Which output is the approved version of the time-phased project budget?

  1. Resource calendar
  2. Scope baseline
  3. Trend analysis
  4. Cost baseline

Answer(s): D

Explanation:

A project budget includes all the funds authorized to execute the project. The cost baseline is the approved version of the time-phased project budget, but excludes management reserves.

7.3.3.1 Cost Baseline
The cost baseline is the approved version of the time-phased project budget, excluding any management reserves, which can only be changed through formal change control procedures and is used as a basis for comparison to actual results. It is developed as a summation of the approved budgets for the different schedule activities.



The purpose of the Project Communications Management Knowledge Area is to:

  1. Monitor and control communications throughout the entire project life cycle.
  2. Maintain an optimal flow of information among all project participants.
  3. Develop an appropriate approach for project communications.
  4. Ensure timely and appropriate collection of project information.

Answer(s): D

Explanation:

10. Project Communications Management
Project Communications Management includes the processes that are required to ensure timely and appropriate planning, collection, creation, distribution, storage, retrieval, management, control, monitoring, and the ultimate disposition of project information.



Processes in the Initiating Process Group may be completed at the organizational level and be outside of the project's:

  1. Level of control.
  2. Communication channels.
  3. Scope.
  4. Strategic alignment.

Answer(s): A



At the completion of a project, a report is prepared that details the outcome of the research conducted on a global trend during the project. Which item did this project create?

  1. Result
  2. Product
  3. Service
  4. Improvement

Answer(s): A



Power, urgency, and legitimacy are attributes of which stakeholder classification model?

  1. Salience
  2. Influence/impact
  3. Power/interest
  4. Power/influence

Answer(s): A

Explanation:

13.1.2.1 Stakeholder Analysis
Stakeholder analysis is a technique of systematically gathering and analyzing quantitative and qualitative information to determine whose interests should be taken into account throughout the project. It identifies the interests, expectations, and influence of the stakeholders and relates them to the purpose of the project. It also helps to identify stakeholder relationships (with the project and with other stakeholders) that can be leveraged to build coalitions and potential partnerships to enhance the project’s chance of success, along with stakeholder relationships that need to be influenced differently at different stages of the project or phase.

Stakeholder analysis generally follows the steps described below:
Identify all potential project stakeholders and relevant information, such as their roles, departments, interests, knowledge, expectations, and influence levels. Key stakeholders are usually easy to identify. They include anyone in a decision-making or management role who is impacted by the project outcome, such as the sponsor, the project manager, and the primary customer. Identifying other stakeholders is usually done by interviewing identified stakeholders and expanding the list until all potential stakeholders are included.
Analyze the potential impact or support each stakeholder could generate, and classify them so as to define an approach strategy. In large stakeholder communities, it is important to prioritize the stakeholders to ensure the efficient use of effort to communicate and manage their expectations.
Assess how key stakeholders are likely to react or respond in various situations, in order to plan how to influence them to enhance their support and mitigate potential negative impacts.

There are multiple classification models used for stakeholders analysis, such as:
Power/interest grid, grouping the stakeholders based on their level of authority (“power”) and their level or concern (“interest”) regarding the project outcomes;
Power/influence grid, grouping the stakeholders based on their level of authority (“power”) and their active involvement (“influence”) in the project;
Influence/impact grid, grouping the stakeholders based on their active involvement (“influence”) in the project and their ability to effect changes to the project’s planning or execution (“impact”); and
Salience model, describing classes of stakeholders based on their power (ability to impose their will), urgency (need for immediate attention), and legitimacy (their involvement is appropriate).



Share your comments for PMI PMI-100 exam with other users:

B
Blessious Phiri
8/13/2023 9:35:00 AM

rman is one good recovery technology

D
DiligentSam
9/30/2023 10:26:00 AM

need it thx

V
Vani
8/10/2023 8:11:00 PM

good questions

F
Fares
9/11/2023 5:00:00 AM

good one nice revision

L
Lingaraj
10/26/2023 1:27:00 AM

i love this thank you i need

M
Muhammad Rawish Siddiqui
12/5/2023 12:38:00 PM

question # 142: data governance is not one of the deliverables in the document and content management context diagram.

A
al
6/7/2023 10:25:00 AM

most answers not correct here

B
Bano
1/19/2024 2:29:00 AM

what % of questions do we get in the real exam?

O
Oliviajames
10/25/2023 5:31:00 AM

i just want to tell you. i took my microsoft az-104 exam and passed it. your program was awesome. i especially liked your detailed questions and answers and practice tests that made me well-prepared for the exam. thanks to this website!!!

D
Divya
8/27/2023 12:31:00 PM

all the best

K
KY
1/1/2024 11:01:00 PM

very usefull document

A
Arun
9/20/2023 4:52:00 PM

nice and helpful questions

J
Joseph J
7/11/2023 2:53:00 PM

i found the questions helpful

M
Meg
10/12/2023 8:02:00 AM

q 105 . ans is d

N
Navaneeth S
7/14/2023 7:57:00 AM

i have interest to get a sybase iq dba certification

A
Aish
10/11/2023 5:27:00 AM

want to pass exm.

A
Anonymous
6/12/2023 7:23:00 AM

are the answers correct?

K
Kris
7/7/2023 9:43:00 AM

good morning, could you please upload this exam again, i need it to test my knowledge in sd-wan with version 7.0.

M
Meghraj mali
10/7/2023 1:47:00 PM

very nice question

N
Noel
11/1/2022 9:14:00 PM

i have learning disability and this exam dumps allowed me to focus on the actual questions and not worry about notes and the those other study materials.

J
Jas
10/25/2023 6:01:00 PM

165 should be apt

N
Neetu
6/22/2023 8:41:00 AM

please upload the dumps, real need of them

M
Mark
10/24/2023 1:34:00 AM

any recent feeedback?

G
Gopinadh
8/9/2023 4:05:00 AM

question number 2 is indicating you are giving proper questions. observe and change properly.

S
Santhi
1/1/2024 8:23:00 AM

passed today.40% questions were new.litwere case study,lots of new questions on afd,ratelimit,tm,lb,app gatway.got 2 set series of questions which are not present here.questions on azure cyclecloud, no.of vnet/vms required for implimentation,blueprints assignment/management group etc

R
Raviraj Magadum
1/12/2024 11:39:00 AM

practice test

S
sivaramakrishnan
7/27/2023 8:12:00 AM

want the dumps for emc content management server programming(cmsp)

A
Aderonke
10/23/2023 1:52:00 PM

brilliant and helpful

A
Az
9/16/2023 2:43:00 PM

q75. azure files is pass

K
ketty
11/9/2023 8:10:00 AM

very helpful

S
Sonail
5/2/2022 1:36:00 PM

thank you for these questions. it helped a lot.

S
Shariq
7/28/2023 8:00:00 AM

how do i get the h12-724 dumps

A
adi
10/30/2023 11:51:00 PM

nice data dumps

E
EDITH NCUBE
7/25/2023 7:28:00 AM

answers are correct

AI Tutor 👋 I’m here to help!