A project life cycle which combines approaches from the linear and iterative life cycles is known as _________ project life cycle.

  1. a hybrid.
  2. an extended.
  3. a reduced.
  4. a combined.

Answer(s): A



The purpose of project management is to:

  1. organise management plans.
  2. keep all stakeholders happy.
  3. control change initiatives.
  4. effect beneficial change.

Answer(s): D



Which of the following statements refers to how scope is managed in a linear project but not an iterative project?

  1. Teams can act on new knowledge to change the scope.
  2. Teams can re-prioritise requirements within the scope.
  3. The scope of work is the starting point for the implementation of change control.
  4. Scope definition is assumed to be fixed for the whole project

Answer(s): D



One difference between an issue and a risk is an issue:

  1. must be recorded but a risk does not.
  2. is an uncertain event but a risk is not.
  3. is a certain event but a risk is not.
  4. always affects scope but a risk does not

Answer(s): C



Communication includes:
1) exchanging information
2) managing stakeholders
3) confirming there is a shared understanding
4) building relationships within your team

  1. 2 and 3 only
  2. 1 and 4 only
  3. 1 and 3 only
  4. 2 and 4 only

Answer(s): C



A project manager requires a team member to focus on the team's objectives and draw out other team members.
Which of the Belbin's team roles is most appropriate?

  1. Shaper.
  2. Monitor evaluator.
  3. Specialist.
  4. Co-ordinator

Answer(s): D



An extended project life cycle can be defined as:

  1. an approach that adds operational and termination phases to a linear life cycle.
  2. an approach that adds adoption and benefits realisation phases to a linear life cycle.
  3. a framework for conducting a cost-benefit analysis once a project has closed.
  4. a framework for ensuring the re-deployment of assets post project.

Answer(s): B



One aspect of quality planning is to:

  1. plan the audit of a project to provide assurance to the project board.
  2. provide confidence that a project will achieve its objectives in the required time frame.
  3. specify the acceptance criteria used to validate the outputs are fit for purpose.
  4. confirm routes for reporting to ensure effective communication

Answer(s): C



Viewing Page 7 of 53



Share your comments for APM APM-PFQ exam with other users:

ibrahim 11/9/2023 7:57:00 AM

page :20 https://exam-dumps.com/snowflake/free-cof-c02-braindumps.html?p=20#collapse_453 q 74: true or false: pipes can be suspended and resumed. true. desc.: pausing or resuming pipes in addition to the pipe owner, a role that has the following minimum permissions can pause or resume the pipe https://docs.snowflake.com/en/user-guide/data-load-snowpipe-intro
FINLAND


Franklin Allagoa 7/5/2023 5:16:00 AM

i want hcia exam dumps
Anonymous


SSA 12/24/2023 1:18:00 PM

good training
Anonymous


BK 8/11/2023 12:23:00 PM

very useful
INDIA


Deepika Narayanan 7/13/2023 11:05:00 PM

yes need this exam dumps
Anonymous


Blessious Phiri 8/15/2023 3:31:00 PM

these questions are a great eye opener
Anonymous


Jagdesh 9/8/2023 8:17:00 AM

thank you for providing these questions and answers. they helped me pass my exam. you guys are great.
CANADA


TS 7/18/2023 3:32:00 PM

good knowledge
Anonymous


Asad Khan 11/1/2023 2:44:00 AM

answer 10 should be a because only a new project will be created & the organization is the same.
Anonymous


Raj 9/12/2023 3:49:00 PM

can you please upload the dump again
UNITED STATES


Christian Klein 6/23/2023 1:32:00 PM

is it legit questions from sap certifications ?
UNITED STATES


anonymous 1/12/2024 3:34:00 PM

question 16 should be b (changing the connector settings on the monitor) pc and monitor were powered on. the lights on the pc are on indicating power. the monitor is showing an error text indicating that it is receiving power too. this is a clear sign of having the wrong input selected on the monitor. thus, the "connector setting" needs to be switched from hdmi to display port on the monitor so it receives the signal from the pc, or the other way around (display port to hdmi).
UNITED STATES


NSPK 1/18/2024 10:26:00 AM

q 10. ans is d (in the target org: open deployment settings, click edit next to the source org. select allow inbound changes and save
Anonymous


mohamed abdo 9/1/2023 4:59:00 AM

very useful
Anonymous


Tom 3/18/2022 8:00:00 PM

i purchased this exam dumps from another website with way more questions but they were all invalid and outdate. this exam dumps was right to the point and all from recent exam. it was a hard pass.
UNITED KINGDOM


Edrick GOP 10/24/2023 6:00:00 AM

it was a good experience and i got 90% in the 200-901 exam.
Anonymous


anonymous 8/10/2023 2:28:00 AM

hi please upload this
Anonymous


Bakir 7/6/2023 7:24:00 AM

please upload it
UNITED KINGDOM


Aman 6/18/2023 1:27:00 PM

really need this dump. can you please help.
UNITED KINGDOM


Neela Para 1/8/2024 6:39:00 PM

really good and covers many areas explaining the answer.
NEW ZEALAND


Karan Patel 8/15/2023 12:51:00 AM

yes, can you please upload the exam?
UNITED STATES


NISHAD 11/7/2023 11:28:00 AM

how many questions are there in these dumps?
UNITED STATES


Pankaj 7/3/2023 3:57:00 AM

hi team, please upload this , i need it.
UNITED STATES


DN 9/4/2023 11:19:00 PM

question 14 - run terraform import: this is the recommended best practice for bringing manually created or destroyed resources under terraform management. you use terraform import to associate an existing resource with a terraform resource configuration. this ensures that terraform is aware of the resource, and you can subsequently manage it with terraform.
Anonymous


Zhiguang 8/19/2023 11:37:00 PM

please upload dump. thanks in advance.
Anonymous


deedee 12/23/2023 5:51:00 PM

great great
UNITED STATES


Asad Khan 11/1/2023 3:10:00 AM

answer 16 should be b your organizational policies require you to use virtual machines directly
Anonymous


Sale Danasabe 10/24/2023 5:21:00 PM

the question are kind of tricky of you didnt get the hnag on it.
Anonymous


Luis 11/16/2023 1:39:00 PM

can anyone tell me if this is for rhel8 or rhel9?
UNITED STATES


hik 1/19/2024 1:47:00 PM

good content
UNITED STATES


Blessious Phiri 8/15/2023 2:18:00 PM

pdb and cdb are critical to the database
Anonymous


Zuned 10/22/2023 4:39:00 AM

till 104 questions are free, lets see how it helps me in my exam today.
UNITED STATES


Muhammad Rawish Siddiqui 12/3/2023 12:11:00 PM

question # 56, answer is true not false.
SAUDI ARABIA


Amaresh Vashishtha 8/27/2023 1:33:00 AM

i would be requiring dumps to prepare for certification exam
Anonymous