The following information and diagram apply to a project:The earliest completion time for the project is:
Answer(s): C
The two paths through the network are A-C-E 5 + 4 + 6 = 15 days) and B-D-E 3 +2 + 6 = 11 days). The critical or longest path is thus A-C-E. Hence, the earliest completion time is 15 days.
Which of the following terms is not used in project management?
Answer(s): D
Project management concerns managing teams assigned to special projects. Lumpy demand refers to periodic demand for a product or service that increases in large, lumpy increments.
Activity scheduling information for the installation of a new computer system is given belowThe earliest completion time for the project is:
The critical path is the longest path because it defines the minimum duration of the project.A-D-E 4 + 6 + 5 = 15) is the critical path.
In a critical path analysis, if slack time in an activity exists, the activity:
Slack is the free time associated with each activity. In other words, paths that are not critical have slack time. Slack represents unused resources that can be diverted to the critical path.
The primary difference between PERT and CPM is that:
Both PERT and CPM are network analysis techniques. But CPM was developed independently of PERT and is widely used in the construction industry. CPM may be thought of as a subset of PERT. Like PERT, it is a network technique, but, unlike PERT, it uses deterministic time and cost estimates. Its advantages include cost estimates plus the concept of "crash" efforts and costs. Activity times are estimated for normal effort and crash effort. Crash time is the time to complete an activity assuming that all available resources were devoted to the task overtime, extra crew, etc.). Activity costs are also estimated for normal and crash efforts. These estimates allow the project manager to estimate the costs of completing the project if some of the activities are completed on a crash basis. The network diagram is constructed in the same manner as PERT diagrams. Once the diagram is constructed, the critical paths are found for normal and crash times. More than one critical path may exist for each diagram.
Share your comments for Financial CIA-III exam with other users:
very inciting
question 5, it seems a instead of d, because: - care plan = case - patient = person account - product = product2;
it look like real one
i am taking oracle fcc certification test next two days, pls share question dumps
i need dumps
its time to comptia sec+
question 35 has an answer for a different question. i believe the answer is "a" because it shut off the firewall. "0" in registry data means that its false (aka off).
helpful content
oracle 19c is complex db
helpful for practice
support team is fast and deeply knowledgeable. i appreciate that a lot.
helpful questions
thanks for question
the software is provided for free so this is a big change. all other sites are charging for that. also that fucking examtopic site that says free is not free at all. you are hit with a pay-wall.
i need exam questions nca 6.5 any help please ?
just took the comptia cybersecurity analyst (cysa+) - wished id seeing this before my exam
very helpful
i need this exam
nice questions... are these questions the same of the exam?
need to view
highly appreciate for your sharing.
kindly share this dump. thank you
link plz for download
data quality oecd
rman is one good recovery technology
need it thx
good questions
good one nice revision
i love this thank you i need
question # 142: data governance is not one of the deliverables in the document and content management context diagram.
most answers not correct here
what % of questions do we get in the real exam?
i just want to tell you. i took my microsoft az-104 exam and passed it. your program was awesome. i especially liked your detailed questions and answers and practice tests that made me well-prepared for the exam. thanks to this website!!!
all the best