What is the purpose of a decision tree?

  1. It demonstrates the path of events in a project.
  2. It calculates the probability of an outcome.
  3. It determines what events may take place.
  4. It takes into account future events for today's choices.

Answer(s): D



Executing the risk response plan in order to react to risk events throughout the project is called:

  1. Contingency planning.
  2. Monitoring and control.
  3. Mitigation.
  4. Life cycle costing.

Answer(s): B



What is the difference between management reserves and contingency reserves?

  1. Contingency reserves address known knowns, whereas management reserves address known unknowns.
  2. Contingency and management reserves both address known unknowns and could be considered the same.
  3. Contingency reserves address known unknowns, whereas management reserves address unknown unknowns.
  4. Contingency reserves are managed by senior management, whereas management reserves are managed by the project manager.

Answer(s): C



A project manager is asked to select a contract type for a new software development project that has complete, detailed requirements.
Which is the BEST contract to choose?

  1. Cost reimbursable (CR)
  2. Fixed price (FP)
  3. Time and material (T&M)
  4. Cost plus fixed fee (CPFF)

Answer(s): B



The project manager and project sponsor are discussing the project costs and whether it is better to have their own company do part of the project or hire another company to do the work. If they asked for your opinion, you might say it would be better to do the work yourself if:

  1. There is a lot of proprietary data.
  2. You have the expertise, but you do not have the available manpower.
  3. You do not need control over the work.
  4. Your company resources are limited.

Answer(s): A



Share your comments for ITIL ISEB-PM1 exam with other users:

M
Marianne
10/22/2023 11:57:00 PM

i cannot see the button to go to the questions

S
sushant
6/28/2023 4:52:00 AM

good questions

A
A\MAM
6/27/2023 5:17:00 PM

q-6 ans-b correct. https://docs.paloaltonetworks.com/pan-os/9-1/pan-os-cli-quick-start/use-the-cli/commit-configuration-changes

U
unanimous
12/15/2023 6:38:00 AM

very nice very nice

A
akminocha
9/28/2023 10:36:00 AM

please help us with 1z0-1107-2 dumps

J
Jefi
9/4/2023 8:15:00 AM

please upload the practice questions

T
Thembelani
5/30/2023 2:45:00 AM

need this dumps

A
Abduraimov
4/19/2023 12:43:00 AM

preparing for this exam is overwhelming. you cannot pass without the help of these exam dumps.

P
Puneeth
10/5/2023 2:06:00 AM

new to this site but i feel it is good

A
Ashok Kumar
1/2/2024 6:53:00 AM

the correct answer to q8 is b. explanation since the mule app has a dependency, it is necessary to include project modules and dependencies to make sure the app will run successfully on the runtime on any other machine. source code of the component that the mule app is dependent of does not need to be included in the exported jar file, because the source code is not being used while executing an app. compiled code is being used instead.

M
Merry
7/30/2023 6:57:00 AM

good questions

V
VoiceofMidnight
12/17/2023 4:07:00 PM

Delayed the exam until December 29th.

U
Umar Ali
8/29/2023 2:59:00 PM

A and D are True

V
vel
8/28/2023 9:17:09 AM

good one with explanation

G
Gurdeep
1/18/2024 4:00:15 PM

This is one of the most useful study guides I have ever used.

AI Tutor 👋 I’m here to help!