Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?

  1. 100
  2. 120
  3. 1,000
  4. 1,200

Answer(s): A



Which stakeholder approves a project's result?

  1. Customer
  2. Sponsor
  3. Seller
  4. Functional manager

Answer(s): A



Which process involves determining, documenting, and managing stakeholders' needs and requirements to meet project objectives?

  1. Collect Requirements
  2. Plan Scope Management
  3. Define Scope
  4. Define Activities

Answer(s): A

Explanation:

Process: 5.2 Collect Requirements
Definition: The process of determining, documenting, and managing stakeholder needs and requirements to meet project objectives.
Key Benefit: The key benefit of this process is that it provides the basis for defining and managing the project scope including product scope.
Inputs
1. Scope management plan
2. Requirements management plan
3. Stakeholder management plan
4. Project charter
5. Stakeholder register

Tools & Techniques
1. Interviews
2. Focus groups
3. Facilitated workshops
4. Group creativity techniques
5. Group decision-making techniques
6. Questionnaires and surveys
7. Observations
8. Prototypes
9. Benchmarking
10. Context diagrams
11. Document analysis

Outputs
1. Requirements documentation
2. Requirements traceability matrix



Plan Communications Management develops an approach and plan for project communications based on stakeholders' needs and requirements and:

  1. Available organizational assets
  2. Project staff assignments
  3. Interpersonal skills
  4. Enterprise environmental factors

Answer(s): A

Explanation:

Process: 10.1 Plan Communications Management
Definition: The process of developing an appropriate approach and plan for project communications based on stakeholder’s information needs and requirements, and available organizational assets.
Key Benefit: The key benefit of this process is that it identifies and documents the approach to communicate most effectively and efficiently with stakeholders.

Inputs
1. Project management plan

2. Stakeholder register
3. Enterprise environmental factors
4. Organizational process assets

Tools & Techniques
1. Communication requirements analysis
2. Communication technology
3. Communication models
4. Communication methods
5. Meetings

Outputs
1. Communications management plan
2. Project documents updates



Perform Integrated Change Control is the process of:

  1. Reviewing, approving, and managing all change requests
  2. Facilitating change management, manuals, or automation tools
  3. Comparing actual results with planned results in order to expand or change a project
  4. Documenting changes according to the change control system by the change control board

Answer(s): A

Explanation:

Process: 4.5 Perform Integrated Change Control
Perform Integrated Change Control is the process of reviewing all change requests; approving changes and managing changes to deliverables, organizational process assets, project documents, and the project management plan; and communicating their disposition. It reviews all requests for changes or modifications to project documents, deliverables, baselines, or the project management plan and approves or rejects the changes.
Key Benefit: The key benefit of this process is that it allows for documented changes within the project to be considered in an integrated fashion while reducing project risk, which often arises from changes made without consideration to the overall project objectives or plans.

Inputs
1. Project management plan
2. Work performance reports
3. Change requests
4. Enterprise environmental factors
5. Organizational process assets

Tools & Techniques
1. Expert judgment
2. Meetings
3. Change control tools

Outputs
1. Approved change requests
2. Change log
3. Project management plan updates
4. Project documents updates



Share your comments for PMI PMI-002 exam with other users:

S
Shariq
7/28/2023 8:00:00 AM

how do i get the h12-724 dumps

A
adi
10/30/2023 11:51:00 PM

nice data dumps

E
EDITH NCUBE
7/25/2023 7:28:00 AM

answers are correct

R
Raja
6/20/2023 4:38:00 AM

good explanation

B
BigMouthDog
1/22/2022 8:17:00 PM

hi team just want to know if there is any update version of the exam 350-401

F
francesco
10/30/2023 11:08:00 AM

helpful on 2017 scrum guide

A
Amitabha Roy
10/5/2023 3:16:00 AM

planning to attempt for the exam.

P
Prem Yadav
7/29/2023 6:20:00 AM

pleaseee upload

A
Ahmed Hashi
7/6/2023 5:40:00 PM

thanks ly so i have information cia

M
mansi
5/31/2023 7:58:00 AM

hello team, i need sap qm dumps for practice

J
Jamil aljamil
12/4/2023 4:47:00 AM

it’s good but not senatios based

C
Cath
10/10/2023 10:19:00 AM

q.119 - the correct answer is b - they are not captured in an update set as theyre data.

P
P
1/6/2024 11:22:00 AM

good matter

S
surya
7/30/2023 2:02:00 PM

please upload c_sacp_2308

S
Sasuke
7/11/2023 10:30:00 PM

please upload the dump. thanks very much !!

V
V
7/4/2023 8:57:00 AM

good questions

T
TTB
8/22/2023 5:30:00 AM

hi, could you please update the latest dump version

T
T
7/28/2023 9:06:00 PM

this question is keep repeat : you are developing a sales application that will contain several azure cloud services and handle different components of a transaction. different cloud services will process customer orders, billing, payment, inventory, and shipping. you need to recommend a solution to enable the cloud services to asynchronously communicate transaction information by using xml messages. what should you include in the recommendation?

G
Gurgaon
9/28/2023 4:35:00 AM

great questions

W
wasif
10/11/2023 2:22:00 AM

its realy good

S
Shubhra Rathi
8/26/2023 1:12:00 PM

oracle 1z0-1059-22 dumps

L
Leo
7/29/2023 8:48:00 AM

please share me the pdf..

A
AbedRabbou Alaqabna
12/18/2023 3:10:00 AM

q50: which two functions can be used by an end user when pivoting an interactive report? the correct answer is a, c because we do not have rank in the function pivoting you can check in the apex app

R
Rohan Limaye
12/30/2023 8:52:00 AM

best to practice

A
Aparajeeta
10/13/2023 2:42:00 PM

so far it is good

V
Vgf
7/20/2023 3:59:00 PM

please provide me the dump

D
Deno
10/25/2023 1:14:00 AM

i failed the cisa exam today. but i have found all the questions that were on the exam to be on this site.

C
CiscoStudent
11/15/2023 5:29:00 AM

in question 272 the right answer states that an autonomous acces point is "configured and managed by the wlc" but this is not what i have learned in my ccna course. is this a mistake? i understand that lightweight aps are managed by wlc while autonomous work as standalones on the wlan.

P
pankaj
9/28/2023 4:36:00 AM

it was helpful

U
User123
10/8/2023 9:59:00 AM

good question

V
vinay
9/4/2023 10:23:00 AM

really nice

U
Usman
8/28/2023 10:07:00 AM

please i need dumps for isc2 cybersecuity

Q
Q44
7/30/2023 11:50:00 AM

ans is coldline i think

A
Anuj
12/21/2023 1:30:00 PM

very helpful

AI Tutor 👋 I’m here to help!