Which of the following is not an output of a critical path analysis?

  1. Total and free float.
  2. Earliest start time and latest finish time of activities.
  3. Project completion time.
  4. Cost-benefit analysis.

Answer(s): D



A project manager would use a cost breakdown structure to produce:

  1. the cost of a do-nothing option.
  2. an analytical estimate.
  3. high-level project costs.
  4. a comparative estimate.

Answer(s): B



Which of the following is the correct sequence for the stages of a linear project life cycle?

  1. Deployment, Concept, Definition, Transition.
  2. Concept, Transition, Definition, Deployment.
  3. Concept, Definition, Deployment, Transition.
  4. Transition, Definition, Deployment, Concept

Answer(s): C



At which stage, in the Tuckman team development model, are team members clear and comfortable with their roles and responsibilities, and the project manager starts to see signs of the team working together?

  1. Storming.
  2. Forming.
  3. Norming.
  4. Performing

Answer(s): C



Which of the following is a definition of project management?

  1. A complex process of supervising and managing the delivery of any time-bound deliverable.
  2. Any change in management techniques in a company that achieves strategic objectives.
  3. The application of processes, methods, knowledge, skills and experience to achieve specific objectives for change.
  4. The coordination of several projects alongside business as usual.

Answer(s): C



Which of the following defines quality?

  1. The fitness for purpose of outputs and processes.
  2. The value for money of a product.
  3. The satisfaction of the stakeholders.
  4. The thoroughness of the management plan.

Answer(s): A



Quality control verifies that:

  1. the project follows appropriate processes.
  2. project outputs are delivered on time.
  3. the project follows appropriate governance.
  4. project outputs meet acceptance criteria.

Answer(s): D



The purpose of a decision gate is to decide whether:

  1. the response to a risk is valid.
  2. a project is viable in line with the business case.
  3. the project delivered against the success criteria.
  4. lessons were effectively learned during the project.

Answer(s): B



Viewing Page 9 of 53



Share your comments for APM APM-PFQ exam with other users:

Nicholas 2/2/2024 6:17:08 PM

Thank you for providing these questions. It helped me a lot with passing my exam.
Anonymous


Timi 8/19/2023 5:30:00 PM

my first attempt
UNITED KINGDOM


Blessious Phiri 8/13/2023 10:32:00 AM

very explainable
Anonymous


m7md ibrahim 5/26/2023 6:21:00 PM

i think answer of q 462 is variance analysis
Anonymous


Tehu 5/25/2023 12:25:00 PM

hi i need see questions
Anonymous


Ashfaq Nasir 1/17/2024 1:19:00 AM

best study material for exam
Anonymous


Roberto 11/27/2023 12:33:00 AM

very interesting repository
ITALY


Nale 9/18/2023 1:51:00 PM

american history 1
Anonymous


Tanvi 9/27/2023 4:02:00 AM

good level of questions
Anonymous


Boopathy 8/17/2023 1:03:00 AM

i need this dump kindly upload it
Anonymous


s_123 8/12/2023 4:28:00 PM

do we need c# coding to be az204 certified
Anonymous


Blessious Phiri 8/15/2023 3:38:00 PM

excellent topics covered
Anonymous


Manasa 12/5/2023 3:15:00 AM

are these really financial cloud questions and answers, seems these are basic admin question and answers
Anonymous


Not Robot 5/14/2023 5:33:00 PM

are these comments real
Anonymous


kriah 9/4/2023 10:44:00 PM

please upload the latest dumps
UNITED STATES


ed 12/17/2023 1:41:00 PM

a company runs its workloads on premises. the company wants to forecast the cost of running a large application on aws. which aws service or tool can the company use to obtain this information? pricing calculator ... the aws pricing calculator is primarily used for estimating future costs
UNITED STATES


Muru 12/29/2023 10:23:00 AM

looks interesting
Anonymous


Tech Lady 10/17/2023 12:36:00 PM

thanks! that’s amazing
Anonymous


Mike 8/20/2023 5:12:00 PM

the exam dumps are helping me get a solid foundation on the practical techniques and practices needed to be successful in the auditing world.
UNITED STATES


Nobody 9/18/2023 6:35:00 PM

q 14 should be dmz sever1 and notepad.exe why does note pad have a 443 connection
Anonymous


Muhammad Rawish Siddiqui 12/4/2023 12:17:00 PM

question # 108, correct answers are business growth and risk reduction.
SAUDI ARABIA


Emmah 7/29/2023 9:59:00 AM

are these valid chfi questions
KENYA


Mort 10/19/2023 7:09:00 PM

question: 162 should be dlp (b)
EUROPEAN UNION


Eknath 10/4/2023 1:21:00 AM

good exam questions
INDIA


Nizam 6/16/2023 7:29:00 AM

I have to say this is really close to real exam. Passed my exam with this.
EUROPEAN UNION


poran 11/20/2023 4:43:00 AM

good analytics question
Anonymous


Antony 11/23/2023 11:36:00 AM

this looks accurate
INDIA


Ethan 8/23/2023 12:52:00 AM

question 46, the answer should be data "virtualization" (not visualization).
Anonymous


nSiva 9/22/2023 5:58:00 AM

its useful.
UNITED STATES


Ranveer 7/26/2023 7:26:00 PM

Pass this exam 3 days ago. The PDF version and the Xengine App is quite useful.
SOUTH AFRICA


Sanjay 8/15/2023 10:22:00 AM

informative for me.
UNITED STATES


Tom 12/12/2023 8:53:00 PM

question 134s answer shoule be "dlp"
JAPAN


Alex 11/7/2023 11:02:00 AM

in 72 the answer must be [sys_user_has_role] table.
Anonymous


Finn 5/4/2023 10:21:00 PM

i appreciated the mix of multiple-choice and short answer questions. i passed my exam this morning.
IRLAND