PMI Certified Associate in Project Management (-100) PMI-100 Dumps in PDF

Free PMI PMI-100 Real Questions (page: 5)

A project manager providing information to the right audience, in the right format, at the right time is an example of which type of communication?

  1. Efficient
  2. Effective
  3. Push
  4. Pull

Answer(s): B

Explanation:

On most projects, communication planning is performed very early, such as during project management plan development. This allows appropriate resources, such as time and budget, to be allocated to communication activities.
Effective communication means that the information is provided in the right format, at the right time, to the right audience, and with the right impact. Efficient communication means providing only the information that is needed.



Scope, schedule, and cost parameters are integrated in the:

  1. Performance measurement baseline.
  2. Analysis of project forecasts.
  3. Summary of changes approved in a period.
  4. Analysis of past performance.

Answer(s): A

Explanation:

Performance Measurement Baseline (PMB). An approved, integrated scope-schedule-cost plan for the project work against which project execution is compared to measure and manage performance. The PMB includes contingency reserve, but excludes management reserve.



A project in which the scope, time, and cost of delivery are determined as early as possible is following a life cycle that is:

  1. Adaptive
  2. Predictive
  3. Incremental
  4. Iterative

Answer(s): B

Explanation:

2.4.2.2 Predictive Life Cycles
Predictive life cycles (also known as fully plan-driven) are ones in which the project scope, and the time and cost required to deliver that scope, are determined as early in the project life cycle as practically possible. As shown in Figure 2-13, these projects proceed through a series of sequential or overlapping phases, with each phase generally focusing on a subset of project activities and project management processes. The work performed in each phase is usually different in nature to that in the preceding and subsequent phases, therefore, the makeup and skills required of the project team may vary from phase to phase.



What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the earned value (EV) is $50?

  1. 0.50
  2. 0.67
  3. 1.50
  4. 2.00

Answer(s): A

Explanation:

CV = EV - AC CPI = EV / AC SV = EV - PV SPI = EV / PV



Which item is an input to the Define Activities process?

  1. Schedule data
  2. Activity list
  3. Risk register
  4. Scope baseline

Answer(s): D

Explanation:

5.4.3.1 Scope Baseline
The scope baseline is the approved version of a scope statement, work breakdown structure (WBS), and its associated WBS dictionary, that can be changed only through formal change control procedures and is used as a basis for comparison. It is a component of the project management plan. Components of the scope baseline include:
Project scope statement. The project scope statement includes the description of the project scope, major deliverables, assumptions, and constraints.
WBS. The WBS is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables. Each descending level of the WBS represents an increasingly detailed definition of the project work. The WBS is finalized by assigning each work package to a control account and establishing a unique identifier for that work package from a code of accounts. These identifiers provide a structure for hierarchical summation of costs, schedule, and resource information. A control account is a management control point where scope, budget, actual cost, and schedule are integrated and compared to the earned value for performance measurement. Control accounts are placed at selected management points in the WBS. Each control account may include one or more work packages, but each of the work packages should be associated with only one control account. A control account may include one or more planning packages. A planning package is a work breakdown structure component below the control account with known work content but without detailed schedule activities.
WBS dictionary. The WBS dictionary is a document that provides detailed deliverable, activity, and scheduling information about each component in the WBS. The WBS dictionary is a document that supports the WBS. Information in the WBS dictionary may include, but is not limited to:
○ Code of account identifier,
○ Description of work,
○ Assumptions and constraints,
○ Responsible organization,
○ Schedule milestones,
○ Associated schedule activities,
○ Resources required,
○ Cost estimates,
○ Quality requirements,
○ Acceptance criteria,
○ Technical references, and
○ Agreement information

Process: 6.2 Define Activities
Definition: The process of identifying and documenting the specific actions to be performed to produce the project deliverables.
Key Benefit: The key benefit of this process is to break down work packages into activities that provide a basis for estimating, scheduling, executing, monitoring, and controlling the project work.
Inputs
1. Schedule management plan
2. Scope baseline
3. Enterprise environmental factors
4. Organizational process assets

Tools & Techniques
1. Decomposition
2. Rolling wave planning
3. Expert judgment

Outputs
1. Activity list
2. Activity attributes
3. Milestone list



Share your comments for PMI PMI-100 exam with other users:

K
Kaleemullah
12/31/2023 1:35:00 AM

great support to appear for exams

B
Bsmaind
8/20/2023 9:26:00 AM

useful dumps

B
Blessious Phiri
8/13/2023 8:37:00 AM

making progress

N
Nabla
9/17/2023 10:20:00 AM

q31 answer should be d i think

V
vladputin
7/20/2023 5:00:00 AM

is this real?

N
Nick W
9/29/2023 7:32:00 AM

q10: c and f are also true. q11: this is outdated. you no longer need ownership on a pipe to operate it

N
Naveed
8/28/2023 2:48:00 AM

good questions with simple explanation

C
cert
9/24/2023 4:53:00 PM

admin guide (windows) respond to malicious causality chains. when the cortex xdr agent identifies a remote network connection that attempts to perform malicious activity—such as encrypting endpoint files—the agent can automatically block the ip address to close all existing communication and block new connections from this ip address to the endpoint. when cortex xdrblocks an ip address per endpoint, that address remains blocked throughout all agent profiles and policies, including any host-firewall policy rules. you can view the list of all blocked ip addresses per endpoint from the action center, as well as unblock them to re-enable communication as appropriate. this module is supported with cortex xdr agent 7.3.0 and later. select the action mode to take when the cortex xdr agent detects remote malicious causality chains: enabled (default)—terminate connection and block ip address of the remote connection. disabled—do not block remote ip addresses. to allow specific and known s

Y
Yves
8/29/2023 8:46:00 PM

very inciting

M
Miguel
10/16/2023 11:18:00 AM

question 5, it seems a instead of d, because: - care plan = case - patient = person account - product = product2;

B
Byset
9/25/2023 12:49:00 AM

it look like real one

D
Debabrata Das
8/28/2023 8:42:00 AM

i am taking oracle fcc certification test next two days, pls share question dumps

N
nITA KALE
8/22/2023 1:57:00 AM

i need dumps

C
CV
9/9/2023 1:54:00 PM

its time to comptia sec+

S
SkepticReader
8/1/2023 8:51:00 AM

question 35 has an answer for a different question. i believe the answer is "a" because it shut off the firewall. "0" in registry data means that its false (aka off).

N
Nabin
10/16/2023 4:58:00 AM

helpful content

B
Blessious Phiri
8/15/2023 3:19:00 PM

oracle 19c is complex db

S
Sreenivas
10/24/2023 12:59:00 AM

helpful for practice

L
Liz
9/11/2022 11:27:00 PM

support team is fast and deeply knowledgeable. i appreciate that a lot.

N
Namrata
7/15/2023 2:22:00 AM

helpful questions

L
lipsa
11/8/2023 12:54:00 PM

thanks for question

E
Eli
6/18/2023 11:27:00 PM

the software is provided for free so this is a big change. all other sites are charging for that. also that fucking examtopic site that says free is not free at all. you are hit with a pay-wall.

O
open2exam
10/29/2023 1:14:00 PM

i need exam questions nca 6.5 any help please ?

G
Gerald
9/11/2023 12:22:00 PM

just took the comptia cybersecurity analyst (cysa+) - wished id seeing this before my exam

R
ryo
9/10/2023 2:27:00 PM

very helpful

J
Jamshed
6/20/2023 4:32:00 AM

i need this exam

R
Roberto Capra
6/14/2023 12:04:00 PM

nice questions... are these questions the same of the exam?

S
Synt
5/23/2023 9:33:00 PM

need to view

V
Vey
5/27/2023 12:06:00 AM

highly appreciate for your sharing.

T
Tshepang
8/18/2023 4:41:00 AM

kindly share this dump. thank you

J
Jay
9/26/2023 8:00:00 AM

link plz for download

L
Leo
10/30/2023 1:11:00 PM

data quality oecd

B
Blessious Phiri
8/13/2023 9:35:00 AM

rman is one good recovery technology

D
DiligentSam
9/30/2023 10:26:00 AM

need it thx

AI Tutor 👋 I’m here to help!