Assume that additional workers are hired for the bottleneck operation to expedite setups and materials handling. The cost of the additional workers is US $50,000 per year. As a result, the annual output of the bottleneck operation will increase by 500 units. The change in operating income attributable to the increase in workers is:

  1. US $50,000
  2. US $36,000
  3. US $ 14,000)
  4. US $ 20,000)

Answer(s): C

Explanation:

Operation 2 is the bottleneck because it is functioning at its capacity. The incremental annual throughput contribution revenues -- direct materials costs) from adding workers to Operation 2 is US $36,000 [500 units x $120 unit price -- $48 DPI per unit)]. Because the cost of the additional workers is US $50,000, the change in operating income is US $ 14,000). This information is relevant to a theory of constraints TOG) analysis. A manufacturer that can sell all of its output produces its sole product using three operations. Each unit sells for US $120, and direct materials costing US $48 per unit are added at the start of the first operation. Other variable costs are immaterial. The fallowing annual cost and capacity information is available concerning those operations:



Assume that C Company offers to perform the operation 2 function on 1,000 units at a unit price of US $40, excluding direct materials cast. Also assume that Y Company offers to perform the Operation 1 function an 1,000 units at a unit price of US $7, excluding direct materials cost.
Which of these mutually exclusive offers is acceptable?

  1. C but not Y.
  2. Y but not C.
  3. X or Y.
  4. Neither offer should be accepted.

Answer(s): A

Explanation:

KG's offer should be accepted because its cast is US $40,000 1,000 units x $40), but the increase in throughput contribution is US $72,000 [1,000 units $120 unit price -- $48 E' 1 per unit)]. Hence, the relevant cost of QC's offer is less than the incremental throughput contribution. ms's offer effectively increases the capacity of the bottleneck operation. Y's offer should be rejected because, even though its US $7 unit price is less than the US $8 unit operating cost excluding direct materials) for Operation 1. it will result in the incurrence of additional casts with no increase in throughput contribution, given that Operation 2 is already producing at its 150,000-unit capacity.



Company J produces two components: A-1 and A-2. The unit throughput contribution margins for A-1 and A-2 are US $150 and US $300, respectively. Each component must proceed through two processes: Operation 1 and Operation 2. The capacity of Operation 1 is 180 machine hours, with A-1 and A-2 requiring 1 hour and 3 hours, respectively.
Furthermore, Company J can sell only 45 units of A-1 and 100 units of A-2. However,
Company J is considering expanding Operation 1's capacity by 90 machine hours at a cost of US $80 per hour. Assuming that Operation 2 has sufficient capacity to handle any additional output from Operation 1, how much should Company J produce?

  1. Option A
  2. Option C
  3. Option C
  4. Option D

Answer(s): C

Explanation:

A-1's throughput contribution margin per unit of the scarce resource the internal binding constraint) is US $150 $150 UCM - 1 machining hour). A-2's throughput contribution margin per unit of the scarce resource is U $100 $300 UCM - 3 machine hours).
Consequently, Company J should produce as much A-1 as it can sell 45 units). If Company adds 90 machine hours to increase the capacity of Operation -I to 270 hours 180 + 90), it cannot produce additional units of A-1 because the external binding constraint has not been relaxed. However, it can produce additional units of A-2. Given that the UCM per machine hour of A-2 is U $100 and that the cost is US $80 per hour, adding capacity to Operation 1 is profitable. Thus, Company J should use 45 machine hours to produce 45 units of A-1. The remaining 225 machine hours 270 - 45) should be used to produce 75 units 225 - 3 hours) of A-2. The latter amount is within the external binding constraint. A company produces two products, and Y, which use material and labor as inputs. Fixed amounts of labor and material are available for production each month In addition. the demand for product Y each month is limited: product has no constraint an the number of units that can be sold. A graphical depiction of these production and demand constraints is presented in the opposite column.



The feasible solution region is bounded by the lines connecting points:

  1. 3, 4, 6, and 7.
  2. I, 5, 6, and 8.
  3. 2, 4, , , and 8.
  4. 3, E. 6, and 7.

Answer(s): A

Explanation:

A model consisting of a system of functions may be used to optimize an objective function. If the functions in the model are all linear, the model is a linear programming model. Linear programming is a technique to determine optimal resource allocation. Several solution methods are available to solve linear programming problems. The graphical method, the easiest technique, is limited to simple problems. Here, the graph consists of three lines, each representing a production constraint. The lines connecting points , 4, 6, and 7 bound the feasible solution region. Product mikes of and Y that lie outside this boundary cannot be produced and/or sold because the demand constraint line ,4), the labor constraint line 4,6), and the material constraint line 6,7) are binding. A company produces two products, and Y, which use material and labor as inputs. Fixed amounts of labor and material are available for production each month In addition. the demand for product Y each month is limited: product has no constraint an the number of units that can be sold. A graphical depiction of these production and demand constraints is presented in the opposite column.



If a series of profit lines for and Y are drawn on the graph, the mix of G and Y that will result in the maximum profit can be determined from:

  1. The last point in the feasible solution region touched by a profit line.
  2. Any point on the boundary of the feasible solution region touched by a profit line.
  3. The first paint an the feasible solution region boundary that intersects a profit line.
  4. Any point on the demand constraint that intersects a profit line.

Answer(s): A

Explanation:

A profit line has negative slope because the profit from sales of one product increases as the profit from sales of the other product declines. Moving the profit line rightward while maintaining its slope) to the last paint in the feasible region determines the solution.



Viewing Page 60 of 312



Share your comments for Financial CIA-III exam with other users:

max 12/22/2023 3:45:00 PM

very useful
Anonymous


Muhammad Rawish Siddiqui 12/8/2023 6:12:00 PM

question # 208: failure logs is not an example of operational metadata.
SAUDI ARABIA


Sachin Bedi 1/5/2024 4:47:00 AM

good questions
Anonymous


Kenneth 12/8/2023 7:34:00 AM

thank you for the test materials!
KOREA REPUBLIC OF


Harjinder Singh 8/9/2023 4:16:00 AM

its very helpful
HONG KONG


SD 7/13/2023 12:56:00 AM

good questions
UNITED STATES


kanjoe 7/2/2023 11:40:00 AM

good questons
UNITED STATES


Mahmoud 7/6/2023 4:24:00 AM

i need the dumb of the hcip security v4.0 exam
EGYPT


Wei 8/3/2023 4:18:00 AM

upload the dump please
HONG KONG


Stephen 10/3/2023 6:24:00 PM

yes, iam looking this
AUSTRALIA


Stephen 8/4/2023 9:08:00 PM

please upload cima e2 managing performance dumps
Anonymous


hp 6/16/2023 12:44:00 AM

wonderful questions
Anonymous


Priyo 11/14/2023 2:23:00 AM

i used this site since 2000, still great to support my career
INDONESIA


Jude 8/29/2023 1:56:00 PM

why is the answer to "which of the following is required by scrum?" all of the following stated below since most of them are not mandatory? sprint retrospective. members must be stand up at the daily scrum. sprint burndown chart. release planning.
UNITED STATES


Marc blue 9/15/2023 4:11:00 AM

great job. hope this helps out.
UNITED STATES


Anne 9/13/2023 2:33:00 AM

upload please. many thanks!
Anonymous


pepe el toro 9/12/2023 7:55:00 PM

this is so interesting
Anonymous


Antony 11/28/2023 12:13:00 AM

great material thanks
AUSTRALIA


Thembelani 5/30/2023 2:22:00 AM

anyone who wrote this exam recently
Anonymous


P 9/16/2023 1:27:00 AM

ok they re good
Anonymous


Jorn 7/13/2023 5:05:00 AM

relevant questions
UNITED KINGDOM


AM 6/20/2023 7:54:00 PM

please post
UNITED STATES


Nagendra Pedipina 7/13/2023 2:22:00 AM

q:42 there has to be a image in the question to choose what does it mean from the options
INDIA


BrainDumpee 11/18/2023 1:36:00 PM

looking for cphq dumps, where can i find these for free? please and thank you.
UNITED STATES


sheik 10/14/2023 11:37:00 AM

@aarun , thanks for the information. it would be great help if you share your email
Anonymous


Random user 12/11/2023 1:34:00 AM

1z0-1078-23 need this dumps
Anonymous


labuschanka 11/16/2023 6:06:00 PM

i gave the microsoft azure az-500 tests and prepared from this site as it has latest mock tests available which helped me evaluate my performance and score 919/1000
Anonymous


Marianne 10/22/2023 11:57:00 PM

i cannot see the button to go to the questions
Anonymous


sushant 6/28/2023 4:52:00 AM

good questions
EUROPEAN UNION


A\MAM 6/27/2023 5:17:00 PM

q-6 ans-b correct. https://docs.paloaltonetworks.com/pan-os/9-1/pan-os-cli-quick-start/use-the-cli/commit-configuration-changes
UNITED STATES


unanimous 12/15/2023 6:38:00 AM

very nice very nice
Anonymous


akminocha 9/28/2023 10:36:00 AM

please help us with 1z0-1107-2 dumps
INDIA


Jefi 9/4/2023 8:15:00 AM

please upload the practice questions
Anonymous


Thembelani 5/30/2023 2:45:00 AM

need this dumps
Anonymous