PMI Certified Associate in Project Management (-100) PMI-100 Dumps in PDF

Free PMI PMI-100 Real Questions (page: 29)

An input to the Identify Stakeholders process is:

  1. The project management plan.
  2. The stakeholder register.
  3. Procurement documents.
  4. Stakeholder analysis.

Answer(s): C

Explanation:

12.1.3.3 Procurement Documents
Procurement documents are used to solicit proposals from prospective sellers. Terms such as bid, tender, or quotation are generally used when the seller selection decision will be based on price (as when buying commercial or standard items), while a term such as proposal is generally used when other considerations, such as technical capability or technical approach are paramount. Common terms are in use for different types of procurement documents and may include request for information (RFI), invitation for bid (IFB), request for proposal (RFP), request for quotation (RFQ), tender notice, invitation for negotiation, and invitation for seller’s initial response. Specific procurement terminology used may vary by industry and location of the procurement. The buyer structures procurement documents to facilitate an accurate and complete response from each prospective seller and to facilitate easy evaluation of the responses. These documents include a description of the desired form of the response, the relevant procurement statement of work (SOW) and any required contractual provisions. With government contracting, some or all of the content and structure of procurement documents may be defined by regulation.

The complexity and level of detail of the procurement documents should be consistent with the value of, and risks associated with, the planned procurement. Procurement documents are required to be sufficient to ensure consistent, appropriate responses, but flexible enough to allow consideration of any seller suggestions for better ways to satisfy the same requirements.
Issuing a procurement request to potential sellers to submit a proposal or bid is normally done in accordance with the policies of the buyer’s organization, which can include publication of the request in public newspapers, in trade journals, in public registries, or on the internet.

Process: 13.1 Identify Stakeholders
Definition: The process of identifying the people, groups, or organizations that could impact or be impacted by a decision, activity, or outcome of the project; and analyzing and documenting relevant information regarding their interests, involvement, interdependencies, influence, and potential impact on project success.
Key Benefit: The key benefit of this process is that it allows the project manager to identify the appropriate focus for each stakeholder or group of stakeholders.

Inputs
1. Project charter
2. Procurement documents
3. Enterprise environmental factors
4. Organizational process assets

Tools & Techniques
1. Stakeholder analysis
2. Expert judgment
3. Meetings

Outputs
1. Stakeholder register



Identify Risks is part of which Process Group?

  1. Planning
  2. Executing
  3. Closing
  4. Initiating

Answer(s): A

Explanation:

Planning Process Group
4.2 Develop Project Management Plan
5.1 Plan Scope Management
5.2 Collect Requirements

5.3 Define Scope
5.4 Create WBS
6.1 Plan Schedule Management
6.2 Define Activities
6.3 Sequence Activities
6.4 Estimate Activity Resources
6.5 Estimate Activity Durations
6.6 Develop Schedule
7.1 Plan Cost Management
7.2 Estimate Costs
7.3 Determine Budget
8.1 Plan Quality Management
9.1 Plan Human Resource Management
10.1 Plan Communications Management
11.1 Plan Risk Management
11.2 Identify Risks
11.3 Perform Qualitative Risk Analysis
11.4 Perform Quantitative Risk Analysis
11.5 Plan Risk Responses
12.1 Plan Procurement Management
13.2 Plan Stakeholder Management



Which conflict resolution technique searches for solutions that bring some degree of satisfaction to all parties in order to temporarily or partially resolve the conflict?

  1. Force/direct
  2. Withdraw/avoid
  3. Compromise/reconcile
  4. Collaborate/problem solve

Answer(s): C



Which tool or technique is used in the Perform Integrated Change Control process?

  1. Decomposition
  2. Modeling techniques
  3. Resource optimization
  4. Meetings

Answer(s): D

Explanation:

4.3.2.3 Meetings
Meetings are used to discuss and address pertinent topics of the project when directing and managing project work. Attendees at the meetings may include the project manager, the project team and appropriate stakeholders involved or affected by the topics addressed. Each attendee should have a defined role to ensure appropriate participation. Meetings tend to be one of three types:

Information exchange;
Brainstorming, option evaluation, or design; or Decision making.
Meeting types should not be mixed as a best practice. Meetings should be prepared with a well-defined agenda, purpose, objective, and time frame and should be appropriately documented with meeting minutes and action items. Meeting minutes should be stored as defined in the project management plan. Meetings are most effective when all participants can be face-to-face in the same location. Virtual meetings can be held using audio and/or video conferencing tools, but generally require additional preparation and organization to achieve the same effectiveness of a face-to-face meeting.

Process: 4.5 Perform Integrated Change Control
Perform Integrated Change Control is the process of reviewing all change requests; approving changes and managing changes to deliverables, organizational process assets, project documents, and the project management plan; and communicating their disposition. It reviews all requests for changes or modifications to project documents, deliverables, baselines, or the project management plan and approves or rejects the changes.
Key Benefit: The key benefit of this process is that it allows for documented changes within the project to be considered in an integrated fashion while reducing project risk, which often arises from changes made without consideration to the overall project objectives or plans.

Inputs
1. Project management plan
2. Work performance reports
3. Change requests
4. Enterprise environmental factors
5. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Meetings
3. Change control tools

Outputs
1. Approved change requests
2. Change log
3. Project management plan updates
4. Project documents updates



A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:

  1. Start-to-start (SS).
  2. Start-to-finish (SF).
  3. Finish-to-start (FS).
  4. Finish-to-finish (FF).

Answer(s): C

Explanation:

A finish-to-start (FS) relationship between two activities implies that the initiation of successor is dependent on the completion of predecessor.
A finish-to-finish (FF) relationship between two activities implies that the completion of successor is dependent on the completion of predecessor.
A start-to-start (SS) relationship implies that the initiation of successor is dependent on the initiation of predecessor.
A start-to-finish (SF) relationship between two activities implies that the completion of successor is dependent on the initiation of its predecessor



Share your comments for PMI PMI-100 exam with other users:

J
Jimmy
11/4/2023 12:11:00 PM

prep for exam

A
Abhi
9/19/2023 1:22:00 PM

thanks for helping us

M
mrtom33
11/20/2023 4:51:00 AM

i prepared for the eccouncil 350-401 exam. i scored 92% on the test.

J
JUAN
6/28/2023 2:12:00 AM

aba questions to practice

L
LK
1/2/2024 11:56:00 AM

great content

S
Srijeeta
10/8/2023 6:24:00 AM

how do i get the remaining questions?

J
Jovanne
7/26/2022 11:42:00 PM

well formatted pdf and the test engine software is free. well worth the money i sept.

C
CHINIMILLI SATISH
8/29/2023 6:22:00 AM

looking for 1z0-116

P
Pedro Afonso
1/15/2024 8:01:00 AM

in question 22, shouldnt be in the data (option a) layer?

P
Pushkar
11/7/2022 12:12:00 AM

the questions are incredibly close to real exam. you people are amazing.

A
Ankit S
11/13/2023 3:58:00 AM

q15. answer is b. simple

S
S. R
12/8/2023 9:41:00 AM

great practice

M
Mungara
3/14/2023 12:10:00 AM

thanks to this exam dumps, i felt confident and passed my exam with ease.

A
Anonymous
7/25/2023 2:55:00 AM

need 1z0-1105-22 exam

N
Nigora
5/31/2022 10:05:00 PM

this is a beautiful tool. passed after a week of studying.

A
Av dey
8/16/2023 2:35:00 PM

can you please upload the dumps for 1z0-1096-23 for oracle

M
Mayur Shermale
11/23/2023 12:22:00 AM

its intresting, i would like to learn more abouth this

J
JM
12/19/2023 2:23:00 PM

q252: dns poisoning is the correct answer, not locator redirection. beaconing is detected from a host. this indicates that the system has been infected with malware, which could be the source of local dns poisoning. location redirection works by either embedding the redirection in the original websites code or having a user click on a url that has an embedded redirect. since users at a different office are not getting redirected, it isnt an embedded redirection on the original website and since the user is manually typing in the url and not clicking a link, it isnt a modified link.

F
Freddie
12/12/2023 12:37:00 PM

helpful dump questions

D
Da Costa
8/25/2023 7:30:00 AM

question 423 eigrp uses metric

B
Bsmaind
8/20/2023 9:22:00 AM

hello nice dumps

B
beau
1/12/2024 4:53:00 PM

good resource for learning

S
Sandeep
12/29/2023 4:07:00 AM

very useful

K
kevin
9/29/2023 8:04:00 AM

physical tempering techniques

B
Blessious Phiri
8/15/2023 4:08:00 PM

its giving best technical knowledge

T
Testbear
6/13/2023 11:15:00 AM

please upload

S
shime
10/24/2023 4:23:00 AM

great question with explanation thanks!!

T
Thembelani
5/30/2023 2:40:00 AM

does this exam have lab sections?

S
Shin
9/8/2023 5:31:00 AM

please upload

P
priti kagwade
7/22/2023 5:17:00 AM

please upload the braindump for .net

R
Robe
9/27/2023 8:15:00 PM

i need this exam 1z0-1107-2. please.

C
Chiranthaka
9/20/2023 11:22:00 AM

very useful!

N
Not Miguel
11/26/2023 9:43:00 PM

for this question - "which three type of basic patient or member information is displayed on the patient info component? (choose three.)", list of conditions is not displayed (it is displayed in patient card, not patient info). so should be thumbnail of chatter photo

A
Andrus
12/17/2023 12:09:00 PM

q52 should be d. vm storage controller bandwidth represents the amount of data (in terms of bandwidth) that a vms storage controller is using to read and write data to the storage fabric.

AI Tutor 👋 I’m here to help!