What is the difference between expected monetary value and net present value?

  1. Expected value is the estimated value of the work actually accomplished and net present value is the value of the work to be done.
  2. Expected value is the value it takes to recover your investment and net present value is the value of money.
  3. Expected value is the probability times impact of an opportunity and net present value is the benefits less costs over many time periods.
  4. Expected value is the estimated value of risk response plans and net present value helps determine the value of investments.

Answer(s): C



A company attorney, newly hired by the company, walks into the project manager's office and tells her that he is ready to work with her on the procurement process. The project manager has little experience with procurement, so she is excited to have the assistance. With which of the following would it be BEST for the project manager to ask the attorney for help?

  1. Claims administration, audit results, and updating organizational process assets
  2. Contract change control system, payments, and change requests
  3. Recommended corrective actions, performance reporting, and records management system
  4. Procurement documentation, project management plan updates, and procurement management plan updates

Answer(s): A



A project manager discovers an urgent need for outsourced resources on the project. He knows he has the money to cover the cost of these resources. He goes to the procurement manager and explains the situation, insisting a contract be drawn up today so he can obtain resources and circumvent the standard procedure. Is this the correct process to follow?

  1. Yes, of course. For urgent needs, it is not necessary to follow the organization's procedure regarding procurement.
  2. Yes. Urgent needs from projects should always be dealt with immediately, as directed by the project manager.
  3. No. The procurement manager has a process to follow when creating contracts that helps protect the company and its projects.
  4. No. The procurement manager should be checking in with the project manager to see if he is in need of a contract, rather than making the project manager come and ask for one.

Answer(s): C



Which of the following is the BEST thing to do at a bidder conference?

  1. Answer sellers' questions
  2. Meet the sellers' teams
  3. Make sure the sellers have all the procurement documents
  4. Make sure the sellers ask all their questions

Answer(s): D



To complete performance index (TCPI) is represented by which of the following?

  1. BAC - EV/BAC - AC
  2. A measure of the value of work completed compared to the actual cost or progress
  3. A measure of progress achieved compared to progress planned
  4. AC + (BAC - EV)

Answer(s): A



Viewing Page 20 of 126



Share your comments for ITIL® ISEB-PM1 exam with other users:

Bsmaind 8/20/2023 9:23:00 AM

nice practice dumps
Anonymous


kumar 11/15/2023 11:24:00 AM

nokia 4a0-114 dumps
Anonymous


Vetri 10/3/2023 12:59:00 AM

great content and wonderful to have the answers with explanation
UNITED STATES


Ranjith 8/21/2023 3:39:00 PM

for question #118, the answer is option c. the screen shot is showing the drop down, but the answer is marked incorrectly please update . thanks for sharing such nice questions.
Anonymous


Eduardo Ramírez 12/11/2023 9:55:00 PM

the correct answer for the question 29 is d.
Anonymous


Dass 11/2/2023 7:43:00 AM

question no 22: correct answers: bc, 1 per session 1 per page 1 per component always
UNITED STATES


Reddy 12/14/2023 2:42:00 AM

these are pretty useful
Anonymous


Daisy Delgado 1/9/2023 1:05:00 PM

awesome
UNITED STATES


Atif 6/13/2023 4:09:00 AM

yes please upload
UNITED STATES


Xunil 6/12/2023 3:04:00 PM

great job whoever put this together, for the greater good! thanks!
Anonymous


Lakshmi 10/2/2023 5:26:00 AM

just started to view all questions for the exam
NETHERLANDS


rani 1/19/2024 11:52:00 AM

helpful material
Anonymous


Greg 11/16/2023 6:59:00 AM

hope for the best
UNITED STATES


hi 10/5/2023 4:00:00 AM

will post exam has finished
UNITED STATES


Vmotu 8/24/2023 11:14:00 AM

really correct and good analyze!
AZERBAIJAN


hicham 5/30/2023 8:57:00 AM

excellent thanks a lot
FRANCE


Suman C 7/7/2023 8:13:00 AM

will post once pass the cka exam
INDIA


Ram 11/3/2023 5:10:00 AM

good content
Anonymous


Nagendra Pedipina 7/13/2023 2:12:00 AM

q:32 answer has to be option c
INDIA


Tamer Barakat 12/7/2023 5:17:00 PM

nice questions
Anonymous


Daryl 8/1/2022 11:33:00 PM

i really like the support team in this website. they are fast in communication and very helpful.
UNITED KINGDOM


Curtis Nakawaki 6/29/2023 9:13:00 PM

a good contemporary exam review
UNITED STATES


x-men 5/23/2023 1:02:00 AM

q23, its an array, isnt it? starts with [ and end with ]. its an array of objects, not object.
UNITED STATES


abuti 7/21/2023 6:24:00 PM

cool very helpfull
Anonymous


Krishneel 3/17/2023 10:34:00 AM

i just passed. this exam dumps is the same one from prepaway and examcollection. it has all the real test questions.
INDIA


Regor 12/4/2023 2:01:00 PM

is this a valid prince2 practitioner dumps?
UNITED KINGDOM


asl 9/14/2023 3:59:00 PM

all are relatable questions
CANADA


Siyya 1/19/2024 8:30:00 PM

might help me to prepare for the exam
Anonymous


Ted 6/21/2023 11:11:00 PM

just paid and downlaod the 2 exams using the 50% sale discount. so far i was able to download the pdf and the test engine. all looks good.
GERMANY


Paul K 11/27/2023 2:28:00 AM

i think it should be a,c. option d goes against the principle of building anything custom unless there are no work arounds available
INDIA


ph 6/16/2023 12:41:00 AM

very legible
Anonymous


sephs2001 7/31/2023 10:42:00 PM

is this exam accurate or helpful?
Anonymous


ash 7/11/2023 3:00:00 AM

please upload dump, i have exam in 2 days
INDIA


Sneha 8/17/2023 6:29:00 PM

this is useful
CANADA