PMI Certified Associate in Project Management (-100) PMI-002 Dumps in PDF

Free PMI PMI-002 Real Questions (page: 42)

A project manager should communicate to stakeholders about resolved project issues by updating the:

  1. project records
  2. project reports
  3. stakeholder notifications
  4. stakeholder register

Answer(s): C

Explanation:

10.2.3.4 Organizational Process Assets Updates
The organizational process assets, which may be updated include, but are not limited to:

Stakeholder notifications. Information may be provided to stakeholders about resolved issues, approved changes, and general project status.

Project reports. Formal and informal project reports describe project status and include lessons learned, issue logs, project closure reports, and outputs from other Knowledge Areas (Sections 4-13).
Project presentations. The project team provides information formally or informally to any or all of the project stakeholders. The information and presentation method should be relevant to the needs of the audience.
Project records. Project records may include correspondence, memos, meeting minutes, and other documents describing the project. This information should, to the extent possible and appropriate, be maintained in an organized manner. Project team members can also maintain records in a project notebook or register, which could be physical or electronic.
Feedback from stakeholders. Information received from stakeholders concerning project operations is distributed and used to modify or improve future performance of the project.
Lessons learned documentation. Documentation includes the causes of issues, reasoning behind the corrective action chosen, and other types of lessons learned about communications management. Lessons learned need to be documented and distributed so that it becomes part of the historical database for both the project and the performing organization.



Which Project Time Management process includes bottom-up estimating as a tool or technique?

  1. Estimate Activity Resources
  2. Sequence Activities
  3. Estimate Activity Durations
  4. Develop Schedule

Answer(s): A

Explanation:

Process: 6.4 Estimate Activity Resources
Definition: The process of estimating the type and quantities of material, human resources, equipment, or supplies required to perform each activity.
Key Benefit: The key benefit of this process is that it identifies the type, quantity, and characteristics of resources required to complete the activity which allows more accurate cost and duration estimates.

Inputs
1. Schedule management plan
2. Activity list
3. Activity attributes
4. Resource calendars

5. Risk register
6. Activity cost estimates
7. Enterprise environmental factors
8. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Alternative analysis
3. Published estimating data
4. Bottom-up estimating
5. Project management software

Outputs
1. Activity resource requirements
2. Resource breakdown structure
3. Project documents updates



Progressively elaborating high-level information into detailed plans is performed by the:

  1. project management office
  2. portfolio manager
  3. program manager
  4. project manager

Answer(s): D



An input to the Control Quality process is:

  1. Activity attributes
  2. Quality control measurements
  3. Enterprise environmental factors
  4. Deliverables

Answer(s): D

Explanation:

Process: 8.3 Control Quality
Definition: The process of monitoring and recording results of executing the quality activities to assess performance and recommend necessary changes.
Key Benefit: The key benefits of this process include: (1) identifying the causes of poor process or product quality and recommending and/or taking action to eliminate them; and (2) validating that project deliverables and work meet the requirements specified by key stakeholders necessary for final acceptance.

Inputs
1. Project management plan
2. Quality metrics
3. Quality checklists

4. Work performance data
5. Approved change requests
6. Deliverables
7. Project documents
8. Organizational process assets

Tools & Techniques
1. Seven basic quality tools
2. Statistical sampling
3. Inspection
4. Approved change requests review

Outputs
1. Quality control measurements
2. Validated changes
3. Verified deliverables
4. Work performance information
5. Change requests
6. Project management plan updates
7. Project documents updates
8. Organizational process assets updates



The chart below is an example of a:

  1. Responsibility assignment matrix (RAM)
  2. Work breakdown structure (WBS)
  3. RACI chart
  4. Requirements traceability matrix

Answer(s): D

Explanation:

5.2.3.2 Requirements Traceability Matrix
The requirements traceability matrix is a grid that links product requirements from their origin to the deliverables that satisfy them. The implementation of a requirements traceability matrix helps ensure that each requirement adds business value by linking it to the business and project objectives. It provides a means to track requirements throughout the project life cycle, helping to ensure that requirements approved in the requirements documentation are delivered at the end of the project. Finally, it provides a structure for managing changes to the product scope.
Tracing includes, but is not limited to, tracing requirements for the following:

Business needs, opportunities, goals, and objectives; Project objectives;
Project scope/WBS deliverables;

Product design; Product development;
Test strategy and test scenarios; and
High-level requirements to more detailed requirements.
Attributes associated with each requirement can be recorded in the requirements traceability matrix. These attributes help to define key information about the requirement. Typical attributes used in the requirements traceability matrix may include: a unique identifier, a textual description of the requirement, the rationale for inclusion, owner, source, priority, version, current status (such as active, cancelled, deferred, added, approved, assigned, completed), and status date. Additional attributes to ensure that the requirement has met stakeholders’ satisfaction may include stability, complexity, and acceptance criteria.



Share your comments for PMI PMI-002 exam with other users:

A
asad Raza
5/15/2023 5:38:00 AM

please upload this exam

R
Reeta
7/17/2023 5:22:00 PM

please upload the c_activate22 dump questions with answer

W
Wong
12/20/2023 11:34:00 AM

q10 - the answer should be a. if its c, the criteria will meet if either the prospect is not part of the suppression lists or if the job title contains vice president

D
david
12/12/2023 12:38:00 PM

this was on the exam as of 1211/2023

T
Tink
7/24/2023 9:23:00 AM

great for prep

J
Jaro
12/18/2023 3:12:00 PM

i think in question 7 the first answer should be power bi portal (not power bi)

9
9eagles
4/7/2023 10:04:00 AM

on question 10 and so far 2 wrong answers as evident in the included reference link.

T
Tai
8/28/2023 5:28:00 AM

wonderful material

V
VoiceofMidnight
12/29/2023 4:48:00 PM

i passed!! ...but barely! got 728, but needed 720 to pass. the exam hit me with labs right out of the gate! then it went to multiple choice. protip: study the labs!

A
A K
8/3/2023 11:56:00 AM

correct answer for question 92 is c -aws shield

N
Nitin Mindhe
11/27/2023 6:12:00 AM

great !! it is really good

B
BailleyOne
11/22/2023 1:45:00 AM

explanations for the answers are to the point.

P
patel
10/25/2023 8:17:00 AM

how can rea next

M
MortonG
10/19/2023 6:32:00 PM

question: 128 d is the wrong answer...should be c

J
Jayant
11/2/2023 3:15:00 AM

thanks for az 700 dumps

B
Bipul Mishra
12/14/2023 7:12:00 AM

thank you for this tableau dumps . it will helpfull for tableau certification

H
hello
10/31/2023 12:07:00 PM

good content

M
Matheus
9/3/2023 2:14:00 PM

just testing if the comments are real

Y
yenvti2@gmail.com
8/12/2023 7:56:00 PM

very helpful for exam preparation

M
Miguel
10/5/2023 12:16:00 PM

question 11: https://help.salesforce.com/s/articleview?id=sf.admin_lead_to_patient_setup_overview.htm&type=5

N
Noushin
11/28/2023 4:52:00 PM

i think the answer to question 42 is b not c

S
susan sandivore
8/28/2023 1:00:00 AM

thanks for the dump

A
Aderonke
10/31/2023 12:51:00 AM

fantastic assessments

P
Priscila
7/22/2022 9:59:00 AM

i find the xengine test engine simulator to be more fun than reading from pdf.

S
suresh
12/16/2023 10:54:00 PM

nice document

W
Wali
6/4/2023 10:07:00 PM

thank you for making the questions and answers intractive and selectable.

N
Nawaz
7/18/2023 1:10:00 AM

answers are correct?

D
das
6/23/2023 7:57:00 AM

can i belive this dump

S
Sanjay
10/15/2023 1:34:00 PM

great site to practice for sitecore exam

J
jaya
12/17/2023 8:36:00 AM

good for students

B
Bsmaind
8/20/2023 9:23:00 AM

nice practice dumps

K
kumar
11/15/2023 11:24:00 AM

nokia 4a0-114 dumps

V
Vetri
10/3/2023 12:59:00 AM

great content and wonderful to have the answers with explanation

R
Ranjith
8/21/2023 3:39:00 PM

for question #118, the answer is option c. the screen shot is showing the drop down, but the answer is marked incorrectly please update . thanks for sharing such nice questions.

AI Tutor 👋 I’m here to help!