PMI Certified Associate in Project Management (-100) PMI-100 Dumps in PDF

Free PMI PMI-100 Real Questions (page: 42)

A project manager should communicate to stakeholders about resolved project issues by updating the:

  1. project records
  2. project reports
  3. stakeholder notifications
  4. stakeholder register

Answer(s): C

Explanation:

10.2.3.4 Organizational Process Assets Updates
The organizational process assets, which may be updated include, but are not limited to:

Stakeholder notifications. Information may be provided to stakeholders about resolved issues, approved changes, and general project status.

Project reports. Formal and informal project reports describe project status and include lessons learned, issue logs, project closure reports, and outputs from other Knowledge Areas (Sections 4-13).
Project presentations. The project team provides information formally or informally to any or all of the project stakeholders. The information and presentation method should be relevant to the needs of the audience.
Project records. Project records may include correspondence, memos, meeting minutes, and other documents describing the project. This information should, to the extent possible and appropriate, be maintained in an organized manner. Project team members can also maintain records in a project notebook or register, which could be physical or electronic.
Feedback from stakeholders. Information received from stakeholders concerning project operations is distributed and used to modify or improve future performance of the project.
Lessons learned documentation. Documentation includes the causes of issues, reasoning behind the corrective action chosen, and other types of lessons learned about communications management. Lessons learned need to be documented and distributed so that it becomes part of the historical database for both the project and the performing organization.



Which Project Time Management process includes bottom-up estimating as a tool or technique?

  1. Estimate Activity Resources
  2. Sequence Activities
  3. Estimate Activity Durations
  4. Develop Schedule

Answer(s): A

Explanation:

Process: 6.4 Estimate Activity Resources
Definition: The process of estimating the type and quantities of material, human resources, equipment, or supplies required to perform each activity.
Key Benefit: The key benefit of this process is that it identifies the type, quantity, and characteristics of resources required to complete the activity which allows more accurate cost and duration estimates.

Inputs
1. Schedule management plan
2. Activity list
3. Activity attributes
4. Resource calendars

5. Risk register
6. Activity cost estimates
7. Enterprise environmental factors
8. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Alternative analysis
3. Published estimating data
4. Bottom-up estimating
5. Project management software

Outputs
1. Activity resource requirements
2. Resource breakdown structure
3. Project documents updates



Progressively elaborating high-level information into detailed plans is performed by the:

  1. project management office
  2. portfolio manager
  3. program manager
  4. project manager

Answer(s): D



An input to the Control Quality process is:

  1. Activity attributes
  2. Quality control measurements
  3. Enterprise environmental factors
  4. Deliverables

Answer(s): D

Explanation:

Process: 8.3 Control Quality
Definition: The process of monitoring and recording results of executing the quality activities to assess performance and recommend necessary changes.
Key Benefit: The key benefits of this process include: (1) identifying the causes of poor process or product quality and recommending and/or taking action to eliminate them; and (2) validating that project deliverables and work meet the requirements specified by key stakeholders necessary for final acceptance.

Inputs
1. Project management plan
2. Quality metrics
3. Quality checklists

4. Work performance data
5. Approved change requests
6. Deliverables
7. Project documents
8. Organizational process assets

Tools & Techniques
1. Seven basic quality tools
2. Statistical sampling
3. Inspection
4. Approved change requests review

Outputs
1. Quality control measurements
2. Validated changes
3. Verified deliverables
4. Work performance information
5. Change requests
6. Project management plan updates
7. Project documents updates
8. Organizational process assets updates



The chart below is an example of a:

  1. Responsibility assignment matrix (RAM)
  2. Work breakdown structure (WBS)
  3. RACI chart
  4. Requirements traceability matrix

Answer(s): D

Explanation:

5.2.3.2 Requirements Traceability Matrix
The requirements traceability matrix is a grid that links product requirements from their origin to the deliverables that satisfy them. The implementation of a requirements traceability matrix helps ensure that each requirement adds business value by linking it to the business and project objectives. It provides a means to track requirements throughout the project life cycle, helping to ensure that requirements approved in the requirements documentation are delivered at the end of the project. Finally, it provides a structure for managing changes to the product scope.
Tracing includes, but is not limited to, tracing requirements for the following:

Business needs, opportunities, goals, and objectives; Project objectives;
Project scope/WBS deliverables;

Product design; Product development;
Test strategy and test scenarios; and
High-level requirements to more detailed requirements.
Attributes associated with each requirement can be recorded in the requirements traceability matrix. These attributes help to define key information about the requirement. Typical attributes used in the requirements traceability matrix may include: a unique identifier, a textual description of the requirement, the rationale for inclusion, owner, source, priority, version, current status (such as active, cancelled, deferred, added, approved, assigned, completed), and status date. Additional attributes to ensure that the requirement has met stakeholders’ satisfaction may include stability, complexity, and acceptance criteria.



Share your comments for PMI PMI-100 exam with other users:

A
anon
10/15/2023 12:21:00 PM

q55- the ridac workflow can be modified using flow designer, correct answer is d not a

N
NanoTek3
6/13/2022 10:44:00 PM

by far this is the most accurate exam dumps i have ever purchased. all questions are in the exam. i saw almost 90% of the questions word by word.

E
eriy
11/9/2023 5:12:00 AM

i cleared the az-104 exam by scoring 930/1000 on the exam. it was all possible due to this platform as it provides premium quality service. thank you!

M
Muhammad Rawish Siddiqui
12/8/2023 8:12:00 PM

question # 232: accessibility, privacy, and innovation are not data quality dimensions.

V
Venkat
12/27/2023 9:04:00 AM

looks wrong answer for 443 question, please check and update

V
Varun
10/29/2023 9:11:00 PM

great question

D
Doc
10/29/2023 9:36:00 PM

question: a user wants to start a recruiting posting job posting. what must occur before the posting process can begin? 3 ans: comment- option e is incorrect reason: as part of enablement steps, sap recommends that to be able to post jobs to a job board, a user need to have the correct permission and secondly, be associated with one posting profile at minimum

I
It‘s not A
9/17/2023 5:31:00 PM

answer to question 72 is d [sys_user_role]

I
indira m
8/14/2023 12:15:00 PM

please provide the pdf

R
ribrahim
8/1/2023 6:05:00 AM

hey guys, just to let you all know that i cleared my 312-38 today within 1 hr with 100 questions and passed. thank you so much brain-dumps.net all the questions that ive studied in this dump came out exactly the same word for word "verbatim". you rock brain-dumps.net!!! section name total score gained score network perimeter protection 16 11 incident response 10 8 enterprise virtual, cloud, and wireless network protection 12 8 application and data protection 13 10 network défense management 10 9 endpoint protection 15 12 incident d

A
Andrew
8/23/2023 6:02:00 PM

very helpful

L
latha
9/7/2023 8:14:00 AM

useful questions

I
ibrahim
11/9/2023 7:57:00 AM

page :20 https://exam-dumps.com/snowflake/free-cof-c02-braindumps.html?p=20#collapse_453 q 74: true or false: pipes can be suspended and resumed. true. desc.: pausing or resuming pipes in addition to the pipe owner, a role that has the following minimum permissions can pause or resume the pipe https://docs.snowflake.com/en/user-guide/data-load-snowpipe-intro

F
Franklin Allagoa
7/5/2023 5:16:00 AM

i want hcia exam dumps

S
SSA
12/24/2023 1:18:00 PM

good training

B
BK
8/11/2023 12:23:00 PM

very useful

D
Deepika Narayanan
7/13/2023 11:05:00 PM

yes need this exam dumps

B
Blessious Phiri
8/15/2023 3:31:00 PM

these questions are a great eye opener

J
Jagdesh
9/8/2023 8:17:00 AM

thank you for providing these questions and answers. they helped me pass my exam. you guys are great.

T
TS
7/18/2023 3:32:00 PM

good knowledge

A
Asad Khan
11/1/2023 2:44:00 AM

answer 10 should be a because only a new project will be created & the organization is the same.

R
Raj
9/12/2023 3:49:00 PM

can you please upload the dump again

C
Christian Klein
6/23/2023 1:32:00 PM

is it legit questions from sap certifications ?

A
anonymous
1/12/2024 3:34:00 PM

question 16 should be b (changing the connector settings on the monitor) pc and monitor were powered on. the lights on the pc are on indicating power. the monitor is showing an error text indicating that it is receiving power too. this is a clear sign of having the wrong input selected on the monitor. thus, the "connector setting" needs to be switched from hdmi to display port on the monitor so it receives the signal from the pc, or the other way around (display port to hdmi).

N
NSPK
1/18/2024 10:26:00 AM

q 10. ans is d (in the target org: open deployment settings, click edit next to the source org. select allow inbound changes and save

M
mohamed abdo
9/1/2023 4:59:00 AM

very useful

T
Tom
3/18/2022 8:00:00 PM

i purchased this exam dumps from another website with way more questions but they were all invalid and outdate. this exam dumps was right to the point and all from recent exam. it was a hard pass.

E
Edrick GOP
10/24/2023 6:00:00 AM

it was a good experience and i got 90% in the 200-901 exam.

A
anonymous
8/10/2023 2:28:00 AM

hi please upload this

B
Bakir
7/6/2023 7:24:00 AM

please upload it

A
Aman
6/18/2023 1:27:00 PM

really need this dump. can you please help.

N
Neela Para
1/8/2024 6:39:00 PM

really good and covers many areas explaining the answer.

K
Karan Patel
8/15/2023 12:51:00 AM

yes, can you please upload the exam?

N
NISHAD
11/7/2023 11:28:00 AM

how many questions are there in these dumps?

AI Tutor 👋 I’m here to help!