approves or rejects the changes.
Key Benefit: The key benefit of this process is that it allows for documented changes within the project to be considered in an integrated fashion while reducing project risk, which often arises from changes made without consideration to the overall project objectives or plans.

Inputs
1. Project management plan
2. Work performance reports
3. Change requests
4. Enterprise environmental factors
5. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Meetings
3. Change control tools

Outputs
1. Approved change requests
2. Change log
3. Project management plan updates
4. Project documents updates



A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:

  1. Start-to-start (SS).
  2. Start-to-finish (SF).
  3. Finish-to-start (FS).
  4. Finish-to-finish (FF).

Answer(s): C

Explanation:

A finish-to-start (FS) relationship between two activities implies that the initiation of successor is dependent on the completion of predecessor.
A finish-to-finish (FF) relationship between two activities implies that the completion of successor is dependent on the completion of predecessor.
A start-to-start (SS) relationship implies that the initiation of successor is dependent on the initiation of predecessor.
A start-to-finish (SF) relationship between two activities implies that the completion of successor is dependent on the initiation of its predecessor



Share your comments for PMI PMI-100 exam with other users:

L
Lily
4/24/2023 10:50:00 PM

questions made studying easy and enjoyable, passed on the first try!

J
John
8/7/2023 12:12:00 AM

has anyone recently attended safe 6.0 exam? did you see any questions from here?

B
Big Dog
6/24/2023 4:47:00 PM

question 13 should be dhcp option 43, right?

B
B.Khan
4/19/2022 9:43:00 PM

the buy 1 get 1 is a great deal. so far i have only gone over exam. it looks promissing. i report back once i write my exam.

G
Ganesh
12/24/2023 11:56:00 PM

is this dump good

A
Albin
10/13/2023 12:37:00 AM

good ................

P
Passed
1/16/2022 9:40:00 AM

passed

H
Harsh
6/12/2023 1:43:00 PM

yes going good

S
Salesforce consultant
1/2/2024 1:32:00 PM

good questions for practice

R
Ridima
9/12/2023 4:18:00 AM

need dump and sap notes for c_s4cpr_2308 - sap certified application associate - sap s/4hana cloud, public edition - sourcing and procurement

T
Tanvi Rajput
10/6/2023 6:50:00 AM

question 11: d i personally feel some answers are wrong.

A
Anil
7/18/2023 9:38:00 AM

nice questions

C
Chris
8/26/2023 1:10:00 AM

looking for c1000-158: ibm cloud technical advocate v4 questions

S
sachin
6/27/2023 1:22:00 PM

can you share the pdf

B
Blessious Phiri
8/13/2023 10:26:00 AM

admin ii is real technical stuff

L
Luis Manuel
7/13/2023 9:30:00 PM

could you post the link

V
vijendra
8/18/2023 7:54:00 AM

hello send me dumps

S
Simeneh
7/9/2023 8:46:00 AM

it is very nice

J
john
11/16/2023 5:13:00 PM

i gave the amazon dva-c02 tests today and passed. very helpful.

T
Tao
11/20/2023 8:53:00 AM

there is an incorrect word in the problem statement. for example, in question 1, there is the word "speci c". this is "specific. in the other question, there is the word "noti cation". this is "notification. these mistakes make this site difficult for me to use.

P
patricks
10/24/2023 6:02:00 AM

passed my az-120 certification exam today with 90% marks. studied using the dumps highly recommended to all.

A
Ananya
9/14/2023 5:17:00 AM

i need it, plz make it available

J
JM
12/19/2023 2:41:00 PM

q47: intrusion prevention system is the correct answer, not patch management. by definition, there are no patches available for a zero-day vulnerability. the way to prevent an attacker from exploiting a zero-day vulnerability is to use an ips.

R
Ronke
8/18/2023 10:39:00 AM

this is simple but tiugh as well

C
CesarPA
7/12/2023 10:36:00 PM

questão 4, segundo meu compilador local e o site https://www.jdoodle.com/online-java-compiler/, a resposta correta é "c" !

J
Jeya
9/13/2023 7:50:00 AM

its very useful

T
Tracy
10/24/2023 6:28:00 AM

i mastered my skills and aced the comptia 220-1102 exam with a score of 920/1000. i give the credit to for my success.

J
James
8/17/2023 4:33:00 PM

real questions

A
Aderonke
10/23/2023 1:07:00 PM

very helpful assessments

S
Simmi
8/24/2023 7:25:00 AM

hi there, i would like to get dumps for this exam

J
johnson
10/24/2023 5:47:00 AM

i studied for the microsoft azure az-204 exam through it has 100% real questions available for practice along with various mock tests. i scored 900/1000.

M
Manas
9/9/2023 1:48:00 AM

please upload 1z0-1072-23 exam dups

S
SB
9/12/2023 5:15:00 AM

i was hoping if you could please share the pdf as i’m currently preparing to give the exam.

J
Jagjit
8/26/2023 5:01:00 PM

i am looking for oracle 1z0-116 exam

AI Tutor 👋 I’m here to help!