Financial The Certified Internal Auditor Part 3 CIA-III Dumps in PDF

Free Financial CIA-III Real Questions (page: 56)

As of week 8, the Gantt chart shows that the project is:

  1. Complete.
  2. Ahead of schedule.
  3. On schedule.
  4. Behind schedule.

Answer(s): B

Explanation:

Assuming that 1) each of the bars represents the expected time necessary to complete an activity and 2) the shaded regions represent the portions completed, activity A has been completed as scheduled and activities B and C are ahead of schedule. Consequently, the project is ahead of schedule.



When using PERT Program Evaluation Review Technique), the expected time for an activity when given an optimistic time A), a pessimistic time B), and a most likely time m) is calculated by which one of the following formulas?

  1. b ­ a) =2
  2. a + b) =2
  3. a + 4m +b) =6
  4. 4 abm) =6

Answer(s): C

Explanation:

PERT was developed to aid managers in controlling large, complex projects. PERT analysis includes probabilistic estimates of activity completion times. Three time estimates are made:
Optimistic, most likely, and pessimistic. The time estimates for an activity are assumed to approximate a beta probability distribution. PERT approximates the mean of the beta distribution by dividing the sum of the optimistic time, the pessimistic time, and four times the most likely time by six.



The process of adding resources to shorten selected activity times on the critical path in project scheduling is called:

  1. Crashing.
  2. The Delphi technique.
  3. ABC analysis.
  4. A branch-and-bound solution.

Answer(s): A

Explanation:

Activity times are estimated for normal effort and crash effort. Crashing is the process of adding resources to shorten activity times on the critical path in project scheduling. The network diagram and the corresponding activity cost chart for a manufacturing project at Networks, Inc. are presented below. The numbers in the diagram are the expected times in days) to perform each activity in the project.



The expected time of the critical path is:

  1. 12.0 days.
  2. 13.0 days.
  3. 11.5 days.
  4. 11.0 days.

Answer(s): B

Explanation:

The critical path is the longest path. The longest path in the diagram is A-D-E, which requires 13 days 5.5 + 7.5) based on expected times. The network diagram and the corresponding activity cost chart for a manufacturing project at Networks, Inc. are presented below. The numbers in the diagram are the expected times in days) to perform each activity in the project.



To keep costs at a minimum and decrease the completion time by 1-1/2 days, Networks, Inc.
should crash activity)

  1. AD and AB.
  2. DE.
  3. AD.
  4. AB and CE.

Answer(s): A

Explanation:

The critical longest) path is A-D-E, which has an expected time of 13 days 5.5 +7.5). However, to decrease the project's completion time by 1.5 days, paths A-B-C-E 4.5 + 1.0 + 6.5 = 12 days) and A-B-D-E 4.5 + .5 + 7.5 = 12.5 days) as well as A-D-E must also be shortened. Hence, A-D-E must be reduced by 1.5 days, A-B-C-E by .5 day, and A-B-D-E by 1.0 day. The only way to decrease A-D-E by 1.5 days is to crash activity. AD 5.5 expected time - 4.0 crash time = 1.5 days). Crashing DE results in a 1.0-day saving 7.5 -- 6.5) only.
Crashing AB is the efficient way to reduce both A-B-C-E and A-B-D-E by the desired amount of time because it i s hart of both paths. The incremental cost of crashing AB is U $1,000 US $4,000 crash cost -- US $3,000 normal cost) to shorten the completion time by 1.0 day 4.5 -- 3.5). The alternatives for decreasing both A-B-C-E and A-B-D-E are more costly.



Share your comments for Financial CIA-III exam with other users:

A
Ali Azam
12/7/2023 1:51:00 AM

really helped with preparation of my scrum exam

J
Jerman
9/29/2023 8:46:00 AM

very informative and through explanations

J
Jimmy
11/4/2023 12:11:00 PM

prep for exam

A
Abhi
9/19/2023 1:22:00 PM

thanks for helping us

M
mrtom33
11/20/2023 4:51:00 AM

i prepared for the eccouncil 350-401 exam. i scored 92% on the test.

J
JUAN
6/28/2023 2:12:00 AM

aba questions to practice

L
LK
1/2/2024 11:56:00 AM

great content

S
Srijeeta
10/8/2023 6:24:00 AM

how do i get the remaining questions?

J
Jovanne
7/26/2022 11:42:00 PM

well formatted pdf and the test engine software is free. well worth the money i sept.

C
CHINIMILLI SATISH
8/29/2023 6:22:00 AM

looking for 1z0-116

P
Pedro Afonso
1/15/2024 8:01:00 AM

in question 22, shouldnt be in the data (option a) layer?

P
Pushkar
11/7/2022 12:12:00 AM

the questions are incredibly close to real exam. you people are amazing.

A
Ankit S
11/13/2023 3:58:00 AM

q15. answer is b. simple

S
S. R
12/8/2023 9:41:00 AM

great practice

M
Mungara
3/14/2023 12:10:00 AM

thanks to this exam dumps, i felt confident and passed my exam with ease.

A
Anonymous
7/25/2023 2:55:00 AM

need 1z0-1105-22 exam

N
Nigora
5/31/2022 10:05:00 PM

this is a beautiful tool. passed after a week of studying.

A
Av dey
8/16/2023 2:35:00 PM

can you please upload the dumps for 1z0-1096-23 for oracle

M
Mayur Shermale
11/23/2023 12:22:00 AM

its intresting, i would like to learn more abouth this

J
JM
12/19/2023 2:23:00 PM

q252: dns poisoning is the correct answer, not locator redirection. beaconing is detected from a host. this indicates that the system has been infected with malware, which could be the source of local dns poisoning. location redirection works by either embedding the redirection in the original websites code or having a user click on a url that has an embedded redirect. since users at a different office are not getting redirected, it isnt an embedded redirection on the original website and since the user is manually typing in the url and not clicking a link, it isnt a modified link.

F
Freddie
12/12/2023 12:37:00 PM

helpful dump questions

D
Da Costa
8/25/2023 7:30:00 AM

question 423 eigrp uses metric

B
Bsmaind
8/20/2023 9:22:00 AM

hello nice dumps

B
beau
1/12/2024 4:53:00 PM

good resource for learning

S
Sandeep
12/29/2023 4:07:00 AM

very useful

K
kevin
9/29/2023 8:04:00 AM

physical tempering techniques

B
Blessious Phiri
8/15/2023 4:08:00 PM

its giving best technical knowledge

T
Testbear
6/13/2023 11:15:00 AM

please upload

S
shime
10/24/2023 4:23:00 AM

great question with explanation thanks!!

T
Thembelani
5/30/2023 2:40:00 AM

does this exam have lab sections?

S
Shin
9/8/2023 5:31:00 AM

please upload

P
priti kagwade
7/22/2023 5:17:00 AM

please upload the braindump for .net

R
Robe
9/27/2023 8:15:00 PM

i need this exam 1z0-1107-2. please.

C
Chiranthaka
9/20/2023 11:22:00 AM

very useful!

AI Tutor 👋 I’m here to help!