In which phase of the project should the Procurement Strategy be written?

  1. Concept
  2. Definition
  3. Deployment
  4. Transition

Answer(s): B



In developing a network the first task after listing the activities is to...

  1. Define activity durations
  2. Determine float
  3. Determine the interdependencies of activities
  4. Harmonise the activity to a calendar

Answer(s): C



Which of these is a correct definition of an Estimate?

  1. The use of a range of tools and techniques to produce forecasts of the probable time or cost of completing work
  2. An educated guess that improves over time
  3. A forecast of the probable time or cost of completing work
  4. An estimate is an approximation of project time and cost targets that forms the basis of the contract

Answer(s): C



Risk management should be initiated...

  1. when the Project Management Plan is initiated.
  2. at the time the Work Breakdown Structure is developed.
  3. at the start of the project.
  4. once the project concept is understood.

Answer(s): C



When are benefits usually realised when using an iterative life cycle?

  1. During the project
  2. Post project
  3. At project closure
  4. Both during and after the project

Answer(s): D



When is an analysis of a project's environment most likely to be undertaken?

  1. In the Definition Phase
  2. In the Transition Phase
  3. In the Concept Phase
  4. In the Deployment Phase

Answer(s): C



Which one of the following statements BEST defines procurement?

  1. A technique to establish the best approach for obtaining the resources for the project
  2. A group of interrelated resources and activities that transform inputs into outputs
  3. The description of the purpose, form and components to support delivery of a product
  4. The process by which products and services required for the project are acquired

Answer(s): D



Which of these is likely to occur if the scope is poorly defined?
1. Additional time spent in the concept phase
2. Scope creep
3. Budget over/under runs
4. Scheduling problems

  1. 1, 2 and 3
  2. 1, 2 and 4
  3. 1, 3 and 4
  4. 2, 3 and 4

Answer(s): D



Share your comments for APM APM-PFQ exam with other users:

U
unanimous
12/15/2023 6:38:00 AM

very nice very nice

A
akminocha
9/28/2023 10:36:00 AM

please help us with 1z0-1107-2 dumps

J
Jefi
9/4/2023 8:15:00 AM

please upload the practice questions

T
Thembelani
5/30/2023 2:45:00 AM

need this dumps

A
Abduraimov
4/19/2023 12:43:00 AM

preparing for this exam is overwhelming. you cannot pass without the help of these exam dumps.

P
Puneeth
10/5/2023 2:06:00 AM

new to this site but i feel it is good

A
Ashok Kumar
1/2/2024 6:53:00 AM

the correct answer to q8 is b. explanation since the mule app has a dependency, it is necessary to include project modules and dependencies to make sure the app will run successfully on the runtime on any other machine. source code of the component that the mule app is dependent of does not need to be included in the exported jar file, because the source code is not being used while executing an app. compiled code is being used instead.

M
Merry
7/30/2023 6:57:00 AM

good questions

V
VoiceofMidnight
12/17/2023 4:07:00 PM

Delayed the exam until December 29th.

U
Umar Ali
8/29/2023 2:59:00 PM

A and D are True

V
vel
8/28/2023 9:17:09 AM

good one with explanation

G
Gurdeep
1/18/2024 4:00:15 PM

This is one of the most useful study guides I have ever used.

AI Tutor 👋 I’m here to help!