Which process is conducted from project inception through completion and is ultimately the responsibility of the project manager?

  1. Control Quality
  2. Monitor and Control Project Work
  3. Control Scope
  4. Perform Integrated Change Control

Answer(s): D

Explanation:

Process: 4.5 Perform Integrated Change Control
Definition: Perform Integrated Change Control is the process of reviewing all change requests; approving changes and managing changes to deliverables, organizational process assets, project documents, and the project management plan; and communicating their disposition. It reviews all requests for changes or modifications to project documents, deliverables, baselines, or the project management plan and approves or rejects the changes.
Key Benefit: The key benefit of this process is that it allows for documented changes within the project to be considered in an integrated fashion while reducing project risk, which often arises from changes made without consideration to the overall project objectives or plans.

Inputs
1. Project management plan
2. Work performance reports
3. Change requests
4. Enterprise environmental factors
5. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Meetings
3. Change control tools

Outputs

1. Approved change requests
2. Change log
3. Project management plan updates
4. Project documents updates



Project management processes ensure the:

  1. alignment with organizational strategy
  2. efficient means to achieve the project objectives
  3. performance of the project team
  4. effective flow of the project throughout its life cycle

Answer(s): D

Explanation:

Project management processes. These processes ensure the effective flow of the project throughout its life cycle. These processes encompass the tools and techniques involved in applying the skills and capabilities described in the Knowledge Areas (Sections 4 through 13)



An element of the modern quality management approach used to achieve compatibility with the International Organization for Standardization (ISO) is known as:

  1. Forecasting,
  2. Brainstorming.
  3. Historical databases.
  4. Cost of quality.

Answer(s): D

Explanation:

Cost of quality (COQ). Cost of quality refers to the total cost of the conformance work and the nonconformance work that should be done as a compensatory effort because, on the first attempt to perform that work, the potential exists that some portion of the required work effort may be done or has been done incorrectly. The costs for quality work may be incurred throughout the deliverable’s life cycle.
For example, decisions made by the project team can impact the operational costs associated with using a completed deliverable. Post-project quality costs may be incurred because of product returns, warranty claims, and recall campaigns. Therefore, because of the temporary nature of projects and the potential benefits that may be derived from reducing the post-project cost of quality, sponsoring organizations may choose to invest in product quality improvement. These investments generally are made in the areas of conformance work that act to prevent defects or act to mitigate the costs of defects by inspecting out nonconforming units.



Which items are components of a project management plan?

  1. Change management plan, process improvement plan, and scope management plan
  2. Agreements, procurement management plan, and work performance information
  3. Schedule management plan, project schedule, and resource calendars
  4. Scope baseline, project statement of work, and requirements traceability matrix

Answer(s): A



Which project document is updated in the Control Stakeholder Engagement process?

  1. Project reports
  2. Issue log
  3. Lessons learned documentation
  4. Work performance information

Answer(s): B

Explanation:

13.4.1.2 Issue Log
Described in Section 13.3.3.1. The issue log is updated as new issues are identified and current issues are resolved.
9.4.1.4 Issue Log
Issues arise in the course of managing the project team. An issue log can be used to document and monitor who is responsible for resolving specific issues by a target date.

Process: 13.4 Control Stakeholder Engagement
Definition: The process of monitoring overall project stakeholder relationships and adjusting strategies and plans for engaging stakeholders.
Key Benefit: The key benefit of this process is that it will maintain or increase the efficiency and effectiveness of stakeholder engagement activities as the project evolves and its environment changes.

Inputs
1. Project management plan
2. Issue log
3. Work performance data
4. Project documents

Tools & Techniques
1. Information management systems
2. Expert judgment
3. Meetings

Outputs
1. Work performance information
2. Change requests
3. Project management plan updates
4. Project documents updates
5. Organizational process assets updates



Share your comments for PMI PMI-002 exam with other users:

R
Raj
9/12/2023 3:49:00 PM

can you please upload the dump again

C
Christian Klein
6/23/2023 1:32:00 PM

is it legit questions from sap certifications ?

A
anonymous
1/12/2024 3:34:00 PM

question 16 should be b (changing the connector settings on the monitor) pc and monitor were powered on. the lights on the pc are on indicating power. the monitor is showing an error text indicating that it is receiving power too. this is a clear sign of having the wrong input selected on the monitor. thus, the "connector setting" needs to be switched from hdmi to display port on the monitor so it receives the signal from the pc, or the other way around (display port to hdmi).

N
NSPK
1/18/2024 10:26:00 AM

q 10. ans is d (in the target org: open deployment settings, click edit next to the source org. select allow inbound changes and save

M
mohamed abdo
9/1/2023 4:59:00 AM

very useful

T
Tom
3/18/2022 8:00:00 PM

i purchased this exam dumps from another website with way more questions but they were all invalid and outdate. this exam dumps was right to the point and all from recent exam. it was a hard pass.

E
Edrick GOP
10/24/2023 6:00:00 AM

it was a good experience and i got 90% in the 200-901 exam.

A
anonymous
8/10/2023 2:28:00 AM

hi please upload this

B
Bakir
7/6/2023 7:24:00 AM

please upload it

A
Aman
6/18/2023 1:27:00 PM

really need this dump. can you please help.

N
Neela Para
1/8/2024 6:39:00 PM

really good and covers many areas explaining the answer.

K
Karan Patel
8/15/2023 12:51:00 AM

yes, can you please upload the exam?

N
NISHAD
11/7/2023 11:28:00 AM

how many questions are there in these dumps?

P
Pankaj
7/3/2023 3:57:00 AM

hi team, please upload this , i need it.

D
DN
9/4/2023 11:19:00 PM

question 14 - run terraform import: this is the recommended best practice for bringing manually created or destroyed resources under terraform management. you use terraform import to associate an existing resource with a terraform resource configuration. this ensures that terraform is aware of the resource, and you can subsequently manage it with terraform.

Z
Zhiguang
8/19/2023 11:37:00 PM

please upload dump. thanks in advance.

D
deedee
12/23/2023 5:51:00 PM

great great

A
Asad Khan
11/1/2023 3:10:00 AM

answer 16 should be b your organizational policies require you to use virtual machines directly

S
Sale Danasabe
10/24/2023 5:21:00 PM

the question are kind of tricky of you didnt get the hnag on it.

L
Luis
11/16/2023 1:39:00 PM

can anyone tell me if this is for rhel8 or rhel9?

H
hik
1/19/2024 1:47:00 PM

good content

B
Blessious Phiri
8/15/2023 2:18:00 PM

pdb and cdb are critical to the database

Z
Zuned
10/22/2023 4:39:00 AM

till 104 questions are free, lets see how it helps me in my exam today.

M
Muhammad Rawish Siddiqui
12/3/2023 12:11:00 PM

question # 56, answer is true not false.

A
Amaresh Vashishtha
8/27/2023 1:33:00 AM

i would be requiring dumps to prepare for certification exam

A
Asad
9/8/2023 1:01:00 AM

very helpful

B
Blessious Phiri
8/13/2023 3:10:00 PM

control file is the heart of rman backup

S
Senthil
9/19/2023 5:47:00 AM

hi could you please upload the ibm c2090-543 dumps

H
Harry
6/27/2023 7:20:00 AM

appriciate if you could upload this again

A
Anonymous
7/10/2023 4:10:00 AM

please upload the dump

R
Raja
6/20/2023 5:30:00 AM

i found some questions answers mismatch with explanation answers. please properly update

D
Doora
11/30/2023 4:20:00 AM

nothing to mention

D
deally
1/19/2024 3:41:00 PM

knowable questions

S
Sonia
7/23/2023 4:03:00 PM

very helpfull

AI Tutor 👋 I’m here to help!