When making a cost-time trade-off in PERT analysis, the first activity that should be crashed is the activity:
Answer(s): D
When making a cost-time trade-off, the first activity to be crashed have its completion time accelerated) is one on the critical path. To select an activity on another path would not reduce the total time of completion. The initial activity chosen should be the one with the completion time that can be accelerated at the lowest possible cost per unit of time saved.
In PERT, slack is the:
PERT diagrams are free-form networks showing each activity in a large project as a line between events. The critical path is the longest path in time through the network. That path is critical in that, if any activity on the critical path takes longer than expected, the entire project will be delayed. Paths that are not critical have slack time. Slack is the number of days an activity can be delayed without forcing a delay for the entire project.
The network below describes the interrelationships of several activities necessary to complete a project. The arrows represent the activities. The numbers between the arrows indicate the number of months to complete each activity. The shortest time to complete the project is:
Answer(s): C
The longest, or critical, path in the network from node A) to node F) is path A- -D-F. All other paths are shorter than path A-C-D-F, so the activities along those paths can be completed before the activities along path A-C-D-F. Thus, the shortest time to complete the project is 8 months 3 + 3 +2).
A shortest-route algorithm is used in network models to:
Answer(s): B
Network models are used to solve managerial problems pertaining to project scheduling, information systems design, and transportation systems design. Networks consisting of nodes and arcs may be created to represent in graphic form problems related to transportation, assignment, and transshipment. The shortest-route, minimal spanning tree, and maximal flow problems are other applications of network models. A shortest-route algorithm minimizes total travel time from one site to each of the other sites in a transportation system.
Which of the following project scheduling techniques is commonly used in total quality management for simplifying work processes?
Flowcharting is commonly used in computer programming for determining program logic and in total quality management for simplifying work processes. However, they are also used for establishing the desirable sequence of activities and decisions.
Share your comments for Financial CIA-III exam with other users:
question: 78 the right answer i think is d not a
very helpful
i am writing this exam tomorrow and have dumps
can i have the icdl excel exam
please upload it
hye when will post again the past year question for this h13-311_v3 part since i have to for my test tommorow…thank you very much
on question 22, option b-once per session is also valid.
this website is very helpful
its my first time exam
correct answers are device configuration-enable the automatic installation of webview2 runtime. & policy management- prevent users from submitting feedback.
is this dump still valid? today is 9-july-2023
i need this exam.. please upload these are really helpful
please upload the oracle 1z0-1059-22 dumps
very good questions
nice, first step to exams
is this valid for chfiv9 as well... as i am reker 3rd time...
great exam for people taking 220-1101
this is very helpfull for me
just started preparing for the exam
these are the type of questions i need.
does this actually work? are they the exam questions and answers word for word?
thanks for providing these questions
interesting
these dumps are pretty good.
good questions
dbua is used for upgrading oracle database
i am thrilled to say that i passed my amazon web services mls-c01 exam, thanks to study materials. they were comprehensive and well-structured, making my preparation efficient.
please upload latest ibm ace c1000-056 dumps
if only explanations were provided...
yes .. i need the dump if you can help me
good morning, could you please upload this exam again?
hi please upload sre foundation and practitioner exam questions
the exam is listed as 80 questions with a pass mark of 70%, how is your 50 questions related?
all questions are so important and covers all ccna modules