PMI Certified Associate in Project Management (-100) PMI-002 Dumps in PDF

Free PMI PMI-002 Real Questions (page: 38)

Activity cost estimates and the project schedule are inputs to which Project Cost Management process?

  1. Estimate Costs
  2. Control Costs
  3. Plan Cost Management
  4. Determine Budget

Answer(s): D

Explanation:

7.2.3.1 Activity Cost Estimates
Activity cost estimates are quantitative assessments of the probable costs required to complete project work. Cost estimates can be presented in summary form or in detail. Costs are estimated for all resources that are applied to the activity cost estimate. This includes, but is not limited to, direct labor, materials, equipment, services, facilities, information technology, and special categories such as cost of financing (including interest charges), an inflation allowance, exchange rates, or a cost contingency reserve. Indirect costs, if they are included in the project estimate, can be included at the activity level or at higher levels.

Process: 7.3 Determine Budget
Definition: The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline.
Key Benefit: The key benefit of this process is that it determines the cost baseline against which project performance can be monitored and controlled.

Inputs
1. Cost management plan
2. Scope baseline
3. Activity cost estimates
4. Basis of estimates
5. Project schedule
6. Resource calendars
7. Risk register

8. Agreements
9. Organizational process assets

Tools & Techniques
1. Cost aggregation
2. Reserve analysis
3. Expert judgment
4. Historical relationships
5. Funding limit reconciliation

Outputs
1. Cost baseline
2. Project funding requirements
3. Project documents updates



In project management, a temporary project can be:

  1. Completed without planning
  2. A routine business process
  3. Long in duration
  4. Ongoing to produce goods

Answer(s): C



Which document in the project management plan can be updated in the Plan Procurement Management process?

  1. Budget estimates
  2. Risk matrix
  3. Requirements documentation
  4. Procurement documents

Answer(s): C

Explanation:

Process: 12.1 Plan Procurement Management
Definition: The process of documenting project procurement decisions, specifying the approach, and identifying potential sellers.
Key Benefit: The key benefit of this process is that it determines whether to acquire outside support, and if so, what to acquire, how to acquire it, how much is needed, and when to acquire it.

Inputs
1. Project management plan
2. Requirements documentation
3. Risk register
4. Activity resource requirements
5. Project schedule

6. Activity cost estimates
7. Stakeholder register
8. Enterprise environmental factors
9. Organizational process assets

Tools & Techniques
1. Make-or-buy analysis
2. Expert judgment
3. Market research
4. Meetings

Outputs
1. Procurement management plan
2. Procurement statement of work
3. Procurement documents
4. Source selection criteria
5. Make-or-buy decisions
6. Change requests
7. Project documents updates



Which type of probability distribution is used to represent uncertain events such as the outcome of a test or a possible scenario in a decision tree?

  1. Uniform
  2. Continuous
  3. Discrete
  4. Linear

Answer(s): C

Explanation:

Decision Tree Analysis. A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty.

- Can only be used with discrete data.



Which change request is an intentional activity that realigns the performance of the project work with the project management plan?

  1. Update
  2. Preventive action
  3. Defect repair
  4. Corrective action

Answer(s): D

Explanation:

4.3.3.3 Change Requests
A change request is a formal proposal to modify any document, deliverable, or baseline. An approved change request will replace the associated document, deliverable, or baseline and may result in an update to other parts of the project management plan. When issues are found while project work is being performed, change requests are submitted, which may modify project policies or procedures, project scope, project cost or budget, project schedule, or project quality. Other change requests cover the needed preventive or corrective actions to forestall negative impact later in the project. Requests for a change can be direct or indirect, externally or internally initiated, and can be optional or legally/contractually mandated, and may include:

Corrective action—An intentional activity that realigns the performance of the project work with the project management plan;
Preventive action—An intentional activity that ensures the future performance of the project work is aligned with the project management plan;
Defect repair—An intentional activity to modify a nonconforming product or product component;
Updates—Changes to formally controlled project documents, plans, etc., to reflect modified or additional ideas or content.



Share your comments for PMI PMI-002 exam with other users:

C
CW
7/10/2023 6:46:00 PM

these are the type of questions i need.

N
Nobody
8/30/2023 9:54:00 PM

does this actually work? are they the exam questions and answers word for word?

S
Salah
7/23/2023 9:46:00 AM

thanks for providing these questions

R
Ritu
9/15/2023 5:55:00 AM

interesting

R
Ron
5/30/2023 8:33:00 AM

these dumps are pretty good.

S
Sowl
8/10/2023 6:22:00 PM

good questions

B
Blessious Phiri
8/15/2023 2:02:00 PM

dbua is used for upgrading oracle database

R
Richard
10/24/2023 6:12:00 AM

i am thrilled to say that i passed my amazon web services mls-c01 exam, thanks to study materials. they were comprehensive and well-structured, making my preparation efficient.

J
Janjua
5/22/2023 3:31:00 PM

please upload latest ibm ace c1000-056 dumps

M
Matt
12/30/2023 11:18:00 AM

if only explanations were provided...

R
Rasha
6/29/2023 8:23:00 PM

yes .. i need the dump if you can help me

A
Anonymous
7/25/2023 8:05:00 AM

good morning, could you please upload this exam again?

A
AJ
9/24/2023 9:32:00 AM

hi please upload sre foundation and practitioner exam questions

P
peter parker
8/10/2023 10:59:00 AM

the exam is listed as 80 questions with a pass mark of 70%, how is your 50 questions related?

B
Berihun
7/13/2023 7:29:00 AM

all questions are so important and covers all ccna modules

N
nspk
1/19/2024 12:53:00 AM

q 44. ans:- b (goto setup > order settings > select enable optional price books for orders) reference link --> https://resources.docs.salesforce.com/latest/latest/en-us/sfdc/pdf/sfom_impl_b2b_b2b2c.pdf(decide whether you want to enable the optional price books feature. if so, select enable optional price books for orders. you can use orders in salesforce while managing price books in an external platform. if you’re using d2c commerce, you must select enable optional price books for orders.)

M
Muhammad Rawish Siddiqui
12/2/2023 5:28:00 AM

"cost of replacing data if it were lost" is also correct.

A
Anonymous
7/14/2023 3:17:00 AM

pls upload the questions

M
Mukesh
7/10/2023 4:14:00 PM

good questions

E
Elie Abou Chrouch
12/11/2023 3:38:00 AM

question 182 - correct answer is d. ethernet frame length is 64 - 1518b. length of user data containing is that frame: 46 - 1500b.

D
Damien
9/23/2023 8:37:00 AM

i need this exam pls

N
Nani
9/10/2023 12:02:00 PM

its required for me, please make it enable to access. thanks

E
ethiopia
8/2/2023 2:18:00 AM

seems good..

W
whoAreWeReally
12/19/2023 8:29:00 PM

took the test last week, i did have about 15 - 20 word for word from this site on the test. (only was able to cram 600 of the questions from this site so maybe more were there i didnt review) had 4 labs, bgp, lacp, vrf with tunnels and actually had to skip a lab due to time. lots of automation syntax questions.

V
vs
9/2/2023 12:19:00 PM

no comments

J
john adenu
11/14/2023 11:02:00 AM

nice questions bring out the best in you.

O
Osman
11/21/2023 2:27:00 PM

really helpful

E
Edward
9/13/2023 5:27:00 PM

question #50 and question #81 are exactly the same questions, azure site recovery provides________for virtual machines. the first says that it is fault tolerance is the answer and second says disater recovery. from my research, it says it should be disaster recovery. can anybody explain to me why? thank you

M
Monti
5/24/2023 11:14:00 PM

iam thankful for these exam dumps questions, i would not have passed without this exam dumps.

A
Anon
10/25/2023 10:48:00 PM

some of the answers seem to be inaccurate. q10 for example shouldnt it be an m custom column?

P
PeterPan
10/18/2023 10:22:00 AM

are the question real or fake?

C
CW
7/11/2023 3:19:00 PM

thank you for providing such assistance.

M
Mn8300
11/9/2023 8:53:00 AM

nice questions

N
Nico
4/23/2023 11:41:00 PM

my 3rd purcahse from this site. these exam dumps are helpful. very helpful.

AI Tutor 👋 I’m here to help!