Which document defines how a project is executed, monitored and controlled, and closed?
Answer(s): C
4.2.3.1 Project Management PlanThe project management plan is the document that describes how the project will be executed, monitored, and controlled. It integrates and consolidates all of the subsidiary plans and baselines from the planning processes. Project baselines include, but are not limited to:Scope baseline (Section 5.4.3.1), Schedule baseline (Section 6.6.3.1), and Cost baseline (Section 7.3.3.1).Subsidiary plans include, but are not limited to:Scope management plan (Section 5.1.3.1), Requirements management plan (Section 5.1.3.2), Schedule management plan (Section 6.1.3.1), Cost management plan (Section 7.1.3.1),Quality management plan (Section 8.1.3.1), Process improvement plan (Section 8.1.3.2),Human resource management plan (Section 9.1.3.1), Communications management plan (Section 10.1.3.1), Risk management plan (Section 11.1.3.1), Procurement management plan (Section 12.1.3.1), and Stakeholder management plan (Section 13.2.3.1).Among other things, the project management plan may also include the following:Life cycle selected for the project and the processes that will be applied to each phase; Details of the tailoring decisions specified by the project management team as follows:○ Project management processes selected by the project management team,○ Level of implementation for each selected process,○ Descriptions of the tools and techniques to be used for accomplishing those processes, and○ Description of how the selected processes will be used to manage the specific project, including the dependencies and interactions among those processes and the essential inputs and outputs.Description of how work will be executed to accomplish the project objectives;Change management plan that documents how changes will be monitored and controlled; Configuration management plan that documents how Configuration management will be performed; Description of how the integrity of the project baselines will be maintained;Requirements and techniques for communication among stakeholders; andKey management reviews for content, the extent of, and timing to address, open issues and pending decisions.The project management plan may be either summary level or detailed, and may be composed of one or more subsidiary plans. Each of the subsidiary plans is detailed to the extent required by the specific project. Once the project management plan is baselined, it may only be changed when a change request is generated and approved through the Perform Integrated Change Control process.
Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a typical project progresses?
Which tool or technique is used in the Plan Scope Management process?
Answer(s): D
5.1.2.1 Expert JudgmentExpert judgment refers to input received from knowledgeable and experienced parties. Expertise may be provided by any group or person with specialized education, knowledge, skill, experience, or training in developing scope management plans.Process: 5.1 Plan Scope ManagementDefinition: The process of creating a scope management plan that documents how the project scope will be defined, validated, and controlled.Key Benefit: The key benefit of this process is that it provides guidance and direction on how scope will be managed throughout the project.Inputs1. Project management plan2. Project charter3. Enterprise environmental factors4. Organizational process assetsTools & Techniques1. Expert judgment2. MeetingsOutputs1. Scope management plan2. Requirements management plan
Which tool or technique is an examination of industry and specific vendor capabilities?
Answer(s): B
12.1.2.3 Market ResearchMarket research includes examination of industry and specific vendor capabilities. Procurement teams may leverage information gained at conferences, online reviews and a variety of sources to identify market capabilities.The team may also refine particular procurement objectives to leverage maturing technologies while balancing risks associated with the breadth of vendors who can provide the materials or services desired.
An input used in developing the communications management plan is:
10.1.3.1 Communications Management PlanThe communications management plan is a component of the project management plan that describes how project communications will be planned, structured, monitored, and controlled. The plan contains the following information:Stakeholder communication requirements;Information to be communicated, including language, format, content, and level of detail; Reason for the distribution of that information;Time frame and frequency for the distribution of required information and receipt of acknowledgment or response, if applicable;Person responsible for communicating the information;Person responsible for authorizing release of confidential information; Person or groups who will receive the information;Methods or technologies used to convey the information, such as memos, e-mail, and/or press releases; Resources allocated for communication activities, including time and budget;Escalation process identifying time frames and the management chain (names) for escalation of issues that cannot be resolved at a lower staff level;Method for updating and refining the communications management plan as the project progresses and develops;Glossary of common terminology;Flow charts of the information flow in the project, workflows with possible sequence of authorization, list of reports, and meeting plans, etc.; andCommunication constraints usually derived from a specific legislation or regulation, technology, and organizational policies, etc.The communications management plan can also include guidelines and templates for project status meetings, project team meetings, e-meetings, and e-mail messages. The use of a project website and project management software can also be included if these are to be used in the project.
Share your comments for PMI PMI-100 exam with other users:
very helpful
thank you for these questions. it helped a lot.
how do i get the h12-724 dumps
nice data dumps
answers are correct
good explanation
hi team just want to know if there is any update version of the exam 350-401
helpful on 2017 scrum guide
planning to attempt for the exam.
pleaseee upload
thanks ly so i have information cia
hello team, i need sap qm dumps for practice
it’s good but not senatios based
q.119 - the correct answer is b - they are not captured in an update set as theyre data.
good matter
please upload c_sacp_2308
please upload the dump. thanks very much !!
good questions
hi, could you please update the latest dump version
this question is keep repeat : you are developing a sales application that will contain several azure cloud services and handle different components of a transaction. different cloud services will process customer orders, billing, payment, inventory, and shipping. you need to recommend a solution to enable the cloud services to asynchronously communicate transaction information by using xml messages. what should you include in the recommendation?
great questions
its realy good
oracle 1z0-1059-22 dumps
please share me the pdf..
q50: which two functions can be used by an end user when pivoting an interactive report? the correct answer is a, c because we do not have rank in the function pivoting you can check in the apex app
best to practice
so far it is good
please provide me the dump
i failed the cisa exam today. but i have found all the questions that were on the exam to be on this site.
in question 272 the right answer states that an autonomous acces point is "configured and managed by the wlc" but this is not what i have learned in my ccna course. is this a mistake? i understand that lightweight aps are managed by wlc while autonomous work as standalones on the wlan.
it was helpful
good question
really nice
please i need dumps for isc2 cybersecuity