Financial The Certified Internal Auditor Part 3 CIA-III Dumps in PDF

Free Financial CIA-III Real Questions (page: 56)

As of week 8, the Gantt chart shows that the project is:

  1. Complete.
  2. Ahead of schedule.
  3. On schedule.
  4. Behind schedule.

Answer(s): B

Explanation:

Assuming that 1) each of the bars represents the expected time necessary to complete an activity and 2) the shaded regions represent the portions completed, activity A has been completed as scheduled and activities B and C are ahead of schedule. Consequently, the project is ahead of schedule.



When using PERT Program Evaluation Review Technique), the expected time for an activity when given an optimistic time A), a pessimistic time B), and a most likely time m) is calculated by which one of the following formulas?

  1. b ­ a) =2
  2. a + b) =2
  3. a + 4m +b) =6
  4. 4 abm) =6

Answer(s): C

Explanation:

PERT was developed to aid managers in controlling large, complex projects. PERT analysis includes probabilistic estimates of activity completion times. Three time estimates are made:
Optimistic, most likely, and pessimistic. The time estimates for an activity are assumed to approximate a beta probability distribution. PERT approximates the mean of the beta distribution by dividing the sum of the optimistic time, the pessimistic time, and four times the most likely time by six.



The process of adding resources to shorten selected activity times on the critical path in project scheduling is called:

  1. Crashing.
  2. The Delphi technique.
  3. ABC analysis.
  4. A branch-and-bound solution.

Answer(s): A

Explanation:

Activity times are estimated for normal effort and crash effort. Crashing is the process of adding resources to shorten activity times on the critical path in project scheduling. The network diagram and the corresponding activity cost chart for a manufacturing project at Networks, Inc. are presented below. The numbers in the diagram are the expected times in days) to perform each activity in the project.



The expected time of the critical path is:

  1. 12.0 days.
  2. 13.0 days.
  3. 11.5 days.
  4. 11.0 days.

Answer(s): B

Explanation:

The critical path is the longest path. The longest path in the diagram is A-D-E, which requires 13 days 5.5 + 7.5) based on expected times. The network diagram and the corresponding activity cost chart for a manufacturing project at Networks, Inc. are presented below. The numbers in the diagram are the expected times in days) to perform each activity in the project.



To keep costs at a minimum and decrease the completion time by 1-1/2 days, Networks, Inc.
should crash activity)

  1. AD and AB.
  2. DE.
  3. AD.
  4. AB and CE.

Answer(s): A

Explanation:

The critical longest) path is A-D-E, which has an expected time of 13 days 5.5 +7.5). However, to decrease the project's completion time by 1.5 days, paths A-B-C-E 4.5 + 1.0 + 6.5 = 12 days) and A-B-D-E 4.5 + .5 + 7.5 = 12.5 days) as well as A-D-E must also be shortened. Hence, A-D-E must be reduced by 1.5 days, A-B-C-E by .5 day, and A-B-D-E by 1.0 day. The only way to decrease A-D-E by 1.5 days is to crash activity. AD 5.5 expected time - 4.0 crash time = 1.5 days). Crashing DE results in a 1.0-day saving 7.5 -- 6.5) only.
Crashing AB is the efficient way to reduce both A-B-C-E and A-B-D-E by the desired amount of time because it i s hart of both paths. The incremental cost of crashing AB is U $1,000 US $4,000 crash cost -- US $3,000 normal cost) to shorten the completion time by 1.0 day 4.5 -- 3.5). The alternatives for decreasing both A-B-C-E and A-B-D-E are more costly.



Share your comments for Financial CIA-III exam with other users:

Q
Q44
7/30/2023 11:50:00 AM

ans is coldline i think

A
Anuj
12/21/2023 1:30:00 PM

very helpful

G
Giri
9/13/2023 10:31:00 PM

can you please provide dumps so that it helps me more

A
Aaron
2/8/2023 12:10:00 AM

thank you for providing me with the updated question and answers. this version has all the questions from the exam. i just saw them in my exam this morning. i passed my exam today.

S
Sarwar
12/21/2023 4:54:00 PM

how i can see exam questions?

C
Chengchaone
9/11/2023 10:22:00 AM

can you please upload please?

M
Mouli
9/2/2023 7:02:00 AM

question 75: option c is correct answer

J
JugHead
9/27/2023 2:40:00 PM

please add this exam

S
sushant
6/28/2023 4:38:00 AM

please upoad

J
John
8/7/2023 12:09:00 AM

has anyone recently attended safe 6.0 certification? is it the samq question from here.

B
Blessious Phiri
8/14/2023 3:49:00 PM

expository experience

C
concerned citizen
12/29/2023 11:31:00 AM

52 should be b&c. controller failure has nothing to do with this type of issue. degraded state tells us its a raid issue, and if the os is missing then the bootable device isnt found. the only other consideration could be data loss but thats somewhat broad whereas b&c show understanding of the specific issues the question is asking about.

D
deedee
12/23/2023 5:10:00 PM

great help!!!

S
Samir
8/1/2023 3:07:00 PM

very useful tools

S
Saeed
11/7/2023 3:14:00 AM

looks a good platform to prepare az-104

M
Matiullah
6/24/2023 7:37:00 AM

want to pass the exam

S
SN
9/5/2023 2:25:00 PM

good resource

Z
Zoubeyr
9/8/2023 5:56:00 AM

question 11 : d

U
User
8/29/2023 3:24:00 AM

only the free dumps will be enough for pass, or have to purchase the premium one. please suggest.

C
CW
7/6/2023 7:37:00 PM

good questions. thanks.

F
Farooqi
11/21/2023 1:37:00 AM

good for practice.

I
Isaac
10/28/2023 2:30:00 PM

great case study

M
Malviya
2/3/2023 9:10:00 AM

the questions in this exam dumps is valid. i passed my test last monday. i only whish they had their pricing in inr instead of usd. but it is still worth it.

R
rsmyth
5/18/2023 12:44:00 PM

q40 the answer is not d, why are you giving incorrect answers? snapshot consolidation is used to merge the snapshot delta disk files to the vm base disk

K
Keny
6/23/2023 9:00:00 PM

thanks, very relevant

M
Muhammad Rawish Siddiqui
11/29/2023 12:14:00 PM

wrong answer. it is true not false.

J
Josh
7/10/2023 1:54:00 PM

please i need the mo-100 questions

V
VINNY
6/2/2023 11:59:00 AM

very good use full

A
Andy
12/6/2023 5:56:00 AM

very valid questions

M
Mamo
8/12/2023 7:46:00 AM

will these question help me to clear pl-300 exam?

M
Marial Manyang
7/26/2023 10:13:00 AM

please provide me with these dumps questions. thanks

A
Amel Mhamdi
12/16/2022 10:10:00 AM

in the pdf downloaded is write google cloud database engineer i think that it isnt the correct exam

A
Angel
8/30/2023 10:58:00 PM

i think you have the answers wrong regarding question: "what are three core principles of web content accessibility guidelines (wcag)? answer: robust, operable, understandable

S
SH
5/16/2023 1:43:00 PM

these questions are not valid , they dont come for the exam now

AI Tutor 👋 I’m here to help!