PMI Certified Associate in Project Management (-100) PMI-100 Dumps in PDF

Free PMI PMI-100 Real Questions (page: 38)

Activity cost estimates and the project schedule are inputs to which Project Cost Management process?

  1. Estimate Costs
  2. Control Costs
  3. Plan Cost Management
  4. Determine Budget

Answer(s): D

Explanation:

7.2.3.1 Activity Cost Estimates
Activity cost estimates are quantitative assessments of the probable costs required to complete project work. Cost estimates can be presented in summary form or in detail. Costs are estimated for all resources that are applied to the activity cost estimate. This includes, but is not limited to, direct labor, materials, equipment, services, facilities, information technology, and special categories such as cost of financing (including interest charges), an inflation allowance, exchange rates, or a cost contingency reserve. Indirect costs, if they are included in the project estimate, can be included at the activity level or at higher levels.

Process: 7.3 Determine Budget
Definition: The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline.
Key Benefit: The key benefit of this process is that it determines the cost baseline against which project performance can be monitored and controlled.

Inputs
1. Cost management plan
2. Scope baseline
3. Activity cost estimates
4. Basis of estimates
5. Project schedule
6. Resource calendars
7. Risk register

8. Agreements
9. Organizational process assets

Tools & Techniques
1. Cost aggregation
2. Reserve analysis
3. Expert judgment
4. Historical relationships
5. Funding limit reconciliation

Outputs
1. Cost baseline
2. Project funding requirements
3. Project documents updates



In project management, a temporary project can be:

  1. Completed without planning
  2. A routine business process
  3. Long in duration
  4. Ongoing to produce goods

Answer(s): C



Which document in the project management plan can be updated in the Plan Procurement Management process?

  1. Budget estimates
  2. Risk matrix
  3. Requirements documentation
  4. Procurement documents

Answer(s): C

Explanation:

Process: 12.1 Plan Procurement Management
Definition: The process of documenting project procurement decisions, specifying the approach, and identifying potential sellers.
Key Benefit: The key benefit of this process is that it determines whether to acquire outside support, and if so, what to acquire, how to acquire it, how much is needed, and when to acquire it.

Inputs
1. Project management plan
2. Requirements documentation
3. Risk register
4. Activity resource requirements
5. Project schedule

6. Activity cost estimates
7. Stakeholder register
8. Enterprise environmental factors
9. Organizational process assets

Tools & Techniques
1. Make-or-buy analysis
2. Expert judgment
3. Market research
4. Meetings

Outputs
1. Procurement management plan
2. Procurement statement of work
3. Procurement documents
4. Source selection criteria
5. Make-or-buy decisions
6. Change requests
7. Project documents updates



Which type of probability distribution is used to represent uncertain events such as the outcome of a test or a possible scenario in a decision tree?

  1. Uniform
  2. Continuous
  3. Discrete
  4. Linear

Answer(s): C

Explanation:

Decision Tree Analysis. A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.

- Can only be used with discrete data.



Which change request is an intentional activity that realigns the performance of the project work with the project management plan?

  1. Update
  2. Preventive action
  3. Defect repair
  4. Corrective action

Answer(s): D

Explanation:

4.3.3.3 Change Requests
A change request is a formal proposal to modify any document, deliverable, or baseline. An approved change request will replace the associated document, deliverable, or baseline and may result in an update to other parts of the project management plan. When issues are found while project work is being performed, change requests are submitted, which may modify project policies or procedures, project scope, project cost or budget, project schedule, or project quality. Other change requests cover the needed preventive or corrective actions to forestall negative impact later in the project. Requests for a change can be direct or indirect, externally or internally initiated, and can be optional or legally/contractually mandated, and may include:

Corrective action—An intentional activity that realigns the performance of the project work with the project management plan;
Preventive action—An intentional activity that ensures the future performance of the project work is aligned with the project management plan;
Defect repair—An intentional activity to modify a nonconforming product or product component;
Updates—Changes to formally controlled project documents, plans, etc., to reflect modified or additional ideas or content.



Share your comments for PMI PMI-100 exam with other users:

B
BigMouthDog
1/22/2022 8:17:00 PM

hi team just want to know if there is any update version of the exam 350-401

F
francesco
10/30/2023 11:08:00 AM

helpful on 2017 scrum guide

A
Amitabha Roy
10/5/2023 3:16:00 AM

planning to attempt for the exam.

P
Prem Yadav
7/29/2023 6:20:00 AM

pleaseee upload

A
Ahmed Hashi
7/6/2023 5:40:00 PM

thanks ly so i have information cia

M
mansi
5/31/2023 7:58:00 AM

hello team, i need sap qm dumps for practice

J
Jamil aljamil
12/4/2023 4:47:00 AM

it’s good but not senatios based

C
Cath
10/10/2023 10:19:00 AM

q.119 - the correct answer is b - they are not captured in an update set as theyre data.

P
P
1/6/2024 11:22:00 AM

good matter

S
surya
7/30/2023 2:02:00 PM

please upload c_sacp_2308

S
Sasuke
7/11/2023 10:30:00 PM

please upload the dump. thanks very much !!

V
V
7/4/2023 8:57:00 AM

good questions

T
TTB
8/22/2023 5:30:00 AM

hi, could you please update the latest dump version

T
T
7/28/2023 9:06:00 PM

this question is keep repeat : you are developing a sales application that will contain several azure cloud services and handle different components of a transaction. different cloud services will process customer orders, billing, payment, inventory, and shipping. you need to recommend a solution to enable the cloud services to asynchronously communicate transaction information by using xml messages. what should you include in the recommendation?

G
Gurgaon
9/28/2023 4:35:00 AM

great questions

W
wasif
10/11/2023 2:22:00 AM

its realy good

S
Shubhra Rathi
8/26/2023 1:12:00 PM

oracle 1z0-1059-22 dumps

L
Leo
7/29/2023 8:48:00 AM

please share me the pdf..

A
AbedRabbou Alaqabna
12/18/2023 3:10:00 AM

q50: which two functions can be used by an end user when pivoting an interactive report? the correct answer is a, c because we do not have rank in the function pivoting you can check in the apex app

R
Rohan Limaye
12/30/2023 8:52:00 AM

best to practice

A
Aparajeeta
10/13/2023 2:42:00 PM

so far it is good

V
Vgf
7/20/2023 3:59:00 PM

please provide me the dump

D
Deno
10/25/2023 1:14:00 AM

i failed the cisa exam today. but i have found all the questions that were on the exam to be on this site.

C
CiscoStudent
11/15/2023 5:29:00 AM

in question 272 the right answer states that an autonomous acces point is "configured and managed by the wlc" but this is not what i have learned in my ccna course. is this a mistake? i understand that lightweight aps are managed by wlc while autonomous work as standalones on the wlan.

P
pankaj
9/28/2023 4:36:00 AM

it was helpful

U
User123
10/8/2023 9:59:00 AM

good question

V
vinay
9/4/2023 10:23:00 AM

really nice

U
Usman
8/28/2023 10:07:00 AM

please i need dumps for isc2 cybersecuity

Q
Q44
7/30/2023 11:50:00 AM

ans is coldline i think

A
Anuj
12/21/2023 1:30:00 PM

very helpful

G
Giri
9/13/2023 10:31:00 PM

can you please provide dumps so that it helps me more

A
Aaron
2/8/2023 12:10:00 AM

thank you for providing me with the updated question and answers. this version has all the questions from the exam. i just saw them in my exam this morning. i passed my exam today.

S
Sarwar
12/21/2023 4:54:00 PM

how i can see exam questions?

C
Chengchaone
9/11/2023 10:22:00 AM

can you please upload please?

AI Tutor 👋 I’m here to help!