Activity cost estimates and the project schedule are inputs to which Project Cost Management process?
Answer(s): D
7.2.3.1 Activity Cost EstimatesActivity cost estimates are quantitative assessments of the probable costs required to complete project work. Cost estimates can be presented in summary form or in detail. Costs are estimated for all resources that are applied to the activity cost estimate. This includes, but is not limited to, direct labor, materials, equipment, services, facilities, information technology, and special categories such as cost of financing (including interest charges), an inflation allowance, exchange rates, or a cost contingency reserve. Indirect costs, if they are included in the project estimate, can be included at the activity level or at higher levels.Process: 7.3 Determine BudgetDefinition: The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline.Key Benefit: The key benefit of this process is that it determines the cost baseline against which project performance can be monitored and controlled.Inputs1. Cost management plan2. Scope baseline3. Activity cost estimates4. Basis of estimates5. Project schedule6. Resource calendars7. Risk register 8. Agreements9. Organizational process assetsTools & Techniques1. Cost aggregation2. Reserve analysis3. Expert judgment4. Historical relationships5. Funding limit reconciliationOutputs1. Cost baseline2. Project funding requirements3. Project documents updates
In project management, a temporary project can be:
Answer(s): C
Which document in the project management plan can be updated in the Plan Procurement Management process?
Process: 12.1 Plan Procurement ManagementDefinition: The process of documenting project procurement decisions, specifying the approach, and identifying potential sellers.Key Benefit: The key benefit of this process is that it determines whether to acquire outside support, and if so, what to acquire, how to acquire it, how much is needed, and when to acquire it.Inputs1. Project management plan2. Requirements documentation3. Risk register4. Activity resource requirements5. Project schedule 6. Activity cost estimates7. Stakeholder register8. Enterprise environmental factors9. Organizational process assetsTools & Techniques1. Make-or-buy analysis2. Expert judgment3. Market research4. MeetingsOutputs1. Procurement management plan2. Procurement statement of work3. Procurement documents4. Source selection criteria5. Make-or-buy decisions6. Change requests7. Project documents updates
Which type of probability distribution is used to represent uncertain events such as the outcome of a test or a possible scenario in a decision tree?
Decision Tree Analysis. A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.- Can only be used with discrete data.
Which change request is an intentional activity that realigns the performance of the project work with the project management plan?
4.3.3.3 Change RequestsA change request is a formal proposal to modify any document, deliverable, or baseline. An approved change request will replace the associated document, deliverable, or baseline and may result in an update to other parts of the project management plan. When issues are found while project work is being performed, change requests are submitted, which may modify project policies or procedures, project scope, project cost or budget, project schedule, or project quality. Other change requests cover the needed preventive or corrective actions to forestall negative impact later in the project. Requests for a change can be direct or indirect, externally or internally initiated, and can be optional or legally/contractually mandated, and may include:Corrective action—An intentional activity that realigns the performance of the project work with the project management plan;Preventive action—An intentional activity that ensures the future performance of the project work is aligned with the project management plan;Defect repair—An intentional activity to modify a nonconforming product or product component;Updates—Changes to formally controlled project documents, plans, etc., to reflect modified or additional ideas or content.
Share your comments for PMI PMI-100 exam with other users:
hi team just want to know if there is any update version of the exam 350-401
helpful on 2017 scrum guide
planning to attempt for the exam.
pleaseee upload
thanks ly so i have information cia
hello team, i need sap qm dumps for practice
it’s good but not senatios based
q.119 - the correct answer is b - they are not captured in an update set as theyre data.
good matter
please upload c_sacp_2308
please upload the dump. thanks very much !!
good questions
hi, could you please update the latest dump version
this question is keep repeat : you are developing a sales application that will contain several azure cloud services and handle different components of a transaction. different cloud services will process customer orders, billing, payment, inventory, and shipping. you need to recommend a solution to enable the cloud services to asynchronously communicate transaction information by using xml messages. what should you include in the recommendation?
great questions
its realy good
oracle 1z0-1059-22 dumps
please share me the pdf..
q50: which two functions can be used by an end user when pivoting an interactive report? the correct answer is a, c because we do not have rank in the function pivoting you can check in the apex app
best to practice
so far it is good
please provide me the dump
i failed the cisa exam today. but i have found all the questions that were on the exam to be on this site.
in question 272 the right answer states that an autonomous acces point is "configured and managed by the wlc" but this is not what i have learned in my ccna course. is this a mistake? i understand that lightweight aps are managed by wlc while autonomous work as standalones on the wlan.
it was helpful
good question
really nice
please i need dumps for isc2 cybersecuity
ans is coldline i think
very helpful
can you please provide dumps so that it helps me more
thank you for providing me with the updated question and answers. this version has all the questions from the exam. i just saw them in my exam this morning. i passed my exam today.
how i can see exam questions?
can you please upload please?