Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?
Answer(s): A
Which stakeholder approves a project's result?
Which process involves determining, documenting, and managing stakeholders' needs and requirements to meet project objectives?
Process: 5.2 Collect RequirementsDefinition: The process of determining, documenting, and managing stakeholder needs and requirements to meet project objectives.Key Benefit: The key benefit of this process is that it provides the basis for defining and managing the project scope including product scope.Inputs1. Scope management plan2. Requirements management plan3. Stakeholder management plan4. Project charter5. Stakeholder registerTools & Techniques1. Interviews2. Focus groups3. Facilitated workshops4. Group creativity techniques5. Group decision-making techniques6. Questionnaires and surveys7. Observations8. Prototypes9. Benchmarking10. Context diagrams11. Document analysisOutputs1. Requirements documentation2. Requirements traceability matrix
Plan Communications Management develops an approach and plan for project communications based on stakeholders' needs and requirements and:
Process: 10.1 Plan Communications ManagementDefinition: The process of developing an appropriate approach and plan for project communications based on stakeholder’s information needs and requirements, and available organizational assets.Key Benefit: The key benefit of this process is that it identifies and documents the approach to communicate most effectively and efficiently with stakeholders.Inputs1. Project management plan 2. Stakeholder register3. Enterprise environmental factors4. Organizational process assetsTools & Techniques1. Communication requirements analysis2. Communication technology3. Communication models4. Communication methods5. MeetingsOutputs1. Communications management plan2. Project documents updates
Perform Integrated Change Control is the process of:
Process: 4.5 Perform Integrated Change ControlPerform Integrated Change Control is the process of reviewing all change requests; approving changes and managing changes to deliverables, organizational process assets, project documents, and the project management plan; and communicating their disposition. It reviews all requests for changes or modifications to project documents, deliverables, baselines, or the project management plan and approves or rejects the changes.Key Benefit: The key benefit of this process is that it allows for documented changes within the project to be considered in an integrated fashion while reducing project risk, which often arises from changes made without consideration to the overall project objectives or plans.Inputs1. Project management plan2. Work performance reports3. Change requests4. Enterprise environmental factors5. Organizational process assetsTools & Techniques1. Expert judgment2. Meetings3. Change control toolsOutputs1. Approved change requests2. Change log3. Project management plan updates4. Project documents updates
Share your comments for PMI PMI-100 exam with other users:
i think it should be a,c. option d goes against the principle of building anything custom unless there are no work arounds available
very legible
is this exam accurate or helpful?
please upload dump, i have exam in 2 days
this is useful
question 232 answer should be perimeter not netowrk layer. wrong answer selected
nice questions
hi team, could you please provide this dump ?
very helpful to clear the exam and understand the concept.
i think it is great that you are helping people when they need it. thanks.
cannot evaluate yet
a laptops wireless antenna is most likely located in the bezel of the lid
good examplae to learn basic
this is useful information
looks usefull
question 81 should be c.
question 18 : response isnt a ?
plaese add questions
is dumps still valid ?
thanks for this
please upload questions
please upload the question dump for professional machinelearning
question 4 answer is c. this site shows the correct answer as b. "adopt a consumption model" is clearly a cost optimization design principle. looks like im done using this site to study!!!
number 52 answer is d
just started preparing for my exam , and this site is so much help
question 35 is incorrect, the correct answer is c, it even states so: explanation: when a vm is infected with ransomware, you should not restore the vm to the infected vm. this is because the ransomware will still be present on the vm, and it will encrypt the files again. you should also not restore the vm to any vm within the companys subscription. this is because the ransomware could spread to other vms in the subscription. the best way to restore a vm that is infected with ransomware is to restore it to a new azure vm. this will ensure that the ransomware is not present on the new vm.
i would like to take psm1 exam.
cbd and pdb are key to the database
the purchase and download process is very much streamlined. the xengine application is very nice and user-friendly but there is always room for improvement.
please upload p_sapea_2023
anyone use this? the question dont seem to follow other formats and terminology i have been studying im getting worried
good questions
hello are these questions valid for ms-102
some questions are wrongly answered but its good nonetheless